U.S. NUCLFAR REGULATORY COMMISSION (
OFFICE OF INSPECTION AND ENFORCEMENT
REGION III
Report No. 50-263/77-23
,
Docket No. 50-263 License No. DPR-22 Licensee: Northern States Power Company 414 Nicollet Mall Minneapolis, MN 55401 Facility Name: Monticello Nuclear Generating Plant Inspection At: Monticello Site, Monticello, MN Inspection Conducted: November.28-30, 1977 Inspectors:
,G. 1/.
dker f
),
Ih4 JS
_[:2/,8!77
.
Ji C. Pulsiphe Approved By:
(.'
[
/
Nuclear Support Section Inspection _ Summary Inspection on November _28-30_,_1977 (Report No.__50-263/77-23)
_
_ Areas Inspected: Routine, unannounced inspection of plant operations following a refueling outage and startup testing during and following a refueling outage, the inspection involved 32 inspector-hours onsite by two NRC inspectors.
Results: No items of noncompliance or deviations were identified.
.
.
(
9102110424 771200 PDR ADOCK 05000263 G
. - - -.
.-.
- _ _.
r
I
\\
-
C (
DETAILS 1.
Persons Contacted
- L.
Eliason, Plant Manager
- W. Anderson, Superintendent, Operations and Maintenance
- M. Clarity, Superintendent, Plant Engineering and Radiation Protection
- W.
Sharnia, Plant Engineer. Technical
- S. Pearson, Operations Supervisor
- R. Ven Dell, Engineer
- D. Wagener. Engineer R. Goranson, Engineer (Surveillance Coordinator)
- Denotes those present at Exit interview.
2.
Review of Plant Operations The inspector verified that systems disturbed or tested during the refueling outage were returned to an operating status prior to plant startup, that control rod withdrawal sequence and rod withdrawal authorization were available and in effect prior to the startup af ter refueling, and that surveillance t est s were performed during the refueling outage as required by Technical Specifications.
The inspection reviewed Control Room Daily Logs for the dates November 1, 1977 through November 20, 1977, reviewed the Shift Supervisor's Log for the dates November 1,1977 through November 20, 1977, reviewed thirteen surveillances to ensure completion within Technical Specification periodicity (including Scram Insertion Timing, SBLC Explosion Charge Initiation, HPCI Simulated Automatic Initiation, Main Steam Isolation High Temperature, Refueling interlocks Test, Reactor Safety / Relief Valve Check, Turbine Stop Valve Closure Scram Test, ECCS Reactor Low Low Level Test, Peak Heat Flux Check, Turbine Control Valve Fast Closure Scram and Control Rod Drive Delta Pressure Testing), and reviewed the complete startup package (including all startup checks, valve lineup checks, and estimated critical position
'
calculations).
i No items of noncompliance or deviations were identified.
3.
_S_tartup Test ing - Refueling The inspector verified that startup testing was conducted in accord-ance with approved procedures and that the facility is being operated (
-2-
r
-
.
t
.s.
in conformance with NRC requirements and licensee procedures.
(
The inspector verified that the licensee conducted cont rol rod drive f riction and scram tests, control rod sequence and reactivity cheeks, core power distribution Ilmits checks, calibration of Local Power Range Monitors (LPRM's), Average Power Range Nonitors (APRM's) calibration, core thernal power evaluations, end determination of reactor shutdown margin.
The inspector reviewed procedures and test results for control rod drive friction and scram tests, LPRM calibrations, APRM calibrations, and shutdown margin determination and verified the tests were conducted in accordance with technically adequate procedures and in accordance with license limits.
No items of noncompliance or deviations were identified.
4.
Exit Interview The inspector met with licensee representatives (denoted in Paragraph 1) at the conclusion of the inspection on November 30, 1977, and summarized the scope and findings of this inspection.
/