IR 05000250/2025403

From kanterella
Jump to navigation Jump to search
Security Baseline Inspection Report 05000250/2025403 and 05000251/2025403
ML25352A287
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 12/19/2025
From: Jannette Worosilo
NRC/RGN-II/DFRSS/NSB
To: Coffey R
Florida Power & Light Co
References
IR 2025403
Download: ML25352A287 (0)


Text

SUBJECT:

TURKEY POINT NUCLEAR PLANT, UNIT 3 & 4 - SECURITY BASELINE INSPECTION REPORT 05000250/2025403 AND 05000251/2025403

Dear Robert Coffey:

On December 9, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Turkey Point Nuclear Plant, Unit 3 & 4 and discussed the results of this inspection with Charles Feldman and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jannette G. Worosilo, Chief Nuclear Security Branch Division of Fuels, Radiological Safety, and Security Docket Nos. 05000250 and 05000251 License Nos. DPR-31 and DPR-41

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000250 and 05000251

License Numbers:

DPR-31 and DPR-41

Report Numbers:

05000250/2025403 and 05000251/2025403

Enterprise Identifier:

I-2025-403-0013

Licensee:

Florida Power & Light Company

Facility:

Turkey Point Nuclear Plant, Unit 3 & 4

Location:

Homestead, FL

Inspection Dates:

December 08, 2025, to December 09, 2025

Inspectors:

L. Jones, Senior Reactor Inspector

Approved By:

Jannette G. Worosilo, Chief

Nuclear Security Branch

Division of Fuels, Radiological Safety, and Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Turkey Point Nuclear Plant, Unit 3

& 4, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.14 - Review of Power Reactor Target Sets

The inspectors evaluated the Security Target Set Program. The following elements were evaluated:

Review of Power Reactor Target Sets

(1) Section 03.01 Review of Events and Logs The inspector reviewed corrective action program entries since the last Target Set inspection that concern the target set identification, development, and maintenance program.

Section 03.02 Target Set Identification and Development Process Review The inspector assessed the licensee's documentation and maintenance of the process used to develop and identify complete and accurate target sets as required by 10 CFR Part 73 by reviewing applicable portions of procedures and samples of records and conducting interviews with responsible personnel and plant employees.

Section 03.03 Verification of Target Sets Changes The inspector reviewed changes to the licensees documented target sets since the last Target Set inspection. The inspector verified that any design modifications and procedure or configuration changes that have occurred were appropriately documented in the site's target sets.

Section 03.04 Verification of Complete and Accurate Target Sets The inspector interviewed licensee personnel and reviewed a sample of target sets for reactor operation and for modes other than operation. The inspector reviewed assumptions used in the licensees development of its target sets.

Section 03.05 Physical Protection Program Review The inspector verified that the licensee performed a review of target sets for accuracy, completeness, and applicability at least every 24 months and as otherwise required, documented the results and recommendations, and entered findings in the sites corrective action program (CAP).

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On December 9, 2025, the inspectors presented the security baseline inspection results to Charles Feldman and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71130.14

Procedures

SY-AA-102-1036

TARGET SET DEVELOPMENT, IDENTIFICATION AND

MAINTENANCE

REVISION 9