IR 05000237/2006005

From kanterella
(Redirected from IR 05000249/2006005)
Jump to navigation Jump to search
IR 05000237-06-005 (Drs); IR 05000249-06-005 (DRS) on 10/23/2006-10/27/2006 for Dresden Nuclear Power Station, Units 2 and 3; Baseline Physical Security Inspection; Access Control (71130.02); Owner-Controlled Area (71130.09)
ML063450392
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 12/07/2006
From: Kenneth Riemer
Division of Reactor Safety III
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-06-005
Download: ML063450392 (7)


Text

ber 7, 2006

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT NO. 05000237/2006005(DRS); 05000249/2006005(DRS)

Dear Mr. Crane:

On October 27, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a baseline security inspection of your Dresden Nuclear Power Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 27, 2006, with Mr. D. Bost, and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents two findings of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process). The deficiencies were promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspector left the site.

Exempt from Public Disclosure in accordance with 10 C.F.R.

2.390.

Exemption Number 5 Enclosure Contains .

Upon separation, this page is Decontrolled .

Name and Organization of person making determination:

K. Brooks, RIII/DRS/PSB Date of Determination 11/27/06 NRC is treating these violations as non-cited violations (NCVs) consistent with Section VI.A.1 of the NRC Enforcement Policy because of the very low security significance of these violations and because they are entered into your corrective action program. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region III, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Dresden Nuclear Power Station.

The findings were both NRC-identified and Licensee-identified.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, DAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not by made available electronically for public inspection in the NRC Public document room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Sincerely,

/RA/

Kenneth Riemer, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 Enclosure Contains .

Upon separation, this page is Decontrolled .

License Nos. DPR-19; DPR-25 Nonpublic Enclosure :

Inspection Report 05000237/2006005(DRS);

05000249/2006005(DRS)

w/Attachment: Supplemental Information See Attached Distribution NRC is treating these violations as non-cited violations (NCVs) consistent with Section VI.A.1 of the NRC Enforcement Policy because of the very low security significance of these violations and because they are entered into your corrective action program. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region III, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Dresden Nuclear Power Station.

The findings were both NRC-identified and Licensee-identified.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, DAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not by made available electronically for public inspection in the NRC Public document room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Sincerely,

/RA/

Kenneth Riemer, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Nonpublic Enclosure :

Inspection Report 05000237/2006005(DRS);

05000249/2006005(DRS)

w/Attachment: Supplemental Information See Attached Distribution Enclosure Contains .

Upon separation, this page is Decontrolled.

DOCUMENT NAME: C:\FileNet\ML063450392.wpd G Publicly Available xG Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME KBrooks:co MRing DFunk KRiemer DATE 12/06/06 12/07/06 12/07/06 12/07/06 OFFICIAL RECORD COPY cc w/encl :

B. Westreich, NSIR/DNS Licensing Assistant, NSIR/DNS/RSS V. Gengler, Dresden Site Security Manager State Liaison Officer, IL cc w/o encl :

Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Enclosure Contains .

Upon separation, this page is Decontrolled. ADAMS Distribution :

TEB JXH11 RidsNrrDirsIrib GEG KGO GLS DRC1 CAA1 LSL (electronic IRs only)

C. Pederson, DRS (hard copy - IRs only)

DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov Enclosure Contains .

Upon separation, this page is Decontrolled.