MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) IR 05000244/20220042023-01-31031 January 2023 LLC - Integrated Inspection Report 05000244/2022004 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 IR 05000244/20224202022-11-22022 November 2022 Security Baseline Inspection Report 05000244-2022420 Cover Letter IR 05000244/20220032022-11-0303 November 2022 LLC - Integrated Inspection Report 05000244/2022003 IR 05000244/20225012022-09-21021 September 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000244/2022501 IR 05000244/20220102022-09-13013 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000244/2022010 IR 05000244/20220052022-08-31031 August 2022 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2022005) IR 05000244/20224022022-08-0303 August 2022 Security Baseline Inspection Report 05000244/2022402 IR 05000244/20220022022-08-0303 August 2022 LLC - Integrated Inspection Report 05000244/2022002 ML22160A3962022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010 IR 05000244/20224032022-05-24024 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Cyber Security Inspection Report 05000244/2022403 (Cover Letter Only) IR 05000244/20220012022-05-0303 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2022001 IR 05000244/20224012022-03-0404 March 2022 LLC - Security Baseline Inspection Report 05000244/2022401 IR 05000244/20210062022-03-0202 March 2022 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2021006) IR 05000244/20210042022-01-20020 January 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2021004 IR 05000244/20220112021-12-16016 December 2021 R. E. Ginna Nuclear Power Plant, LLC - Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000244/2022011 IR 05000244/20210032021-11-0404 November 2021 Integrated Inspection Report 05000244/2021003 IR 05000244/20215012021-09-29029 September 2021 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2021501 IR 05000244/20210052021-09-0101 September 2021 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 IR 05000244/20210022021-08-0303 August 2021 LLC: Integrated Inspection Report 05000244/2021002 IR 05000244/20214012021-07-0202 July 2021 R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2021401 IR 05000244/20210102021-06-0707 June 2021 LLC: NRC Inspection Report 05000244/2021010 IR 05000244/20210012021-05-0505 May 2021 LLC: Integrated Inspection Report 05000244/2021001 IR 05000244/20210112021-04-27027 April 2021 LLC: Temporary Instruction 2515/194 Inspection Report 05000244/2021011 IR 05000244/20200032021-04-15015 April 2021 R. E. Ginna Nuclear Power Plant, LLC: Reissued Integrated Inspection Report 05000244/2020003 IR 05000244/20200062021-03-0303 March 2021 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020006) IR 05000244/20200132021-02-17017 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Design Basis Assurance Inspection (Programs) Inspection Report 05000244/2020013 IR 05000244/20200042021-02-0808 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Integrated Inspection Report 05000244/2020004 IR 07200067/20200022021-01-21021 January 2021 Independent Spent Fuel Storage Installation (ISFSI) NRC Inspection Report No. 07200067/2020002 IR 05000244/20203012020-12-0101 December 2020 R. E. Ginna Nuclear Power Plant, Initial Operator Licensing Examination Report 05000244/2020301 ML20315A3682020-11-10010 November 2020 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2020003 IR 05000244/20200052020-08-31031 August 2020 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020005) IR 05000244/20204022020-07-30030 July 2020 R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2020402 IR 05000244/20190102020-06-29029 June 2020 Revised Design Bases Assurance Inspection (Teams) Report 05000244/2019010 IR 05000244/20200012020-05-0606 May 2020 LLC: Integrated Inspection Report 05000244/2020001 and Independent Spent Fuel Storage Installation Report 07200067/2020001 IR 05000244/20200122020-04-0606 April 2020 LLC: Biennial Problem Identification and Resolution Inspection Report 05000244/2020012 IR 05000244/20190062020-03-0303 March 2020 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2019006) IR 05000244/20190042020-02-0505 February 2020 R.E Ginna Nuclear Power Plant, LLC: Integrated Inspection Report 05000244/2019004 IR 05000244/20194102019-11-21021 November 2019 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2019410 IR 05000244/20190032019-10-30030 October 2019 LLC - Integrated Inspection Report 05000244/2019003 2024-02-05
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Text
ber 26, 2017
SUBJECT:
R.E. GINNA NUCLEAR POWER PLANT, LLC - NRC EVALUATED EMERGENCY PREPAREDNESS EXERCISE - INSPECTION REPORT NO.
05000244/2017502
Dear Mr. Hanson:
On August 24, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the August 22, 2017, evaluated emergency preparedness exercise at your R.E. Ginna Nuclear Power Plant, LLC (Ginna). The enclosed inspection report documents the inspection results, which were discussed on August 24, 2017, with Mr. William Carsky, Site Vice President, and other members of the Ginna staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-244 License No. DPR-18
Enclosure:
Inspection Report 05000244/2017502 w/Attachment: Supplementary Information
REGION I==
Docket No: 50-244 License No: DPR-18 Report No: 05000244/2017502 Licensee: Exelon Generation Company, LLC Facility: R.E. Ginna Nuclear Power Plant, LLC Location: Ontario, New York Dates: August 21 - 24, 2017 Inspectors: J. Ambrosini, Sr. Emergency Preparedness Inspector, Division of Reactor Safety (DRS), Region I J. DeBoer, Emergency Preparedness Inspector, DRS, Region I P. Elkmann, Sr. Emergency Preparedness Inspector, DRS, Region IV B. Fuller, Senior Operations Inspector, DRS, Region I J. Lilliendahl, Senior Emergency Response Coordinator, DRS, Region I S. Obadina, Project Engineer, Division of Reactor Projects (DRP),
Region I (in training)
Approved By: Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
OF FI NDINGS
IR 05000244/2017502; 8/21/2017-8/24/2017; Exelon Generation Company, LLC; R.E. Ginna Nuclear Power Plant, LLC (Ginna); Exercise Evaluation, Exercise Evaluation - Scenario Review, Performance Indicator Verification.
This was an announced inspection conducted by six Region-based inspectors. No findings were identified during the inspection. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,
Revision 5.
Cornerstone: Emergency Preparedness
No findings were identified.
REPORT DETAILS
REACTOR SAFETY
Cornerstone: Emergency Preparedness
1EP1 Exercise Evaluation
Main article: IP 71114.01
a. Inspection Scope
On August 22, 2017, Exelon conducted a biennial emergency preparedness exercise at the R.E. Ginna Nuclear Power Plant. The NRC inspectors evaluated the adequacy of the licensees conduct of the exercise and its capability to assess the Exelon staffs performance via a formal critique process, as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.47(b)(14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The exercise evaluation consisted of the following review and assessment:
- The adequacy of Exelons performance in the biennial full-participation exercise regarding the implementation of the planning standards described in 10 CFR 50.47(b)(4), (5), (9), and (10), which are: emergency classification, offsite notification, radiological assessment, and, onsite protective actions and public protective action recommendations, respectively.
- The overall adequacy of Exelons emergency response facilities with regard to Ginna Emergency Plan commitments. The facilities assessed were the Control Room Simulator, the Technical Support Center, the Operations Support Center, and the Emergency Operations Facility.
- A review of other performance areas, such as: the licensee emergency response organizations (ERO) recognition of abnormal plant conditions, command and control, intra- and inter-facility communications, prioritization of mitigating activities, utilization of repair and field monitoring teams, interface with offsite agencies, staffing and procedure adequacy, and, the overall implementation of the Ginna Emergency Plan and its implementing procedures.
- A review of past performance issues from the last NRC Ginna exercise inspection report and Exelons emergency preparedness drill reports, to determine the effectiveness of licensee corrective actions as demonstrated during the August 22, 2017, exercise and to ensure compliance with 10 CFR 50.47(b)(14).
- The licensees post-exercise critiques, to evaluate Exelons self-assessment of its ERO performance during the August 22, 2017, exercise and to ensure compliance with 10 CFR Part 50, Appendix E, Section IV.F.2.g.
Documents reviewed for each section of this inspection report are listed in the
.
b. Findings
No findings were identified.
1EP8 Exercise Evaluation - Scenario Review
Main article: IP 71114.08
a. Inspection Scope
Prior to the August 22, 2017, emergency preparedness exercise, the NRC inspectors conducted an in-office review of the exercise objectives and scenario, which Exelon had submitted to the NRC, to determine if the exercise would test major elements of the Ginna Emergency Plan as required by 10 CFR 50.47(b)(14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
b. Findings
No findings were identified.
OTHER ACTIVITIES (OA)
4OA1 Performance Indicator Verification (71151 - 3 Samples)
a. Inspection Scope
The inspectors reviewed data for the Ginna Emergency Preparedness performance indicators, which are:
- (1) Drill and Exercise Performance,
- (2) ERO Drill Participation, and,
- (3) Alert and Notification System Reliability. The last emergency preparedness inspection at Ginna was conducted in the third calendar quarter of 2016, so the inspectors reviewed supporting documentation from emergency preparedness drills and tests from the third calendar quarter of 2016 through the second calendar quarter of 2017, to verify the accuracy of the reported performance indicator data. The review of these performance indicators was conducted in accordance with NRC Inspection Procedure 71151, using the acceptance criteria documented in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guidelines, Revision 7.
This inspection activity represented the completion of three samples.
b. Findings
No findings were identified.
4OA6 Meetings, including Exit
On August 24, 2017, the inspectors presented the results of this inspection to Mr. W. Carsky, Site Vice President, and other members of the Exelon staff. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.
ATTACHMENT
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- W. Carsky, Site Vice President
- V. Cwietniewicz, Exelon Mid-Atlantic Emergency Planning Manager
- J. Jackson, Ginna Emergency Planning Manager
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
None.