November 28, 2007
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3
NRC SECURITY BASELINE INSPECTION REPORT 05000237/2007402(DRS);
Dear Mr. Pardee:
On October 16, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Dresden Nuclear Power Station, Units 2 and 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 16, 2007, with Mr. D. Wozniak and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings of significance were identified.
EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)
Exemption number: 5___________
Nuclear Regulatory Commission review required before public release.
Joseph Maynen, RIII/DRS/PSB___________
Name and organization of person making determination.
Date of determination: 11/02/2007______
Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety
Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Nonpublic Enclosure: Inspection Report 05000237/2007402(DRS);
w/Attachment: Supplemental Information
cc w/encl:
D. Riffle, NSIR/DSO/DDSO
D. Combs, Braidwood Security Manager
State Liaison Officer, State of Illinois
DISTRIBUTION See next page Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled.