IR 05000016/2025001

From kanterella
Jump to navigation Jump to search
Enrico Fermi Atomic Power Plant, Unit 1 - NRC Inspection Report No. 05000016/2025001
ML25190A440
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 07/09/2025
From: Dave Hills
NRC/RGN-III
To: Peter Dietrich
DTE Electric Company, Detroit Edison, Co
References
IR 2025001
Download: ML25190A440 (1)


Text

SUBJECT:

ENRICO FERMI ATOMIC POWER PLANT, UNIT 1 - NRC INSPECTION REPORT NO. 050-00016/2025-001 (DRSS)

Dear Pete Dietrich:

On June 24, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Enrico Fermi Atomic Power Plant, Unit 1 (Fermi 1). On June 24, 2025, the NRC inspectors discussed the results of this inspection with Mike Ciko, Director, Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

During the inspection period, the NRC inspector reviewed the following aspects of onsite activities: safety reviews, design changes and modifications; problem identification and resolution; fire protection; decommissioning performance; occupational radiation exposure; radiological surveys; radioactive waste treatment, effluent, and environmental monitoring; and waste management and transportation. The inspection consisted of an examination of activities at the site as they relate to safety and compliance with the Commissions rules and regulations.

No violations of more than minor safety significance were identified during this inspection.

July 9, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, David E. Hills, Chief Decommissioning, Reactor, and ISFSI HP Branch Division of Radiological Safety and Security Docket No.50-016 License No. DPR-9

Enclosure:

IR No. 05000016/2025001

Inspection Report

Docket No:

50-016

License No:

DPR-9

Report No:

05000016/2025001(DRSS)

Licensee:

DTE Electric Company

Facility:

Enrico Fermi Atomic Power Plant, Unit 1

Location:

Newport, MI

Dates:

October 8, 2024, to June 24, 2025

Inspector:

Peter J Lee, Reactor Inspector (Decom), Ph.D., CHP

Approved by:

David E. Hills, Chief

Decommissioning, Reactor, ISFSI HP Branch

Division of Radiological Safety and Security

EXECUTIVE SUMMARY

Enrico Fermi Atomic Power plant, Unit 1

NRC Inspection Report Nos. 05000016/2025001(DRSS)

This U.S. Nuclear Regulatory Commission (NRC) inspection was a routine, announced

inspection of decommissioning activities being conducted at the facility. A brief summary of the

areas reviewed are described below. Based on the results of the inspection no violations of

more than minor safety significance were identified.

Safety Reviews, Design Changes, and Modifications

The inspector determined that licensee had not performed any design changes that

warranted a safety evaluation per Title 10 of the Code of Federal Regulations

(CFR) 50.59.

Problem Identification and Resolution

Issues were identified by the licensee at appropriate thresholds and entered into the

Corrective Action Program (CAP). Issues were screened and prioritized commensurate

with safety significance. Licensee evaluations determined the significance of issues and

included appropriate remedial corrective actions.

Fire Protection Program at Permanently Shutdown Reactors

The program is inspected by the NRC through the Reactor Oversight Process (ROP) for

Unit 2.

Decommissioning Performance and Status Review

The inspectors determined that decommissioning activities were in accordance with the

regulations and license requirements.

Occupational Radiation Exposure

The inspector determined that the licensee had not conducted any radiological work that

resulted in worker exposures this past year.

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

The liquid and gaseous effluent sampling program was effective at quantifying

radioactive effluent releases and the Radiological Environmental Monitoring Program

(REMP) and Groundwater Protection Initiative (GPI) were implemented in accordance

with applicable procedures.

Solid Radioactive Waste Management and Transportation of Radioactive Materials

The licensee effectively processed, handled, stored, and transported radioactive

material.

Report Details

Summary of Facility Status

Enrico Fermi Atomic Power Plant, Unit 1 (FERMI 1) is a permanently shut-down and defueled

power reactor maintained in a Safe Storage (SAFSTOR) condition. During this inspection

period, the licensee continued to maintain Fermi 1 in a passive monitoring SAFSTOR status;

therefore, no physical decommissioning activities have been conducted. Since the last NRC

inspection of Fermi 1, the licensee continued to conduct the technical specification monitoring

surveillances, removal of standing water from the facility, and the groundwater monitoring. This

facility is co-located with an operating reactor; thus, inspection activities were focused on

program elements not assessed under the reactor oversight process for the operating unit.

1.0

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown

Reactors (IP 37801)

1.1

Inspection Scope

The purpose of this portion of the inspection was to verify that the licensees safety

review process was in accordance with the requirements of 10 CFR 50.59,

Changes, tests, and experiments such that license amendments were obtained when

required.

1.2

Observations and Findings

During the inspection, the inspector confirmed there were no changes to the

decommissioning facility that required a safety evaluation according to the provisions of

10 CFR 50.59.

No findings of significance were identified.

1.3

Conclusions

The licensee had not performed any design changes that warranted a safety evaluation

per 10 CFR 50.59.

2.0

Problem Identification and Resolution at Permanently Shutdown Reactors

(IP 40801)

2.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate 1) the effectiveness of

licensee controls to identify, resolve, and correct issues, 2) the audit and assessment

program, and 3) management reviews of the safety conscious work environment.

2.2

Observations and Findings

The inspector reviewed all issues the licensee entered into the CAP since the last

inspection. The inspector reviewed the licensees audit of its semi-annual technical

specification monitoring surveillances, Audit 25-0104 conducted from May 19, 2025,

through June 02, 2025. Selected corrective action work orders associated with identified

deficiencies were also reviewed. The technical specification monitoring surveillances

included weekly and monthly facility inspections, and quarterly radiation surveys. The

audits of technical specification monitoring surveillances were appropriately focused in

both scope and level of detail, and the licensee initiated appropriate corrective actions to

resolve the audit findings.

No findings of significance were identified.

2.3

Conclusions

Issues were identified by the licensee at appropriate thresholds and entered into the

CAP. Issues were screened and prioritized commensurate with safety significance.

Licensee evaluations determined the significance of issues and included appropriate

remedial corrective actions.

3.0

Fire Protection Program at Permanently Shutdown Reactors (IP 64704)

3.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate the effectiveness of the fire

protection program to ensure adequate protection from fire-induced release of

radioactive material.

3.2

Observations and Findings

The fire protection program was inspected by the NRCs Reactor Oversight Process

(ROP). The licensees fire protection program is documented in the Fermi Integrated

Inspection Report (ADAMS Accession Number ML23244A212).

No findings of significance were identified.

3.3

Conclusions

This program is inspected by the NRC through the ROP for Unit 2.

4.0

Decommissioning Performance and Status Review (IP 71801)

4.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate the status of

decommissioning and to verify the decommissioning activities are in accordance with

regulatory and license requirements.

4.2

Observations and Findings

The inspector performed walkdowns, reviewed documents, and interviewed plant

personnel to assess the licensees performance in the following areas:

Weekly and monthly facility inspection, and quarterly radiation surveillance;

The postings and boundaries for contamination control; and

Control of the final status survey areas.

The general condition of the facility was found to be well maintained and consistent with

good housekeeping practices. The postings and boundaries for contamination control

were well maintained. Final status survey (FSS) areas were adequately isolated and

posted. There were no unexpected radiation readings detected. The radiation readings

were consistent with the measurements taken to support the licensees return of Fermi 1

in early 2012 from active decommissioning to a passive monitoring SAFSTOR status

(ADAMS Accession Number ML12090A151).

The only standing water left was in the sumps of the Fuel and Repair Building (FARB)

maintenance pit. As described in Section 6.2, the licensee had pumped the water to the

sanitary sewer system due to no detectable licensed materials identified.

No findings of significance were identified.

4.3

Conclusions

The inspectors determined that decommissioning activities were in accordance with the

regulations and license requirements.

5.0

Occupational Radiation Exposure at Permanently Shutdown Reactors (IP 83750)

5.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate the effectiveness of the

licensees occupational radiation safety program to adequately protect worker health and

safety from exposure to radiation or radioactive material.

5.2

Observations and Findings

Based on the discussion with the licensee, there was no radiological work associated

with worker exposures this past year.

No findings of significance were identified.

5.3

Conclusions

The inspector determined that the licensee had not conducted any radiological work that

resulted in worker exposures this past year.

6.0

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

(IP 84750)

6.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate the effectiveness of the

licensees liquid and gaseous effluent sampling program to quantify radioactive effluent

releases and to verify that the radiological environmental monitoring program and

groundwater protection initiative were effectively implemented.

6.2

Observations and Findings

The inspector performed walkdowns, reviewed documents, and interviewed plant

personnel to assess the licensees performance in the following areas:

Analyses of ground water from Fermi1 active sumps;

Analyses of ground water from Fermi1 monitoring wells; and

Analyses of water recirculated through filter from the hot sump and from

maintenance pits.

As noted in Sections 4.2, the licensee had removed the standing water from the FARB

maintenance pit sumps, pumping it into the sanitary sewer system. The inspector

reviewed analytical sampling results associated with those releases, as well as those

from active sumps and determined that no licensed materials were released. Fermi 1

active sumps were sampled semi-annually in accordance with Surveillance Performance

Form, Event FI 98. The inspector also reviewed the groundwater analytical sampling

results from monitoring wells. Based on the review of the analytical sampling results, the

inspector determined that only natural occurring radioactive materials were identified.

The licensee had recirculated the water from the hot sump through filters until no

licensed materials were identified and then discharged water from the hot sump to the

maintenance pit sumps in the FARB. The inspector reviewed the sampling results and

determined that no licensed materials were identified in the water of the hot sump. The

licensee also had recirculated the water from the maintenance pits through filters until no

licensed materials were identified and then discharged it into the sanitary sewer system.

No findings of significance were identified.

6.3

Conclusions

The liquid and gaseous effluent sampling program was effective at quantifying

radioactive effluent releases and the Radiological Environmental Monitoring Program

(REMP) and Groundwater Protection Initiative (GPI) were implemented in accordance

with applicable procedures.

7.0

Solid Radioactive Waste Management and Transportation of Radioactive Materials

(IP 86750)

7.1

Inspection Scope

The purpose of this portion of the inspection was to evaluate the effectiveness of the

licensees programs for processing, handling, storage, and transportation of radioactive

material.

7.2

Observations and Findings

During the inspection, the inspector found that radioactive material was controlled in

accordance with requirements. The inspector interviewed plant personnel and

determined that no shipments of radioactive material occurred since the last inspection.

No findings of significance were identified.

7.3

Conclusions

The licensee effectively processed, handled, stored, and transported radioactive

material.

8.0

Exit Meeting

The inspector presented the inspection results to Mike Ciko and the other members of

the Fermi1 staff at the conclusion of the inspection on June 24, 2025. The licensee

acknowledged the results presented and did not identify any of the information

discussed as proprietary.

ATTACHMENT: SUPPLEMENTAL INFORMATION

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

  • Mike Ciko - Director, Operations
  • Kelly Belenky - Asst. Manager, Operations
  • Patrick McMahon - Supervisor, Nuclear Fire Marshal and Operations Support
  • Eric Frank - Manager, Nuclear Licensing
  • Roxanne Vonhabsburg - Supervisor, Licensing
  • Bruce Rumans - General Supervisor, RP
  • Greg Anderson - Licensing
  • Present at the June 24, 2025, exit meeting.

INSPECTION PROCEDURES (IPs) USED

IP 37801

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown

Reactors

IP 40801

Self-Assessment, Auditing, and Corrective Action at Permanently Shutdown

Reactors

IP 64704

Fire Protection Program at Permanently Shutdown Reactors

IP 71801

Decommissioning Performance and Status Reviews at Permanently Shutdown

Plants

IP 83750

Occupational Radiation Exposure

IP 84750

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

IP 86750

Solid Radioactive Waste Management and Transportation of Radioactive

Materials

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

Type

Summary

None

Closed

Type

Summary

None

DOCUMENTS REVIEWED

Licensee documents reviewed and utilized during the course of this inspection are specifically

identified in the Report Details

LIST OF ACRONYMS USED

ADAMS

Agencywide Document Access and Management System

CAP

Corrective Action Program

CFR

Code of Federal Regulations

DRSS

Division of Nuclear Radiological Safety and Security

FSS

Final Status Survey

FARB

Fuel and Repair Building

GPI

Groundwater Protection Initiative

IP

Inspection Procedure

NRC

U.S. Nuclear Regulatory Commission

REMP

Radiological Environmental Monitoring Program

SAFSTOR

Safe Storage

TS

Technical Specification