MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments GO2-22-110, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor2022-10-17017 October 2022 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor GO2-22-096, Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-10-0404 October 2022 Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-085, Docket No. 50-397, Evacuation Time Estimate Analysis2022-08-30030 August 2022 Docket No. 50-397, Evacuation Time Estimate Analysis GO2-22-075, Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves2022-07-11011 July 2022 Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves GO2-22-072, Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing2022-07-11011 July 2022 Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process GO2-22-062, Registration of Spent Fuel Cask Use2022-05-19019 May 2022 Registration of Spent Fuel Cask Use GO2-22-049, Supplement to Licensing Amendment Request to Adopt 10CFR50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Rectors2022-05-10010 May 2022 Supplement to Licensing Amendment Request to Adopt 10CFR50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Rectors GO2-22-054, Independent Spent Fuel Storage Installation, 2021 Annual Radiological Environmental Operating Report2022-05-0909 May 2022 Independent Spent Fuel Storage Installation, 2021 Annual Radiological Environmental Operating Report GO2-22-056, Registration of Spent Fuel Cask Use2022-04-21021 April 2022 Registration of Spent Fuel Cask Use GO2-22-055, 2021 Annual Environmental Operating Report2022-04-20020 April 2022 2021 Annual Environmental Operating Report GO2-22-048, 2021 Annual Radioactive Effluent Release Report2022-04-15015 April 2022 2021 Annual Radioactive Effluent Release Report GO2-22-045, Registration of Spent Fuel Cask Use2022-04-0606 April 2022 Registration of Spent Fuel Cask Use GO2-22-044, Level of Financial Protection - Annual Reporting Requirement2022-03-21021 March 2022 Level of Financial Protection - Annual Reporting Requirement GO2-22-038, Docket No. 50-397, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462022-03-0909 March 2022 Docket No. 50-397, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-22-031, Response to Audit Plan and Online Reference Portal Request2022-02-15015 February 2022 Response to Audit Plan and Online Reference Portal Request GO2-22-011, Docket No. 72-35; Independent Spent Fuel Storage Installation, 2021 Annual Effluent Release Report2022-02-0808 February 2022 Docket No. 72-35; Independent Spent Fuel Storage Installation, 2021 Annual Effluent Release Report GO2-22-001, License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-02-0303 February 2022 License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-012, Independent Spent Fuel Storage Installation - Biennial 50.59/72.48 Report2022-01-24024 January 2022 Independent Spent Fuel Storage Installation - Biennial 50.59/72.48 Report 2024-01-08
[Table view] Category:License-Fitness for Duty (FFD) Performance Report
MONTHYEARML23054A3672023-02-23023 February 2023 Single Positive Test Form Collected on 05/02/2022 ML23054A3712023-02-23023 February 2023 Single Positive Test Form Collected on 10/24/2022 ML23054A3652023-02-23023 February 2023 Single Positive Test Form Collected on 02/07/2022 ML23054A3662023-02-23023 February 2023 Single Positive Test Form Collected on 03/08/2022 ML23054A3702023-02-23023 February 2023 Single Positive Test Form Collected on 06/28/2022 ML23054A3762023-02-23023 February 2023 Annual Fatigue Report Form for 2022 ML23054A3682023-02-23023 February 2023 Single Positive Test Form Collected on 05/02/2022 ML23054A3752023-02-23023 February 2023 Annual Report Form for Drug and Alcohol Tests for 2022 ML23054A3692023-02-23023 February 2023 Single Positive Test Form Collected on 06/06/2022 ML23054A3742023-02-23023 February 2023 Single Positive Test Form Collected on 11/01/2022 ML23054A3722023-02-23023 February 2023 Single Positive Test Form Collected on 10/31/2022 ML22055B1862022-02-24024 February 2022 Single Positive Test Form Collected on 04/15/2021 ML22055B1942022-02-24024 February 2022 Single Positive Test Form Collected on 05/11/2021 ML22055B1842022-02-24024 February 2022 Single Positive Test Form Collected on 04/06/2021 ML22055B1782022-02-24024 February 2022 Single Positive Test Form Collected on 02/09/2021 ML22055B1802022-02-24024 February 2022 Single Positive Test Form Collected on 03/11/2021 ML22055B1832022-02-24024 February 2022 Single Positive Test Form Collected on 03/30/2021 ML22055B1882022-02-24024 February 2022 Single Positive Test Form Collected on 04/19/2021 ML22055B1822022-02-24024 February 2022 Single Positive Test Form Collected on 03/23/2021 ML22055B1812022-02-24024 February 2022 Single Positive Test Form Collected on 03/22/2021 ML22055B1872022-02-24024 February 2022 Single Positive Test Form Collected on 04/19/2021 ML22055B1792022-02-24024 February 2022 Single Positive Test Form Collected on 03/08/2021 ML22055B1852022-02-24024 February 2022 Single Positive Test Form Collected on 04/12/2021 ML22055B1912022-02-24024 February 2022 Single Positive Test Form Collected on 04/22/2021 ML22055B1902022-02-24024 February 2022 Single Positive Test Form Collected on 04/22/2021 ML22055B1972022-02-24024 February 2022 Annual Fatigue Report Form for 2021 ML22055B1952022-02-24024 February 2022 Single Positive Test Form Collected on 05/17/2021 ML22055B1892022-02-24024 February 2022 Single Positive Test Form Collected on 04/19/2021 ML22055B1932022-02-24024 February 2022 Single Positive Test Form Collected on 05/05/2021 ML22055B1922022-02-24024 February 2022 Single Positive Test Form Collected on 04/26/2021 ML22055B1962022-02-24024 February 2022 Annual Report Form for Drug and Alcohol Tests for 2021 ML21042B9172021-02-11011 February 2021 Single Positive Test Form Collected on 4/1/2020 ML21042B9182021-02-11011 February 2021 Single Positive Test Form Collected on 05/27/2020 ML21042B9162021-02-11011 February 2021 Annual Fatigue Report Form for 2020 ML21042B9192021-02-11011 February 2021 Single Positive Test Form Collected on 07/27/2020 ML21042B9152021-02-11011 February 2021 Annual Report Form for Drug and Alcohol Tests for 2020 ML21042B9212021-02-11011 February 2021 Single Positive Test Form Collected on 10/05/2020 ML21042B9202021-02-11011 February 2021 Single Positive Test Form Collected on 08/31/2020 ML20098F2652020-04-0707 April 2020 Licensed Operator Positive Fitness-For-Duty Test ML20044D9922020-02-13013 February 2020 Single Positive Test Form Collected on 11/13/2019 ML20044D9762020-02-13013 February 2020 Annual Fatigue Report Form for 2019 ML20044D9822020-02-13013 February 2020 Single Positive Test Form Collected on 04/02/2019 ML20044D9742020-02-13013 February 2020 Annual Report Form for Drug and Alcohol Tests for 2019 ML20044D9862020-02-13013 February 2020 Single Positive Test Form Collected on 05/02/2019 ML20044D9882020-02-13013 February 2020 Single Positive Test Form Collected on 05/08/2019 ML20044D9812020-02-13013 February 2020 Single Positive Test Form Collected on 04/01/2019 ML20044D9832020-02-13013 February 2020 Single Positive Test Form Collected on 04/17/2019 ML20044D9892020-02-13013 February 2020 Single Positive Test Form Collected on 05/16/2019 ML20044D9852020-02-13013 February 2020 Single Positive Test Form Collected on 04/24/2019 ML20044D9912020-02-13013 February 2020 Single Positive Test Form Collected on 06/11/2019 2023-02-23
[Table view] |
Text
r 7
-IDale A
EVice ENERGY K. Atkinson President, Operational Support RichaO. Box 968, P0 Richland, WA 99352-0968 NTEPh. 509.377.4302 F. 509.377.4098 dkatkinson @energy-northwest.com February 26, 2010 G02-10-034 10 CFR 26.717 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 FITNESS FOR DUTY ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009
Dear Sir or Madam:
Pursuant to 10 CFR 26.717, attached is the Energy Northwest Fitness for Duty (FFD)
Annual Performance Data Report for January 1 to December 31, 2009 without subpart I.
The Fitness for Duty Performance Data for fatigue and work hours as required by Part 26, Subpart I, 26.203 will be submitted separately. The data submitted in this report has been analyzed. No program weakness was identified during this reporting period. There are no commitments being made to the NRC by this letter.
Should you have any questions or desire additional information regarding this matter, please call CR Forrester, Manager, Nuclear Security at (509) 377-2290.
Respectfully, D.K. Atkinson Vice President, Operational Support
Attachment:
Fitness for Duty Annual Performance Data Report January 1 to December 31, 2009 cc: NRC Region IV Administrator NRC NRR Project Manager NRC Sr. Resident Inspector/988C RN Sherman -.BPN1399 WA Horin- Winston & Strawn AV -
Ni 1-
FITNESS FOR DUTY ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 1 of 6 Personnel Subject to 10 CFR 26 Energy Northwest December 31, 2009 Company 12 months ending Columbia Generating Station Location Chuck Forrester, Manager, Nuclear Security (509) 377-2290 Contact Name Phone Cutoffs: Screen/Confirmation (nq/ml)
Marijuana 50/15 Amphetamines 1000/500 Cocaine 300/150 Phencyclidine 25/25 Opiates 2000/2000 Alcohol (%BAC) 0.04%
Testing Results Licensee ContractorsNendors Employees Average Number with Unescorted 1171 493 Access: 1664 Categories # Tested # Positive # Tested # Positive Pre-Access 388 5 1669 12 For-Cause Post-Accident For-Cause 23 2 9 0 Observed Behavior Random 774 6 290 3 Follow-Up 42 1 5 0 Other 0 0 0 0 Return to Duty 7 0 2 0 Total 1241 14 1977 15
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 2 of 6 Breakdown of Confirmed Positive Tests for Specific Substances Tampering THC COCAINE OPIATES AMPHETAMINES PCP ALCOHOL REFUSED by Substitution Licensee Empeoyee 6 0 0 0 0 7 0 1 Employees Contractors/ 2 2 0 1 0 1 1 Vendors 8 Total 14 2 0 1 0 8 1 3 Refusal to test and tampering by substitution results are counted as positive in the testing results matrix.
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 3 of 7 FITNESS FOR DUTY PROGRAM
SUMMARY
During the reporting period January 1 to December 31, 2009, the number of random tests performed was equivalent to the number required to test at an annual rate equal to at least 50 percent of the unescorted access population. The annual rate of positive results from random testing for the calendar year 2009 was 0.838 percent.
POSITIVE RESULTS There were twenty-nine positive test results reported during 2009. Calculated from the positives recorded from January 1, 1990 until December 31, 2009, marijuana is the drug of preference, accounting for 60 percent of all the positive results; cocaine is second, yielding 16 percent of all the positive results.
MANAGEMENT ACTIONS Pre-Access Testing There were seventeen pre-access positive test results during this reporting period.
Access to Energy Northwest property was denied for five licensee employee applicants and twelve contractor/vendor employee applicants. Management was notified and the individual's files were annotated regarding the test results, access denial and management's actions.
One licensee employee applicant and one contractor/vendor employee applicant were confirmed as providing a substituted sample. The two individual's were permanently denied access at Energy Northwest. Management was notified and the individual's files were annotated regarding the permanent denial. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
Random Testing There were nine positive random test results during this reporting period.
Access was denied to Energy Northwest property for a minimum of fourteen days and referral to the Employee Assistance Program (EAP) for six licensee employees and three contractor/vendor employees. Management was notified and the individual's files were annotated regarding the test results, access denial and management action.
One contractor/vendor employee was confirmed as tampering with a sample by substitution for the random collection. The individual was permanently denied access at Energy Northwest. Management was notified and the individual's file was annotated regarding the permanent denial. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 4 of 7 At the time of the random failure by providing a substituted sample, the individual was employed as a foreman and as such had supervisory duties. This resulted in a Plant Event Report to NRC.
Follow-Up Testing There was one positive follow-up test result during this reporting period.
Access was denied to Energy Northwest property for a minimum of five years.
Management was notified and the individual's file was annotated regarding the test results, access denial and management action. The five year denial information was recorded in the Personnel Access Data System (PADS) as required.
Presently, there are four Energy Northwest employees participating in the follow-up program.
For-Cause/Observable Behavior Testing There were thirty-two for-cause tests administered due to observable behavior; twenty-three licensee employees and nine contractor/vendor employees were tested during this reporting period. Of the thirty-two for-cause tests for observable behavior thirty tested negative and two tested positive. One of the two positive test results was reported to the NRC as a Plant Event report due to the individual's required supervisory duties.
The for-cause/observable behavior tests were administered after the following incidents:
- An Energy Northwest employee sustained a lost time knee injury while walking up a flight of stairs.
- An Energy Northwest employee sustained a recordable injury receiving medical treatment heat illness.
" Two Energy Northwest employees were observed as inattentive to duties.
- An Energy Northwest employee sustained a recordable injury due to a slip and fall.
- An Energy Northwest employee sustained a recordable injury due a splash in the eye.
- An Energy Northwest employee participated in a human performance issue of an unauthorized entry.
- Three Energy Northwest employees engaged in a compensatory measure procedure violation.
- Three contractor vendor employees were involved in an incident of a one inch sling failing when tensioned.
- Two contractor/vendor employees were involved in an incident of a channel lifting hoist rope parting.
- An Energy Northwest employee sustained a recordable knee injury while accessing the IDC's main gate.
- An Energy Northwest employee sustained a first aid injury in falling over boxes in a hallway.
- Two Energy Northwest employees were involved in a valve mis-position event.
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 5 of 7
- An Energy Northwest employee sustained a recordable and lost time injury when a fork came off a fork lift.
" An Energy Northwest employee reported to post without required equipment.
" A contractor/vendor employee was observed engaging in unusual behavior.
" A contractor/vendor employee sustained a recordable injury laceration requiring stitches.
- Two Energy Northwest employees were observed exhibiting a strong odor of alcohol.
- Two Energy Northwest employees were involved in circuit breaker E-CB 8/3 faceplate bent while racking.
- Two contractor vendor employees were observed as E-C1 -7 fused disconnect was inadvertently opened.
" An Energy Northwest employee sustained a recordable knee injury by falling.
" An Energy Northwest employee sustained a recordable wrist injury opening a Bullet Resistant Enclosure door.
" An Energy Northwest employee sustained a recordable injury requiring stitches to the hand after falling in the parking lot.
For-Cause/Post Accident Testing There were nine for-cause/post-accident tests administered during this reporting period.
Seven licensee employee and two contractor/vendor employees were tested for cause/post-accident/near miss. All nine tests for-cause/post accident/near misses tested negative.
The for-cause/post-accident test was administered after the following incidents:
- An Energy Northwest employee while driving a company vehicle made a sharp turn and struck a concrete manhole cover.
- An Energy Northwest employee dropped a fire pump from a forklift.
- Two contractor/vendor employees were involved in an access road traffic accident.
- Two Energy Northwest employees were involved in a vehicle accident while exiting the vehicle trap leaving the site.
" An Energy Northwest employee while maneuvering a box truck turned too close to a building damaging the truck.
- An Energy Northwest employee backed a company vehicle into a yield sign.
" An Energy Northwest employee operating a company vehicle struck a jersey barrier.
No personal injuries were sustained as a result of the vehicle accidents or the near miss accidents.
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 6 of 7 Return to Duty Testing There were nine Return to Duty tests administered during this reporting period. Return to Duty testing is administered following a Fitness for Duty failure as part of the reentry process when applying for unescorted access.
Sample Tampering by Substitution and Refusal to Test There were three attempts at tampering and one refusal to test during this reporting period.
One licensee employee applicant and one contractor/vendor employee applicant were confirmed by the Medical Review Officer as tampering with the collection by providing substituted samples. One contractor provided a low out of range sample temperature at 87°F on a pre-access test. One licensee employee applicant provided a high out of range sample temperature at 103'F. Both individuals remained in the collection facility and did provide samples under observed conditions. Both were permanently denied access at Energy Northwest. Management was notified and the individual's files were annotated regarding the permanent denial. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
One contractor/vendor employee was confirmed as tampering with a random sample by substitution. The individual provided a high out of range sample temperature at 105'F.
The individual remained in the collection facility and did provide another sample under observed conditions. At the time of the random failure and confirmed tampering by substitution, the individual was employed as a foreman and as such had supervisory duties. This resulted in a Plant Event Report to NRC. This contractor employee was permanently denied access at Energy Northwest. Management was notified and the individual's file was annotated regarding the permanent dentil. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
One contractor/vendor employee applicant refused to provide a urine sample during a pre-access test. The individual did understand the ramifications of refusing to provide a urine sample and continued to refuse and subsequently choose to leave the collection facility.
The contractor/vendor was permanently denied access at Energy Northwest.
Management was notified and the individual's files were annotated regarding the permanent denial. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
ADMINISTRATIVE ACTIONS There were no administrative actions taken during this reporting period.
FITNESS FOR DUTY SEMI-ANNUAL PERFORMANCE DATA REPORT JANUARY 1 TO DECEMBER 31, 2009 Attachment Page 7 of 7 EVENTS REPORTED TO THE NRC During this reporting period, there were two Fitness for Duty events that were reportable in 2009 in accordance with 10 CFR 26.719.
The first was a contractor/vendor employee was confirmed as tampering by sample substitution for a random collection as reported under both the random section and the sample tampering by substitution sections of this report. The substitution was discovered by high out of range temperature at 105'F. At the time of the random failure and tampering by substitution, the contractor/vendor employee was employed as a foreman and as such had supervisory duties. This resulted in a Plant Event Report to NRC. The individual was permanently denied access at Energy Northwest. Management was notified and the individual's file was annotated regarding the permanent denial. The permanent denial information was recorded in the Personnel Access Data System (PADS) as required.
The second was a licensee employee manager who failed an FFD test for cause due to observable behavior. At the time of the for cause test for observable behavior the individual was employed as a manager and as such had supervisory duties. This resulted in a Plant Event Report to the NRC. The individual was denied access for a minimum of fourteen days and referred to the EAP for treatment. The licensee employee manager subsequently resigned and did not return to work at Energy Northwest.
PROGRAM WEAKNESSES No program weaknesses were identified during this reporting period.
PROGRAM CHANGES Effective January 12, 2009, program changes were made to the Fitness for Duty drug and alcohol testing program to meet new 10 CFR Part 26 requirements.