CPSES-200201037, Augmented Inservice Inspection Program Plan, Revision 1

From kanterella
Jump to navigation Jump to search
Augmented Inservice Inspection Program Plan, Revision 1
ML021070700
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 04/08/2002
From: Terry C, Walker R
TXU Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation, NRC Region 4
References
CPSES-200201037, TXX-02072
Download: ML021070700 (62)


Text

TXU TXU Energy Comanche Peak Steam Electric Station P.O. Box 1002 (E01)

Glen Rose, TX 76043 Tel: 254 897 8920 Fax: 254 897 6652 lance.terry@txu.com C. Lance Terry Senior Vice President &

Principal Nuclear Officer Ref:10CFR50.55a(g)

CPSES-200201037 Log # TXX-02072 File#

10010.1 905.4 April 8, 2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)-UNIT 2 DOCKET NO. 50-446 TRANSMITTAL OF UNIT 2 AUGMENTED INSERVICE INSPECTION PROGRAM PLAN, REVISION 1 (UNIT 2:1986 EDITION OF ASME CODE SECTION XI, NO ADDENDA, INTERVAL START DATE AUGUST 3, 1993, FIRST INTERVAL)

Gentlemen:

Enclosed is one copy of Revision 1 to the Unit 2 Augmented Inservice Inspection (AISI)

Program Plan for updating your manual. The enclosed Plan Revision 1 replaces the Plan Revision 0 in its entirety.

This communication contains no new licensing basis commitments regarding CPSES Units 1 and 2.

041

TXU TXX-02072 Page 2 of 2 Via this letter a copy of this report is also forwarded to Mr. G. Bynog, the Director and Chief Inspector of Texas Department of Licensing and Regulation. Should you need additional copies or require additional information, please contact Obaid Bhatty at (254) 897-5839 or Douglas Snow at (254) 897-8448.

Sincerely, TXU Generation Company LP By:

TXU Generation Management Company LLC Its General Partner C. L. Terry Senior Vice President and Principal Nuclear Officer By:

I Regulatory Affairs Manager OAB/dws Enclosure cc:

E. W. Merschoff, Region IV W.D. Johnson, Region IV D. H. Jaffe, NRR Resident Inspectors, CPSES G. Bynog, TDLR J.C. Hair, ANII W/O Enclosure W/O Enclosure W/O Enclosure W/O Enclosure

AUGMENTED INSERVICE INSPECTION PLAN TXU ENERGY COMANCHE PEAK STEAM ELECTRIC STATION UNIT 2 Revision 1 22 2 9-1) -

Prepared:

ISI Program Coordi~dtor Approved:

Date S

1 31071/0.

Engineering Programs Manager

'A paj in Date

AUGMENTED INSERVICE INSPECTION PLAN The purpose of this document is to identify and describe various regulatory and Comanche Peak Steam Electric Station (CPSES ) commitments involving the performance of periodic non-destructive examinations (NDE) other than those addressed in ASME Section XI (i.e., augmented inservice inspection). A separate section is provided for each major activity. Within each section the following information is provided:

a.

Governing Document

b.

Exam Items & Boundaries

c.

NDE Method and Schedule

d.

Acceptance Criteria

e.

Special Reports NOTE: Where Sections of the ASME Code are used in this document, the Edition and Addenda shall be as referenced in the CPSES Unit 1 Inservice Inspection Plan.

(I)

TABLE OF CONTENTS SECTION 1

Reactor Coolant Pump Flywheels 2

Safety Injection Pump Shroud 3

Flux Thimble Tubes 4

Main Steam and Feedwater Break Exclusion Piping Examination Tables 5

Supplementary Containment Spray and Residual Heat Removal Piping Welds Examination Tables 6

Reactor Vessel Head and Internals Lifting Devices App A Summary of Revision App B Interim Change Request (ICR) Index (ii)

REACTOR COOLANT PUMP FLYWHEELS This program shall provide for the inspection of each reactor coolant pump flywheel per the recommendations of Regulatory Position C.4.b of Regulatory Guide 1.14, Revision 1, August 1975. In lieu of Position C.4.b (I) and C.4.b (2), a qualified in-place UT examination over the volume from the inner bore of the flywheel to the circle one-half of the outer radius or a surface examination (MT and/or PT) of exposed surfaces of the removed flywheels may be conducted at approximately 10 year intervals coinciding with Inservice Inspection schedule as required by ASME Section XI.

The schedule for examinations shall be coincident with the inservice inspection periods and intervals described in ASME Section XI.

The acceptance limit for flaw size based upon the maximum design overspeed is 1.15 in. (Ref. WCAP-8163). All flaws detected shall be recorded for evaluation and monitored for growth rate.

No special reports are required for this activity unless examination and evaluation indicate that the 1.15 in. flaw size limit has been or will be exceeded during the service life of the flywheel. Should this occur, the NRC shall be notified (Ref.

Guide 1.14). Records of the examinations shall be maintained with the applicable work control document.

Summary Discussion

a.

Governing Document - Regulatory Guide 1.14 Rev. 1.

b.

Exam Items and Boundaries - Each reactor coolant pump flywheel.

c.

NDE Method and Schedule - In-place UT examination over the volume from the inner bore of the flywheel to the circle one-half of the outer radius or a surface examination (MT and/or PT) of exposed surfaces of the removed flywheels may be conducted at approximately 10 year intervals

d.

Acceptance Criteria - No flaws greater than 1.15 in.

e.

Special Reports - The NRC shall be notified should the maximum flaw size be exceeded, or expect to be exceeded, during the service life.

(1)

SAFETY INJECTION PUMP SHROUD Visible linear indications have been found on the shroud that separates and supports the diffuser vanes and return guide vanes on the type pump utilized as the safety injection pump at Comanche Peak Steam Electric Station (CPSES). These indications exceed the designer-permitted 1/16 in. maximum. The pump supplier (Pacific Pumps) has evaluated the significance of these indications and determined they have no adverse affects upon the operability of the pumps (Ref NUREG-0797 Supplement 12).

Pacific Pumps has proposed a field inspection program which addresses this issue. This program has been supplemented by the NRC and is described in NUREG-0797 Supplement 12.

The program requires a visual and surface examination of the shroud section of the intermediate cover during normal or emergency maintenance at approximately 10-year intervals (pump disassembly solely for this examination is not required). A log of all indications is to be maintained, with indications having a depth greater than 1.0 in. in the radial direction to be reported to Pacific Pumps. Records of the examination shall be maintained in the applicable work control document.

Summary Discussion

a.

Governing Document - Supplemental Safety Evaluation Report 12 (NUREG-0797).

b.

Exam Items and Boundaries - Shroud section of the safety injection pumps' intermediate cover.

c.

NDE Method and Schedule - Visual and surface examination during normal or emergency maintenance at approximately 10-year intervals.

d.

Acceptance Criteria - All indications shall be recorded with evaluation being on a case-by-case basis.

e.

Special Reports - All indications exceeding 1.0 in. in radial direction shall be reported to Pacific Pumps.

(1)

FLUX THIMBLE TUBES Westinghouse reactors containing bottom mounted instrumentation (BMI) flux thimble tubes have experienced wear due to flow induced vibration in the reactor vessel. These thimble tubes provide a pathway for the neutron flux detectors and extend from the seal table into the fuel assembly area. These tubes are closed within the vessel but open at the seal table.

Therefore, these tubes constitute a portion of the reactor coolant system pressure boundary.

In response to this issue, the NRC issued Information Notice 87-44 (9/87), with supplement (3/88), and Bulletin 88-09 (7/88).Bulletin 88-09 requested an inspection program be implemented to monitor thimble tube performance, with the program to include acceptance criterion, inspection methodology and frequency. Letter TXX-89781 provides a response to this bulletin and describes the intention of TXU Energy to comply with the bulletins' requirements.

The augmented inservice inspection shall include a full length examination, within the limitations of probe travel, of all 58 thimble tubes using standard eddy current testing (ET) techniques. Supplementary techniques or methods may be used for further evaluation. These examinations shall be conducted during the first refueling outage with subsequent examinations determined by the results obtained during previous examination.

Acceptance criteria for this activity is as follows:

Wa< 80%:

No action required Wa > 80%:

Cap or reposition Use the following equation to calculate predicted wear:

Wa = W, (N/Nd)'

Where:

Na = Accumulated time at which wear depth is to be calculated Nd = Operating time accumulated before inspection W, = Percent Wear Depth at time Na Wd = Percent Wear Depth at the time of the inspection n =

0.99 Summary Discussion

a.

Governing Document - NRC Bulletin 88-09, CPSES-9006199.

b.

Exam Items and Boundaries -All 58 thimble tubes to the extent possible of the full length.

c.

NDE Method and Schedule - ET to be performed on a schedule based upon previous examinations..

d.

Acceptance Criteria -See above discussion based on WCAP 12866.

e.

Special Reports - A special report will be issued to the NRC within 30 days of completion of the thimble tube inspection conducted during the first outage. This report was submitted under letter TXX-91455. Following the first inspection no special reports are required.

Note:

The following pages tabulate wear data for the 58 thimble tubes obtained from the various refueling outages.

TUBE ID OUTAGE Wd COMMENTS A-9 RF01 0

RF02 34 RF03 25 RF04 24 A-11 RF01 0

RF02 22 RF03 19 RF04 28 B-3 RFO1 0

RF02 23 RF03 16 RF04 0

B-6 RFO1 0

RF02 28 RF03 39 RF04 38 B-8 RFO1 0

RF02 40 RF03 46 RF04 52 B-13 RFO1 0

RF02 25 RF03 31 RF04 35 C-5 RFO1 0

RF02 20 RF03 15 RF04 0

C-7 RFO1 0

RF02 0

RF03 0

RF04 0

C-8 RF01 0

RF02 29 RF03 24 RF04 18 D-3 RFO1 0

RF02 27 RF03 23 RF04 26 D-8 RF01 0

RF02 0

RF03 0

RF04 0

D-10 RF01 0

RF02 0

RF03 0

RF04 15 D-12 RFO1 0

RF02 24 RF03 29 RF04 28 D-14 RFO1 0

RF02 31 RF03 41 RF04 44 (2)

TUBE ID OUTAGE Wd COMMENTS E-5 RFO1 0

RF02 19 RF03 18 RF04 0

E-9 RFO1 24 RF02 30 RF03 27 RF04 29 E-11 RFO1 0

RF02 32 RF03 38 RF04 41 F-i RFO1 0

RF02 32 RF03 23 RF04 20 F-3 RF01 0

RF02 23 RF03 27 RF04 28 F-7 RFO1 0

RF02 24 RF03 26 RF04 22 F-8 RFO1 0

RF02 24 RF03 17 RF04 18 F-14 RFO1 0

RF02 24 RF03 26 RF04 29 G-5 RFO1 0

RF02 18 RF03 20 RF04 22 G-9 RFO1 0

RF02 23 RF03 24 RF04 26 G-12 RFO1 0

RF02 25 RF03 11 RF04 0

H-2 RFO1 0

RF02 21 RF03 18 RF04 21 H-3 RFO1 0

RF02 20 RF03 22 RF04 24 (3)

TUBE ID H-4 H-6 H-11 H-13 H-15 J-1 J-7 OUTAGE RFO1 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RFO1 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 RF01 RF02 RF03 RF04 Wd 0

27 35 33 0

18 24 28 35 49 50 53 0

21 16 20 58 65 76 26 0

31 20 26 0

35 30 35 0

0 0

0 0

45 50 51 0

20 25 0

21 28 32 34 0

22 36 24 0

0 0

0 0

16 17 18 COMMENTS Tube repositioned at 2RF03 J-8 J-10 J-14 K-2 K-6 K-12 L-5 (4)

TUBE ID OUTAGE Wd COMMENTS L-8 RFO1 0

RF02 27 RF03 24 RF04 23 L-10 RFO1 0

RF02 19 RF03 19 RF04 0

L-11 RF01 0

RF02 0

RF03 0

RF04 0

L-13 RFO1 0

RF02 31 RF03 28 RF04 20 L-15 RFO1 0

RF02 21 RF03 28 RF04 21 M-7 RFO1 0

RF02 23 RF03 24 RF04 33 N-2 RFO1 0

RF02 17 RF03 19 RF04 25 N-4 RFO1 0

RF02 24 RF03 24 RF04 20 N-6 RF01 0

RF02 25 RF03 20 RF04 16 N-8 RFO1 0

RF02 22 RF03 22 RF04 0

N-13 RFO1 0

RF02 20 RF03 0

RF04 0

N-14 RFO1 0

RF02 25 RF03 13 RF04 18 P-4 RFO1 0

RF02 18 RF03 21 RF04 21 P-9 RF01 22 RF02 27 RF03 33 RF04 32 (5)

TUBE ID R-6 R-11 2RF01 2RF02 2RF03 2RF04 2RF05 2RF06 OUTAGE RFO1 RF02 RF03 RF04 RF02 RF03 RF04 RFO0 RF02 RF03 RF04 ONE/SMF ONE 94-1280 ONE 96-207 ONE-97-1294 SMF 2000-2137 W.O.

3-94-329397-01 3-95-329397-01 3-97-329397-01 3-98-329397-01 COMMENTS Wd 0

0 0

0 38 31 20 0

20 20 22 RFO1 0

Cycle Length EFPD 450 464 537 445 503 (est) 510 (est)

(6)

R-8

SUPPLEMENTARY CONTAINMENT SPRAY AND RESIDUAL HEAT REMOVAL PIPING WELDS The containment spray (CT) system piping on the discharge side of the four CT pumps contains 80 welds (15-25 each loop) that are 10-inch NPS Schedule 40 with a wall thickness of 0.365 inch. Furthermore, the residual heat removal (RHR) system piping on the discharge side of RHR pumps 1 and 2 contains a total of 166 welds on 8-inch and 10-inch NPS Schedule 40 piping with wall thicknesses of 0.322 inch and 0.365 inch, respectively.

Resulting from SSER-26, the augmented inservice inspection shall include a volumetric examination (i.e., ultrasonic examination) on 7.5 percent of the aforementioned welds. These examinations shall be distributed such that each weld or portion thereof is examined once during each 10-year interval.

Examination procedures and personnel shall be in accordance with the rules of ASME Section XI.

No special reports are required for this activity. Records of the examinations shall be maintained according to procedures.

Results of these examinations shall be evaluated against the acceptance criteria provided in ASME Section XI, IWC-3000.

Summary Discussion

a.

Governing Document - SSER-26

b.

Exam Items and Boundaries - 7.5 percent of the welds discussed above.

c.

NDE Method and Schedule - Ultrasonic examination once per 10-year interval. The specific schedule by refueling outage is attached..

d.

Acceptance Criteria - ASME Section XI, IWC-3000.

e.

Special Reports - None (1)

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 112 OUTAGE 1

2 3

1 2

-.... I

- - - I PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-001-1303-2 099200 TCX-2-2100-16 PIPE TO PIPE 877SB C-F-2 C5.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-33**

099250 TCX-2-2100-16L LONG.

SEAM 877RB C-F-2 UT 1 C C5.52 100% FROM WELD 16 TO 21.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

MAIN STEAM MS-25 (DRIP POT) 099400 TCX-2-2100-18 PIPE TO BRANCH CONNECTION 874SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51 MAIN STEAM 32-MS-2-001-1303-2 099700 TCX-2-2100-21 PIPE TO PIPE 877SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51 099750 TCX-2-2100-21L LONG.

SEAM 877SB C-F-2 UT I C CS.52 100% FROM WELD 21 TO 25.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

100100 TCX-2-2100-25 PIPE TO PIPE 877SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C CS. 51 DATE:

03/27/02 PAGE:

    • TBX-22**
    • TBX-33**
    • TBX-33**

i I

DATE:

03/27/02 PAGE:

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD O

I1

)UTAGE-I 1

2 3

1 2

PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-001-1303-2 C-F-2 C5. 52 100150 TCX-2-2100-25L LONG.

SEAM 877SB 100200 TCX-2-2100-26 PIPE TO VALVE 877SB UT 100% FROM WELD 25 TO 26.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-33**

100300 TCX-2-2100-27 VALVE TO MOMENT RESTRAINT 877SB 92 SELECTED FOR ISI.

C-F-2 UT 1

C5.51

    • TBX-33**

MAIN STEAM MS-25 (DRIP POT) 100500 TCX-2-2100-29 PIPE TO CAP 874SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C Cs. 51

    • TBX-22**

MAIN STEAM 8-MS-2-257-1303-2 100600 TCX-2-2100-30 BRANCH CONNECTION TO PIPE 878SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-17**

100700 TCX-2-2100-31 PIPE TO VALVE 881SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5. 51

    • TBX-17**

I ----

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS FIRST SECOND ASME PERIOD PERIOD PRESERVICE YEAR THIRD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH OUTA 12 12 3

G E 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 8-MS-2-257-1303-2 100900 TCX-2-2100-33 PIPE TO ELBOW 885SB C-F-2 C5.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-17**

101000 TCX-2-2100-34 ELBOW TO PIPE 885SB C-F-2 UT 1 C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-17**

101100 TCX-2-2100-35 PIPE TO VALVE 885SB C-F-2 UT I C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-17**

MAIN STEAM 6-2003-2 101200 TCX-2-2100-36 BRANCH CONNECTION TO FLANGE 878SB C-F-2 UT 1 C Cs. 51 TDLR VERIFICATION BOUNDARY.

    • TBX-36**

101300 TCX-2-2100-37 BRANCH CONNECTION TO FLANGE 878SB C-F-2 UT 1 C Cs. 51 TDLR VERIFICATION BOUNDARY.

    • TBX-36**

101400 TCX-2-2100-38 BRANCH CONNECTION TO FLANGE 878SB C-F-2 UT 1C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-36**

101500 TCX-2-2100-39 BRANCH CONNECTION TO FLANGE 878S1B C-F-2 UT I C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBXX-36**

PAGE:

DATE:

03/27/02 I -- - - - - -- - - - -

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS_

FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH OUT 1

2 1

2 A G 3

E- -----

1 2

PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATION BLOCK**

MAIN STEAM 6-2003-2 101600 TCX-2-2100-40 BRANCH CONNECTION TO FLANGE 878SB C-F-2 C5.51 UT i

C TDLR VERIFICATION BOUNDARY.

    • TBX-36**

FEEDWATER 18-FW-2-019-1303-2 102800 TCX-2-2101-12 PIPE TO PIPE 856SB C-F-2 C5.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-21**

FEEDWATER 18-FW-2-036-2003-2 103000 TCX-2-2101-14 PIPE TO VALVE 856SB C-F-2 UT 1

C5. 51 X

92 TDLR VERIFICATION BOUNDARY.

    • TBX-38**

103200 TCX-2-2101-16 PIPE TO VALVE 856SB 103300 TCX-2-2101-17 VALVE TO PIPE 856SB C-F-2 UT 1 C C5.51

    • TBX-38**

C-F-2 Cs.51 UT I C

    • TBX-38**

103400 TCX-2-2101-18 PIPE TO MOMENT RESTRAINT 856SB C-F-2 C5.51 UT 1 C

    • TBX-38**

DATE:

03/27/02 PAGE:

4

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS_

FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 112 OUTAGE 1

2 3

1 2

PRESERVICE YEAR INSTRUCTIONS i

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-095-1303-2 108500 TCX-2-2103-10 PIPE TO PIPE 864SB C-F-2 C5.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

108600 TCX-2-2103-11 ELBOW TO PIPE 864SB C-F-2 C5.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

108700 TCX-2-2103-12 PIPE TO ELBOW 864SB C-F-2 Cs.51 UT i

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

108800 TCX-2-2103-13 ELBOW TO PIPE 864SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

108900 TCX-2-2103-14 PIPE TO ELBOW 865SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109000 TCX-2-2103-15 ELBOW TO PIPE 868SB C-F-2 CS.51 UT I C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

109100 TCX-2-2103-16 PIPE TO ELBOW 869SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51 DATE:

03/27/02 PAGE:

5

    • TBX-35**

I ----------- -----------

DATE:

03/27/02 PAGE:

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD 1

2 0

U TAG 1

2 3

12 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-095-1303-2 C-F-2 C5.51 109200 TCX-2-2103-17 ELBOW TO PIPE 869SB 109300 TCX-2-2103-18 PIPE TO ELBOW 868SB UT I C TDLR VERIFICATION BOUNDARY.

TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109400 TCX-2-2103-19 ELBOW TO PIPE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109500 TCX-2-2103-20 PIPE TO ELBOW 862SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109600 TCX-2-2103-21 TEE TO PIPE 862SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109700 TCX-2-2103-22 PIPE TO TEE 862SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 C C5.51

    • TBX-35**

109800 TCX-2-2103-23 VALVE TO PIPE 862SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT I C C5. 51

    • TBX-35**

DATE:

03/27/02 PAGE:

7 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD i---------------

i --------

OUTAGE---

1 2

123 1

2 PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATIOl FEEDWATER 6-FW-2-095-1303-2 109900 TCX-2-2103-24 PIPE TO VALVE 862SB C-F-2 C5.51 UT 1

92 SELECTED FOR ISI. TDLR VERIFICATION BOUNDARY.

    • TBX-35**

110000 TCX-2-2103-25 PIPE TO PIPE 862SB C-F-2 Cs.51 UT 1 C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

FEEDWATER 6-FW-2-091-2003-2 C-F-2 C5.51 110100 TCX-2-2103-26 VALVE TO PIPE 862SB 110300 TCX-2-2103-28 ELBOW TO PIPE 862SB UT I C TDLR VERIFICATION BOUNDARY.

    • TBX-34**

C-F-2 UT 1C Cs.51 110400 TCX-2-2103-29 PIPE TO ELBOW 862SB 110500 TCX-2-2103-30 ELBOW TO PIPE 862SB C-F-2 UT 1 C C5.51 C-F-2 C5.51 UT i

C 110600 TCX-2-2103-31 PIPE TO ELBOW 861SB C-F-2 UT 1

C C5.51 BLOCK-*

    • TBX-34**
    • TBX-34**
    • TBX-34**

DATE:

03/27/02 PAGE:

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

FIRST ASME PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 112 PLAN STATUS_

SECOND THIRD PERIOD PERIOD OUTAGE-- -----------

1 2

3 1

2 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-091-2003-2 110700 TCX-2-2103-32 VALVE TO PIPE 861SB 110800 TCX-2-2103-33 PIPE TO VALVE 860SB C-F-2 UT 1 C C5. 51 C-F-2 UT 1 C C5.51

    • TBX-34**
    • TBX-34**

110900 TCX-2-2103-34 BRANCH CONNECTION TO PIPE 857SB C-F-2 UT 1

C5.51 92 SELECTED FOR ISI.

    • TBX-34**

MAIN STEAM 32-MS-2-002-1303-2 112900 TCX-2-2200-19 PIPE TO PIPE R109C877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

112950 TCX-2-2200-19L LONG.

SEAM R109C877SB C-F-2 UT 1

C5.52 C

100% FROM WELD 19 TO 23.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

e 113300 TCX-2-2200-23 PIPE TO PIPE RI09C877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

113550 TCX-2-2200-23L LONG.

SEAM R109C877SB C-F-2 UT C5. 52 C

100% FROM WELD 23 TO 27.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

ASME PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD PRESERVICE YEAR SEC.

XI

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION CATGY NDE

- ---------- O U T A G E ITEM NO METH I

2 1

2 3

1 2 INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-002-1i03-2 113700 TCX-2-2200-27 PIPE TO PIPE R11OC877SB C-F-2 CS. 51 UT 1

C TDLR VERIFICATION BOUNDARY.

    • TBX-33**

113750 TCX-2-2200-27L LONG.

SEAM R11OC877SB C-F-2 UT 1

C5.52 C

100% FROM WELD 27 TO 28.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

113800 TCX-2-2200-28 PIPE TO VALVE RIIOC877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

113900 TCX-2-2200-29 VALVE TO MOMENT RESTRAINT RI09C877SB C-F-2 UT 1

CS. 51 92 SELECTED FOR ISI.

    • TBX-33**

MAIN STEAM 8-MS-2-240-1303-2 114000 TCX-2-2200-30 BRANCH CONNECTION TO PIPE RI09C878SB C-F-2 UT 1

Cs. 51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

114100 TCX-2-2200-31 PIPE TO VALVE R109C881SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

114200 TCX-2-2200-32 VALVE TO PIPE RI09C883SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

PAGE:

9 Il -----

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH FIRST PERIOD Ii 0

1 2

PLAN STATUS_

PRESERVICE YEAR SECOND PERIOD U TAG E 2

3 1

THIRD PERIOD 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 8-MS-2-240-1303-2 114300 TCX-2-2200-33 PIPE TO ELBOW Ri0 9C883B C-F-2 C5.51 UT 1 -

92 SELECTED FOR ISI.

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

114400 TCX-2-2200-34 ELBOW TO PIPE R109C885SB C-F-2 UT 1

CS.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

MAIN STEAM 6-2003-2 114600 TCX-2-2200-36 BRANCH CONNECTION TO FLANGE R109C878SB C-F-2 UT 1

C5.51 92 SELECTED FOR ISI. TDLR VERIFICATION BOUNDARY.

    • TBX-36**

114700 TCX-2-2200-37 BRANCH CONNECTION TO FLANGE R109C878SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

114800 TCX-2-2200-38 BRANCH CONNECTION TO FLANGE R109C878SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

114900 TCX-2-2200-39 C-F-2 UT 1

C-TDLR VERIFICATION BOUNDARY.

BRANCH CONNECTION TO FLANGE C5.51 R109C878SB

    • TBX-36**

115000 TCX-2-2200-40 C-F-2 UT 1

BRANCH CONNECTION TO FLANGE C5.51 R109C878SB C

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

DATE:

03/27/02 PAGE:

10

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS PRESERVICE YEAR FIRST PERIOD 112

-i SECOND PERIOD OUTAGE 1

2 3

THIRD PERIOD 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM MS-24 (DRIP POT) 115200 TCX-2-2200-66 BRANCH CONNECTION TO PIPE R110C876SB C-F-2 UT 1 -C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-22**

115300 TCX-2-2200-67 PIPE TO CAP RI0OD874SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-22**

FEEDWATER 18-FW-2-035-2003-2 118000 TCX-2-2202-1 MOMENT RESTRAINT TO PIPE 856SB 118100 TCX-2-2202-2 PIPE TO VALVE 856SB 118200 TCX-2-2202-3 VALVE TO PIPE 856SB C-F-2 UT 1 -

C C5.51 C-F-2 UT 1 -

C C5.51

    • TBX-38**
    • TBX-38**

FEEDWATER 18-FW-2-018-1303-2 118600 TCX-2-2202-7 PIPE TO PIPE 856SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -C C5.51 DATE:

03/27/02 PAGE:

11 C-F-2 UT C5.51 C

    • TBX-38**
    • TBX-21**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS _

PRESERVICE YEAR FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION FEEDWATER 6-FW-2-092-2003-2 122000 TCX-2-2204-2 BRANCH CONNECTION TO PIPE 857SB 122100 TCX-2-2204-3 PIPE TO VALVE 860SB SEC.

XI CATGY NDE ITEM NO METH C-F-2 Cs.51 I ----

I OUT 1

2 112 AG 3

1 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

UT 1

C C-F-2 UT 1 -

C C5.51 122200 TCX-2-2204-4 VALVE TO PIPE 861SB 122300 TCX-2-2204-5 PIPE TO ELBOW 862SB C-F-2 UT 1 -

C C5.51 C-F-2 UT 1

C C5.51

    • TBX-34**
    • TBX-34**

122400 TCX-2-2204-6 ELBOW TO PIPE 863SB C-F-2 UT 1

CS.s51 92 SELECTED FOR ISI.

    • TBX-34**

122500 TCX-2-2204-7 PIPE TO ELBOW 863SB 122600 TCX-2-2204-8 ELBOW TO PIPE 863SB C-F-2 UT 1 -

C C5.51 C-F-2 UT 1 -

C C5.51 PAGE:

12

    • TBX-34**
    • TBX-34**
    • TBX-34**
    • TBX-34**

DATE:

03/27/02 PAGE:

13 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL

____PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD SEC. XI CATGY NDE -

0 U T A G ETAGE--

ITEM NO METH 1

2 1

2 3

1 2

PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-092-2003-2 122700 TCX-2-2204-9 PIPE TO VALVE 863SB C-F-2 UT 1

C C5.51 122800 TCX-2-2204-10 VALVE TO PIPE 863SB C-F-2 UT 1

C5.51 92 SELECTED FOR ISI. TDLR VERIFICATION BOUNDARY.

FEEDWATER 6-FW-2-096-1303-2 122900 TCX-2-2204-11 PIPE TO PIPE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -C C5.51

    • TBX-35**

123000 TCX-2-2204-12 PIPE TO VALVE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -

C Cs.51

    • TBX-35**

123100 TCX-2-2204-13 VALVE TO PIPE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -

C Cs.51

    • TBX-35**

123200 TCX-2-2204-14 PIPE TO TEE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -

C C5.51

    • TBX-35**

123300 TCX-2-2204-15 TEE TO PIPE 863SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1 -

C Cs.51

    • TBX-34**
    • TBX-35**

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL ASME SEC.

XI EXAMINATION AREA IDENTIFICATION CATGY NDE ITEM NO METH PLAN STATUS______

FIRST PERIOD 1

2 SECOND PERIOD OUTAGE 1

2 3

PRESERVICE YEAR THIRD PERIOD

- - I 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-096-1303-2 123400 TCX-2-2204-16 PIPE TO ELBOW 863SB C-F-2 C5.51 UT 1 -

92 SELECTED FOR ISI. TDLR VERIFICATION BOUNDARY.

    • TBX-35**

123500 TCX-2-2204-17 ELBOW TO PIPE 863SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

123600 TCX-2-2204-18 PIPE TO ELBOW 868SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

123700 TCX-2-2204-19 ELBOW TO PIPE 870SB C-F-2 UT C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

123800 TCX-2-2204-20 PIPE TO ELBOW 870SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

123900 TCX-2-2204-21 ELBOW TO PIPE 868SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

124000 TCX-2-2204-22 PIPE TO ELBOW 865SB C-F-2 UT 1 -C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

SUMMARY

NUMBER PAGE:

14 DATE:

03/27/02


----------- ----------- I

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL-PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH I---------

OUTAGE 112 1

2 3

1 2 PAGE:

15 PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-096-1303-2 124100 TCX-2-2204-23 ELBOW TO PIPE 864SB C-F-2 CS.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

124200 TCX-2-2204-24 PIPE TO ELBOW 864SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

124300 TCX-2-2204-25 ELBOW TO PIPE 864SB C-F-2 UT 1

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

124400 TCX-2-2204-26 PIPE TO PIPE 864SB C-F-2 UT 1 -

C C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

MAIN STEAM 32-MS-2-003-1303-2 129700 TCX-2-2300-18 PIPE TO PIPE 877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

129750 TCX-2-2300-18L LONG.

SEAM 877SB C-F-2 UT 1

C5.52 C

100% FROM WELD 18 TO 22.

TDLR VERIFICATION BOUNDARY.

130100 TCX-2-2300-22 PIPE TO PIPE 877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

DATE:

03/27/02

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS- _PRESERVICE YEAR EXAMINATION AREA IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH FIRST PERIOD 112

-i - - - -

SECOND PERIOD O U TAG 1

2 3

THIRD PERIOD E

1 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-003-1303-2 130150 TCX-2-2300-22L LONG.

SEAM 877SB C-F-2 C5.52 UT 1 -

C 100% FROM WELD 22 TO 26.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

130500 TCX-2-2300-26 PIPE TO PIPE 877SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

130550 TCX-2-2300-26L LONG.

SEAM B77SB C-F-2 UT 1

C5.52 C

100% FROM WELD 26 TO 27.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

130600 TCX-2-2300-27 PIPE TO VALVE 877SB C-F-2 UT 1

CS. 51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

130700 TCX-2-2300-28 VALVE TO MOMENT RESTRAINT 877SB C-F-2 UT 1

C5.51 C

    • TBX-33**

MAIN STEAM MS-23 (DRIP POT) 130900 TCX-2-2300-30 PIPE TO CAP 873SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-22**

MAIN STEAM 8-MS-2-223-1303-2 131000 TCX-2-2300-31 BRANCH CONNECTION TO PIPE 878SB C-F-2 UT 1

C5.51 X

92 TDLR VERIFICATION BOUNDARY.

    • TBX-17**

SUMMARY

NUMBER PAGE:

16

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS__

PRESERVICE YEAR FIRST

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH SECOND PERIOD PERIOD THIRD PERIOD I---------

OUTAGE-------------

1 2

1 2

3 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM B-MS-2-223-1303-2 131100 TCX-2-2300-32 PIPE TO VALVE 880SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

131300 TCX-2-2300-34 PIPE TO ELBOW 884SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-17**

131400 TCX-2-2300-35 ELBOW TO PIPE 885SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-17**

131500 TCX-2-2300-36 PIPE TO VALVE 885SB C-F-2 UT 1

C5. 51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

MAIN STEAM 6-2003-2 131600 TCX-2-2300-37 BRANCH CONNECTION TO FLANGE 878SB C-F-2 C5.51 UT I

C TDLR VERIFICATION BOUNDARY.

    • TBX-36**

131700 TCX-2-2300-38 BRANCH CONNECTION TO FLANGE 878SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

131800 TCX-2-2300-39 BRANCH CONNECTION TO FLANGE 878SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

PAGE:

17

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL_

ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS_

FIRST SECOND THIRD PERIOD PERIOD PERIOD

-OUTAGE 1

2 1

2 3

1 2

PRESERVICE YEAR INSTRUCTIONS "I

    • CALIBRATION BLOCK**

MAIN STEAM 6-2003-2 131900 TCX-2-2300-40 BRANCH CONNECTION TO FLANGE 878SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-36**

132000 TCX-2-2300-41 BRANCH CONNECTION TO FLANGE 878SB C-F-2 UT 1

C5.51

-X 92 TDLR VERIFICATION BOUNDARY.

    • TBX-36**

MAIN STEAM MS-23 (DRIP POT) 132100 TCX-2-2300-62 PIPE TO PIPE 873SB C-F-2 C5.51 UT C

TDLR VERIFICATION BOUNDARY.

    • TBX-22**

FEEDWATER 18-FW-2-017-1303-2 134800 TCX-2-2301-27 PIPE TO PIPE RI00D856SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-21**

FEEDWATER 18-FW-2-034-2003-2 135200 TCX-2-2301-31 PIPE TO VALVE RI0OH856SB 135300 TCX-2-2301-32 VALVE TO PIPE RI0OH856SB C-F-2 C5.51 C-F-2 C5.51 UT 1 -

UT 1

C C

PAGE:

18

    • TBX-38**
    • TBX-38**

DATE:

03/27/02

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL_

ASME SEC.

XI CATGY NDE ITEM NO METH FIRST PERIOD 12 PLAN STATUS-

_PRESERVICE YEAR SECOND THIRD PERIOD PERIOD OU A

E-----------

ISRCON 0 U T A G E INSTRUCTIONS 1

2 3

1 2

-*CALIBRATIOT N BLOCK**

FEEDWATER 18-FW-2-034-2003-2 135400 TCX-2-2301-33 PIPE TO MOMENT RESTRAINT RI0OH856SB C-F-2 C5.51 UT 1 -

C FEEDWATER 6-FW-2-093-2003-2 138700 TCX-2-2303-2 BRANCH CONNECTION TO PIPE RI0OD856SB 138800 TCX-2-2303-3 PIPE TO VALVE RI00D858SB C-F-2 UT 1

C5.51 C-F-2 UT 1

C5.51 C

C 138900 TCX-2-2303-4 VALVE TO PIPE RI0OD859SB 139000 TCX-2-2303-5 PIPE TO ELBOW RI00D862SB C-F-2 UT 1

C5.51 C-F-2 UT 1

C5.51 139100 TCX-2-2303-6 ELBOW TO PIPE RI00D863SB 139200 TCX-2-2303-7 PIPE TO ELBOW R100D863SB C-F-2 UT 1

C5.51 C-F-2 UT 1 -

C5.51 92 SELECTED FOR ISI.

    • TBX-34**

C

    • TBX-34**

PAGE:

19

    • TBX-38**
    • TBX-34**
    • TBX-34**

C

    • TBX-34**

C

    • TBX-34**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS__

PRESERVICE YEAR

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH FIRST PERIOD 1

2 SECOND PERIOD O UTAG 1

2 3

THIRD PERIOD E---------------I E

1 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-093-2003-2 139300 TCX-2-2303-8 ELBOW TO PIPE R100D863SB 139400 TCX-2-2303-9 PIPE TO VALVE RI0O0D863SB 139500 TCX-2-2303-10 VALVE TO PIPE Ri10D863SB C-F-2 C5.51 UT C

TDLR VERIFICATION BOUNDARY.

    • TBX-34**

FEEDWATER 6-FW-2-097-1303-2 139600 TCX-2-2303-11 PIPE TO PIPE R100D863SB C-F-2 UT 1

C5. 51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

139800 TCX-2-2303-13 VALVE TO PIPE RI10D863SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

139900 TCX-2-2303-14 PIPE TO TEE RI10D863SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140000 TCX-2-2303-15 TEE TO PIPE R100D863SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

PAGE:

20 C-F-2 C5.51 UT 1

C C-F-2 C5.51 UT 1 -

    • TBX-34**

C

    • TBX-34**

DATE:

03/27/02 PAGE:

21 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

EXAMINATION AREA IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD 1

2 PERIOD PERIOD

-OUTAGE-1 2

3 1

2

- I PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-097-1303-2 140100 TCX-2-2303-16 PIPE TO ELBOW R100D863SB C-F-2 C5. 51 UT 1

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140200 TCX-2-2303-17 ELBOW TO PIPE R100D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140300 TCX-2-2303-18 PIPE TO PIPE RI00D866SB C-F-2 C5.51 UT 1 -

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140400 TCX-2-2303-19 PIPE TO ELBOW R100D869SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140500 TCX-2-2303-20 ELBOW TO PIPE R100D870SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140600 TCX-2-2303-21 PIPE TO ELBOW R1000870SB C-F-2 C5.51 UT 1

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140700 TCX-2-2303-22 ELBOW TO PIPE R100D869SB TDLR VERIFICATION BOUNDARY.

C-F-2 UT 1

C5.51

SUMMARY

NUMBER

    • TBX-35**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS _PRESERVICE YEAR I

FIRST SECOND THIRD I

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PERIOD PERIOD I-112 PERIOD OUTAGE G

1 2

3 1

2 INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-097-1303-2 140800 TCX-2-2303-23 PIPE TO ELBOW RI10D865SB C-F-2 Cs.51 UT I

C TDLR VERIFICATION BOUNDARY.

    • TBX-35**

140900 TCX-2-2303-24 ELBOW TO PIPE R100D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

141100 TCX-2-2303-26 ELBOW TO PIPE RI00D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

141200 TCX-2-2303-27 PIPE TO PIPE RI10D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

144920 TCX-2-2303-65 PIPE TO PIPE RI10D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-3S**

144940 TCX-2-2303-66 PIPE TO PIPE R100D864SB C-F-2 UT 1

C5.51 C

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

MAIN STEAM 32-MS-2-004-1303-2 146600 TCX-2-2400-17 PIPE TO PIPE 877SB C-F-2 UT 1

C5.51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-33**

PAGE:

22

DATE:

03/27/02 PAGE:

23 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL_

ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD OUTAGE------------

1 2

1 2 3

1 2 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-004-1303-2 146650 TCX-2-2400-17L LONG.

SEAM 877SB C-F-2 C5.52 UT 1 -

X 100% FROM WELD 17 TO 19.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

146800 TCX-2-2400-19 PIPE TO PIPE 877SB C-F-2 UT C5.51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-33**

146850 TCX-2-2400-19L LONG.

SEAM 877SB C-F-2 UT 1

CS. 52

-X 100% FROM WELD 19 TO 25.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

147400 TCX-2-2400-25 PIPE TO PIPE 877SB X

C-F-2 UT 1

C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-33**

147450 TCX-2-2400-25L LONG.

SEAM 877SB C-F-2 UT 1

CS. 52

-X 100% FROM WELD 25 TO 56.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

147500 TCX-2-2400-26 PIPE TO VALVE 877SB C-F-2 UT 1

C5.51 X

92 TDLR VERIFICATION BOUNDARY.

    • TBX-33**

147550 TCX-2-2400-26L LONG.

SEAM 877SB C-F-2 UT 1

C5. 52

-X 92 100% FROM WELD 56 TO 26.

TDLR VERIFICATION BOUNDARY.

    • TBX-33**

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION INSPECTION INTERVAL_

ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD 0 U T A 1

2 3

12 G

E--

G E 1

2 PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-004-1303-2 147600 TCX-2-2400-27 VALVE TO MOMENT RESTRAINT 877SB C-F-2 C5.51 UT 1

X

    • TBX-33**

MAIN STEAM MS-26 (DRIP POT) 147800 TCX-2-2400-29 PIPE TO CAP 874SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-22**

MAIN STEAM 8-MS-2-274-1303-2 147900 TCX-2-2400-30 BRANCH CONNECTION TO PIPE 878SB 148000 TCX-2-2400-31 PIPE TO VALVE 878SB 148100 TCX-2-2400-32 VALVE TO PIPE 879SB C-F-2 UT 1 -

C5.51 C-F-2 UT 1 -

C5.51 C-F-2 UT 1

CS. 51 X

-X X

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

148200 TCX-2-2400-33 PIPE TO ELBOW 884SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

PAGE:

24 DATE:

03/27/02

DATE:

03/27/02 PAGE:

25 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

ASME SEC. XI PLAN STATUS______

FIRST SECOND PERIOD PERIOD PRESERVICE YEAR THIRD PERIOD I -- - - - -

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION CATGY NDE I

ITEM NO METH I 12 OUTAGE 1

2 3

1 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

MAIN STEAM 8-MS-2-274-1303-2 148300 TCX-2-2400-34 ELBOW TO PIPE 885SB C-F-2 C5.51 UT 1

X TDLR VERIFICATION BOUNDARY.

    • TBX-17**

148400 TCX-2-2400-35 PIPE TO VALVE 885SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-17**

MAIN STEAM 6-2003-2 148500 TCX-2-2400-36 BRANCH CONNECTION TO FLANGE 879SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

148600 TCX-2-2400-37 BRANCH CONNECTION TO FLANGE 879SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

148700 TCX-2-2400-38 BRANCH CONNECTION TO FLANGE 879SB C-F-2 UT 1

C5.51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-36**

148800 TCX-2-2400-39 BRANCH CONNECTION TO FLANGE 879SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-36**

148900 TCX-2-2400-40 BRANCH CONNECTION TO FLANGE 879SB C-F-2 UT 1

CS. 51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-36**

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 1

2 OUTAGE------------

1 2

3 1

2 PAGE:

26 PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATION BLOCK**

MAIN STEAM 32-MS-2-004-1303-2 148950 TCX-2-2400-56 PIPE TO PIPE 877SB C-F-2 C5.51 UT 1

X TDLR VERIFICATION BOUNDARY.

    • TBX-33**

MAIN STEAM MS-26 (DRIP POT) 149000 TCX-2-2400-60 PIPE TO PIPE 876SB C-F-2 UT 1

C5.51 X

92 TDLR VERIFICATION BOUNDARY.

    • TBX-22**

FEEDWATER 18-FW-2-020-1303-2 150100 TCX-2-2401-11 PIPE TO PIPE 856SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-21**

150200 TCX-2-2401-12 PIPE TO PIPE 856SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-21**

FEEDWATER 18-FW-2-037-2003-2 150300 TCX-2-2401-13 PIPE TO VALVE 856SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-38**

150400 TCX-2-2401-14 VALVE TO PIPE 856SB C-F-2 UT 1

C5. 51

-X DATE:

03/27/02

    • TBX-38**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS_

FIRST SECOND THIRD PERIOD PERIOD PERIOD SOUTAGE-------------

1 21 2

3 1

2 PRESERVICE YEAR INSTRUCTIONS "I

    • CALIBRATION BLOCK**

FEEDWATER 18-FW-2-037-2003-2 150500 TCX-2-2401-15 PIPE TO VALVE 856SB 150600 TCX-2-2401-16 VALVE TO PIPE 856SB 150700 TCX-2-2401-17 PIPE TO MOMENT RESTRAINT 856SB C-F-2 UT 1

C5.51

-X C-F-2 UT 1

C5.51 FEEDWATER 6-FW-2-094-2003-2 154700 TCX-2-2403-2 BRANCH CONNECTION TO PIPE 857SB C-F-2 UT 1

C5.51 I

154800 TCX-2-2403-3 PIPE TO VALVE 859SB C-F-2 UT 1

C5.51 154900 TCX-2-2403-4 VALVE TO PIPE 861SB 155000 TCX-2-2403-5 PIPE TO ELBOW 862SB C-F-2 UT 1

C5.51 C-F-2 UT 1

C5.51 X

X PAGE:

27 C-F-2 C5.51 UT 1

X

    • TBX-38**
    • TBX-38**

X

    • TBX-38**
    • TBX-34**

IC -

92

    • TBX-34**
    • TEX-34**
    • TBX-34**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

ASME SEC.

XI EXAMINATION AREA CATGY NDE IDENTIFICATION ITEM NO METH PLAN STATUS_

FIRST SECOND THIRD PERIOD PERIOD PERIOD OUTAGE------------

1 2

2 3

1 2

PRESERVICE YEAR INSTRUCTIONS I

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-094-2003-2 155100 TCX-2-2403-6 ELBOW TO PIPE 863SB C-F-2 C5.51 UT 1 -

-X 155200 TCX-2-2403-7 PIPE TO ELBOW 863SB C-F-2 UT 1

Cs.51 155300 TCX-2-2403-8 ELBOW TO PIPE 863SB 155400 TCX-2-2403-9 PIPE TO VALVE 863SB C-F-2 UT 1 -

C5.51 C-F-2 UT 1 -

C5.51 X

X 155500 TCX-2-2403-10 VALVE TO PIPE 863SB C-F-2 UT I

C5.51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-34**

FEEDWATER 6-FW-2-098-1303-2 155600 TCX-2-2403-11 PIPE TO PIPE 862SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

155700 TCX-2-2403-12 PIPE TO VALVE 862SB C-F-2 UT 1

C5. 51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-35**

SUMMARY

NUMBER PAGE:

28

    • TBX-34**

X 92

    • TBX-34**
    • TBX-34**
    • TBX-34**

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

FIRST ASME PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 112 PLAN STATUS SECOND THIRD PERIOD PERIOD OUTAGE G----

1 2

3 1

2 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-098-1303-2 155800 TCX-2-2403-13 VALVE TO PIPE 862SB C-F-2 C5.51 UT I

X TDLR VERIFICATION BOUNDARY.

    • TBX-35**

155900 TCX-2-2403-14 PIPE TO TEE 862SB C-F-2 UT 1

CS. 51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156000 TCX-2-2403-15 TEE TO PIPE 862SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156100 TCX-2-2403-16 PIPE TO ELBOW 862SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156200 TCX-2-2403-17 ELBOW TO PIPE 863SB C-F-2 UT 1

Cs. 51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156300 TCX-2-2403-18 PIPE TO ELBOW 869SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156400 TCX-2-2403-19 ELBOW TO PIPE 870SB C-F-2 UT I

C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

PAGE:

29 I ----------- -----------

DATE:

03/27/02 HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS_

PRESERVICE YEAR

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH FIRST PERIOD 1

2 SECOND PERIOD OUTAGE 1

2 3

1 THIRD PERIOD 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-098-1303-2 156500 TCX-2-2403-20 PIPE TO ELBOW 870SB X

C-F-2 UT 1

C5.51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156600 TCX-2-2403-21 ELBOW TO PIPE 869SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156700 TCX-2-2403-22 PIPE TO ELBOW 865SB 156800 TCX-2-2403-23 ELBOW TO PIPE 864SB X

C-F-2 UT 1

Cs. 51 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

C-F-2 UT 1

CS. 51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

156900 TCX-2-2403-24 PIPE TO ELBOW 864SB 157000 TCX-2-2403-25 ELBOW TO PIPE 864SB C-F-2 UT 1

C5. 51 X

92 TDLR VERIFICATION BOUNDARY.

    • TBX-35**

C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

157100 TCX-2-2403-26 PIPE TO PIPE 864SB C-F-2 UT 1

C5.51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-35**

PAGE:

30 I ----------- ----------- --

HIGH ENERGY LINE BREAK UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD SEC. XI

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION CATGY NDE ITEM NO METH I

2 112 OUTAGE G-----

1 2

3 1

2 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

FEEDWATER 6-FW-2-098-1303-2 157920 TCX-2-2403-35 PIPE TO PIPE 864SB C-F-2 UT 1

C5.51 X

TDLR VERIFICATION BOUNDARY.

    • TBX-35**

157940 TCX-2-2403-36 PIPE TO PIPE 864SB C-F-2 UT 1

C5. 51

-X TDLR VERIFICATION BOUNDARY.

    • TBX-35**

PAGE:

31 DATE:

03/27/02

SUPPLEMENTARY CONTAINMENT SPRAY AND RESIDUAL HEAT REMOVAL PIPING WELDS The containment spray (CT) system piping on the discharge side of the four CT pumps contains 80 welds (15-25 each loop) that are 10-inch NPS Schedule 40 with a wall thickness of 0.365 inch. Furthermore, the residual heat removal (RHR) system piping on the discharge side of RHR pumps 1 and 2 contains a total of 166 welds on 8-inch and 10-inch NPS Schedule 40 piping with wall thicknesses of 0.322 inch and 0.365 inch, respectively.

Resulting from SSER-26, the augmented inservice inspection shall include a volumetric examination (i.e., ultrasonic examination) on 7.5 percent of the aforementioned welds. These examinations shall be distributed such that each weld or portion thereof is examined once during each 10-year interval.

Examination procedures and personnel shall be in accordance with the rules of ASME Section XI.

No special reports are required for this activity. Records of the examinations shall be maintained according to procedures.

Results of these examinations shall be evaluated against the acceptance criteria provided in ASME Section XI, IWC-3000.

Summary Discussion

a.

Governing Document - SSER-26

b.

Exam Items and Boundaries - 7.5 percent of the welds discussed above.

c.

NDE Method and Schedule - Ultrasonic examination once per 10-year interval. The specific schedule by refueling outage is attached..

d.

Acceptance Criteria - ASME Section XI, IWC-3000.

e.

Special Reports - None (1)

RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

ASME PLAN STATUS-PRESERVICE YEAR FIRST SECOND THIRD PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 1

2 OUTAGE

-I 1

2 3

1 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

RESIDUAL HEAT REMOVAL 10-RH-2-061-601R-2 170700 TCX-2-2520-35 REDUCER TO PIPE 787SB 170750 TCX-2-2520-35L LONG.

SEAM 787SB 170800 TCX-2-2520-36 PIPE TO VALVE 787SB 170850 TCX-2-2520-36L LONG.

SEAM 787SB 170900 TCX-2-2520-37 VALVE TO PIPE 787SB C-F-l UT 1 C C5.12 C-F-l UT 1 C C5. 11 C-F-1 UT 1 C CS. 12 C-F-I UT 1 C C5. 11 170950 TCX-2-2520-37L LONG.

SEAM 787SB C-F-i UT 1 C C5.12 RESIDUAL HEAT REMOVAL 8-RH-2-064-601R-2 178000 TCX-2-2521-48 PIPE TO FLANGE 781SB C-F-I UT I

Cs.11

-X PAGE:

C-F-I UT C5.11 1 C

    • TBX-10**
    • TBX-10**
    • TBX-10**
    • TBX-10**
    • TBX-7**

DATE:

03/24/02 I ---- -----. - ---- ---.-

-- I

    • TBX-10**

DATE:

03/24/02 RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL_

ASME

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND THIRD PERIOD PERIOD PERIOD I----------

OUTAGE 1

2 1

2 3

1 2

- I PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

RESIDUAL HEAT REMOVAL 8-RH-2-064-601R-2 178050 TCX-2-2521-48L LONG.

SEAM 781SB C-F-I C5.12 UT 1

X 178100 TCX-2-2521-49 FLANGE TO PIPE 781SB C-F-I UT 1

C5. 11 178150 TCX-2-2521-49L LONG.

SEAM 781SB 178200 TCX-2-2521-50 PIPE TO ELBOW 781SB 178250 TCX-2-2521-50L LONG.

SEAM 781SB 178300 TCX-2-2521-51 ELBOW TO PIPE 781SB C-F-i UT 1

CS. 12 C-F-i UT 1

C5. 11 C-F-i UT 1

C5.12 C-F-I UT 1

C5. 11 X

X X

X 178350 TCX-2-2521-51L LONG.

SEAM 781SB PAGE:

X

    • TBX-7**
    • TBX-7**
    • TBX-7**

C-F-i UT I

C5.12

    • TBX-7**

X

    • TBX-7**

RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

__PLAN STATUS_

FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION RESIDUAL HEAT RFMoVAT.

in-PM-SEC.

XI CATGY NDE ITEM NO METH 2-n2------

I Ia.

OUTAGE 1

2 3

2 1

2 PAGE:

3 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

185100 TCX-2-2531-4 PIPE TO ELBOW 789SB 185150 TCX-2-2531-4L LONG.

SEAM 789SB 185200 TCX-2-2531-5 ELBOW TO PIPE 789SB 185300 TCX-2-2531-6 PIPE TO FLANGE 800SB C-F-I UT 1 C C5.12 C-F-i UT 1 C C5. 1i C-F-I UT 1 C C5. 11 RESIDUAL HEAT REMOVAL 8-RH-2-027-601R-2 190100 TCX-2-2532-36 PIPE TO ELBOW 797SB 190150 TCX-2-2532-36L LONG.

SEAM 797SB 190200 TCX-2-2532-37 ELBOW TO PIPE 797SB C-F-i UT 1

Cs. 11 C-F-1 UT 1

C5. 12 C-F-l UT 1

C5. 11 DATE:

03/24/02 C-F-1 UT C5.11

    • TBX-10**
    • TBX-10**
    • TBX-10**
    • TBX-10**

X

    • TBX-7**

X

    • TBX-7**

X

    • TBX-7**

2-026-601R-2 I C

RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION ASME SEC.

XI CATGY NDE ITEM NO METH PLAN STATUS FIRST SECOND PERIOD PERIOD 1

2

-OUTAGE 1

2 3

-PRESERVICE YEAR THIRD I

1 PERIOD 2

INSTRUCTIONS

    • CALIBRATION BLOCK**

RESIDUAL HEAT REMOVAL 8-RH-2-027-601R-2 190250 TCX-2-2532-37L LONG.

SEAM 797SB 190300 TCX-2-2532-38 PIPE TO ELBOW 797SB 190350 TCX-2-2532-38L LONG.

SEAM 797SB C-F-I UT 1 -

C5. 11 C-F-i UT 1

CS. 12 190400 TCX-2-2532-39 ELBOW TO PIPE 798SB C-F-i UT 1

C5. 11 X

190450 TCX-2-2532-39L LONG.

SEAM 798SB C-F-I UT 1

C5.12 X

    • TBX-7**

CONTAINMENT SPRAY 10-CT-2-011-301R-2 203800 TCX-2-2539-2 ELBOW TO PIPE 776SB C-F-I UT 1

C5. 11 C

203850 TCX-2-2539-2L LONG.

SEAM 776SB PAGE:

4 C-F-i C5.12 UT 1 -

X

    • TBX-7**

X

    • TBX-7**

X

    • TBX-7**

C-F-I UT C5.12 C

    • TBX-10**

DATE:

03/24/02

RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS FIRST SECOND ASME PERIOD PERIOD

SUMMARY

NUMBER EXAMINATION AREA IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH 1

2 OUTAGE 1

2 3

T P

1 2

PRESERVICE YEAR HIRD ERIOD INSTRUCTIONS I

    • CALIBRATIOl CONTAINMENT SPRAY 10-CT 011-301R-2 203900 TCX-2-2539-3 PIPE TO ELBOW 776SB 203950 TCX-2-2539-3L LONG.

SEAM 776SB 204000 TCX-2-2539-4 ELBOW TO PIPE 776SB C-F-I UT 1 -

C5.11 C-F-I UT 1

C5.12 C-F-I UT 1

CS. 11 204050 TCX-2-2539-4L LONG.

SEAM 776SB 204900 TCX-2-2539-13 VALVE TO PIPE 787SB C-F-1 UT 1

CS. 12 C-F-1 UT 1

Cs. 11 204950 TCX-2-2539-13L LONG.

SEAM 787SB C-F-I UT 1

C5.12 C

205000 TCX-2-2539-14 PIPE TO ELBOW 787SB C-F-1 UT 1

C5. 11 DATE:

03/24/02 PAGE:

5 4 BLOCK--

C

    • TBX-10**

C

    • TBX-10**

C

    • TBX-10**

C

    • TBX-10**

C

    • TBX-10**
    • TBX-10**

C

DATE:

03/24/02 RESIDUAL HEAT REMOVAL/CONTAINMENT SPRAY UNIT 2 INSERVICE INSPECTION PLAN CLASS 2 SCHED/COMPL COMPONENTS INSPECTION INTERVAL PLAN STATUS FIRST SECOND THIRD ASME PERIOD PERIOD PERIOD

SUMMARY

EXAMINATION AREA NUMBER IDENTIFICATION SEC.

XI CATGY NDE ITEM NO METH I

-2 112 0

1 U T A G E 2

3 1

2 PRESERVICE YEAR INSTRUCTIONS

    • CALIBRATION BLOCK**

CONTAINMENT SPRAY 10-CT-2-011-301R-2 205050 TCX-2-2539-14L LONG.

SEAM 787SB C-F-1 UT C5.12 1 -

C

    • TBX-10**

205100 TCX-2-2539-15 ELBOW TO PIPE 787SB C-F-I UT 1

C5. 11 205150 TCX-2-2539-15L LONG.

SEAM 787SB C-F-I UT I

C5.12 C

PAGE:

6 C

    • TBX-10**
    • TBX-10**

I ----------- ----------- --------

REACTOR VESSEL HEAD AND INTERNALS LIFTING DEVICES ANSI N14.6-1978 provides detailed requirements for the design, fabrication, testing, maintenance, and quality assurance of special lifting devices at nuclear power stations. To address the control of heavy loads and to ensure against and mitigate the consequences of postulated accidental load drops, the Nuclear Regulatory Commission (NRC) issued NUREG 0612.

Westinghouse Electric Corporation conducted an evaluation and documented the results under WCAP-10156, Rev. 1 to determine the acceptability of the reactor vessel head and internals lifting devices to meet the requirements of NUREG 0612. As a result of this effort, recommendations were made to perform periodic non-destructive examinations on prescribed critical welds and/or parts once every ten years as part of an inservice inspection outage.

Therefore volumetric, surface and or visual examinations shall be performed as described in the attached pages at approximately 10-year intervals coinciding with Inservice Inspection schedules as required by ASME Section XI. The acceptance criteria shall be in accordance with ASME Section XI, IWC-3000. Examinations shall be performed by written procedures and by personnel qualified in accordance with the rules in ASME Section XI.

No special reports are required for this activity. Records of the examinations shall be maintained with the applicable work control document.

Summary Discussion

a.

Governing Document - ANSI N14.6-1978, NUREG 0612, TXX-4226 and TXX-99172.

b.

Exam Items and Boundaries - Reactor vessel head and internal lifting rigs' critical welds and/or parts as described in the attached pages.

c.

NDE Method and Schedule -Volumetric, surface and or visual examinations at approximately 10-year intervals coinciding with Inservice Inspection schedules as required by ASME Section XI.

d.

Acceptance Criteria - ASME Section XI, IWC-3000.

e.

Special Reports - None (1)

REACTOR VESSEL HEAD LIFT RIG, CRITICAL ITEMS LIST Item (2)

Removable Pin RV Head Lifting Lug Material Description Lifting Block Lug Clevis Pin Clevis Lifting Leg Clevis Pin (load sensing)

Side Plates ASTM A564 Type 630 SA-533 Gr B Class 1 Non-Destructive Examination Method Visual Visual Volumetric Visual Visual ASTM A350 GR, LF ASTM A516 Grade 70 ASTM A434 AISI 4340 Steel Class BD ASTM A668 Forging and Class L AIS14340 ASTM A434 Class BC AISI 4340 ASTM A564 Type XM12 ASTM 533 Type B Class 1 Visual Volumetric Visual (a) See Page 4 (2)

Volumetric 1

2 3,6 4,10 5,9 11 12 13 14

REACTOR VESSEL HEAD LIFT RIG, CRITICAL ITEMS LIST OF WELDS Non-Destructive Examination Item (a)

Description Method 1,2 Lugs to Lifting Block Surface (Full Penetration) 7,8 Spreader Arm Surface Lug to Spreader Arm (fillet) 14 RV Head Lifting Lug Surface (integral attachment area)

(a) See Page 4 (3)

REMOVABLE PIN

@ SIDE PLATE LIFTING LEG CLEVIS PIN -<

POSlTIOP LUG G LIFTING LEG TYPICAL CRDM CLEVIS CLEVIS PIN REACTOR VESSEL HEAD Reactor Vessel Head Lift Rig (4)

REACTOR VESSEL INTERNALS LIFT RIG CRITICAL ITEMS LIST Item (a)

Material 1

(') See Page 8 (5)

Description Lifting Block Lifting Block Lug Clevis Pin Clevis Sling Rod Spread Lug Leg Lug Mounting Block Leg Channels ASTM A350 GR. LF 2 ASTM A516 Grade 70 ASTM A564 Grade 70 Precipitation Hardening SST Age treated @

1150' F/4 Hrs.

Air cooled RC 28-31 ASTM A471 Class 3 Steel Forging ASTM A434 Class BC AISI 4340 or (ASTM A588)

ASTM A516 Gr. 70 STL Plate Normalized ASTM 350 LFI Forging Steel ASTM A36 CS, HR 2

3,7 4,6 Non-Destructive Examination Method Visual Visual 5

Volumetric Visual Visual 8,11 13 12 Visual Visual Visual

REACTOR VESSEL INTERNALS LIFT RIG CRITICAL ITEMS LIST Description Load Nuts Rod Housing Guide Sleeve Engaging Screw Non-Destructive Examination Method Material ASTM A276 Type 304 SST, Hot Rolled, Condition A ASTM A276 Type 304 SST, Hot Rolled, Annealed & Pickled, Condition A ASTM A564 Type 630, 17-4 pH Steel @ 1100°F for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> (a) See Page 8 (6)

Item (2) 14,15 16 Visual 17 Visual Visual

REACTOR VESSEL INTERNALS LIFT RIG CRITICAL ITEMS LIST OF WELDS Non-Destructive Examination Item (a)

Description Method 1,2 Lugs to Lifting Block Surface (Full Penetration) 8,9 Lug to Spreader Block Surface (Full Penetration) 11,12 Leg Lug to Channel Leg Surface (fillet) 12,13 Mounting Block to Surface Channel Leg (fillet)

(a) See Page 8 (7)

LIFTING BLOCK Q LUG 0 ROD Q CLEVIS BLOCK LUG @

LEG LUG @

CHANNEL @

(9 LOAD NUT MOUNTING BLOCK ROD HOUSING GUIDE SLEEVE' ENGAGING SCREW'

a.

Reactor Vessel Internals Lift Rig (8)

SCLEVIS PIN ARM

Appendix A

SUMMARY

OF REVISIONS Rev. No.

Rev. Summary 0

Original issue Incorporation of ICR 1 to Rev. 0 (schedule lifting rig exams at the 10 year ISI outage)

Incorporation of ICR 2 to Rev. 0 (adopted wear method, acceptance criteria from WCAP 12866 and documented wear found during 2RF01)

Incorporation of ICR 3 to Rev. 0 (removed inaccessible exam items from the table)

Incorporation of ICR 4 to Rev. 0 (adopted wear method calculation from WCAP 12866 and documented wear found during 2RF02)

Incorporation of ICR 5 to Rev. 0 (removed inaccessible exam items from the table)

Incorporation of ICR 6 to Rev. 0 (removed inaccessible exam items from the table)

Incorporation of ICR 7 to Rev.0 (incorporated 2RF04 wear data)

Revised Section 6 - Reactor Vessel Head and Internals Lifting Devices Revised the piping tables in Sections 3 and 4 (Main Steam and Feedwater Break Exclusion and Containment and Residual Heat Removal) to show completed exams during 2RF01, 2RF02, 2RF03, 2RF04, and 2RF05.

Removed an inaccessible exam (summary number 131200) from the table that was identified in 2RF04 and not included in ICR 7 Re-instated exams (summary numbers 103000, 131000, 132000, 147500, 149000, 154800, 155200, and 156900) to AISI that were originally selected for the ISI program, but were deleted because of implementing RI-ISI for selected piping welds Editorial changes made to summary numbers 099200, 139100, 139700, and 147750.

(1)

Appendix B INDEX OF INTERIM CHANGE REQUEST (ICRs)

AFFECTED PAGES Section 6 Page 1 Section 3 Pages 1 and 2 Section 4 Section 3 Section 4 Section 4 Pages 10 and 18 Section 3 Page 2 ICR No.

AISI-2R0-01 AISI-2R0-02 (1)

CHANGE Schedule lifting rig exams at the 10 year ISI outage.

Adopted wear method and acceptance criteria from WCAP 12866.

Documented wear found during 2RFO1.

Removed inaccessible exam items from table.

Adopted wear method calculation from WCAP 12866. Document wear found during 2RF02.

Removed inaccessible exam items from table.

Removed inaccessible exam items from table.

Incorporated 2RF04 data.

AISI-2R0-03 AISI-2R0-04 AISI-2R0-05 AISI-2R0-06 AISI-2R0-07