MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report CP-202300139, (CPNPP) - Property Damage Insurance2023-03-30030 March 2023 (CPNPP) - Property Damage Insurance CP-202300098, (Cpnpp), Annual Report of Changes in Peak Cladding Temperature2023-03-16016 March 2023 (Cpnpp), Annual Report of Changes in Peak Cladding Temperature CP-202200481, Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST)2022-12-0707 December 2022 Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST) CP-202200454, (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 .2022-12-0101 December 2022 (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 . CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200450, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2022-11-16016 November 2022 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202200435, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2022-11-0808 November 2022 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report CP-202200358, (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46)2022-09-14014 September 2022 (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46) CP-202200246, Evacuation Time Estimate Analysis2022-08-25025 August 2022 Evacuation Time Estimate Analysis CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200276, (CPNPP) - Relief Request Application P-1, Inservice Testing (IST)2022-07-20020 July 2022 (CPNPP) - Relief Request Application P-1, Inservice Testing (IST) CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 2024-01-31
[Table view] Category:Request for Code Relief or Alternative
[Table view] |
Text
m Jack C. Hicks Manager, Regulatory Affairs Comanche Peak Nuclear Power Plant (Vistra Operations Company LLC)
Luminant P.O. Box 1002 6322 North FM 56 Glen Rose , TX 76043 T 254 .897.6725 CP-202200041 TXX-22009 January 27, 2022 U. S. Nuclear Regulatory Commission Ref 10 CFR 50.55a ATIN: Document Control Desk Washington, DC 20555-0001
Subject:
Comanche Peak Nuclear Power Plant (CPNPP)
Docket Nos. 50-445 and 50-446 SUPPLEMENT TO ASME OM INSERVICE TEST PROGRAM RELIEF REQUEST SNB-3, SNUBBER INSERVICE PROGRAM THIRD INTERVAL EXTENSION
Reference:
- 1. Letter from Steven K. Sewell to the NRC for ASME OM INSERVICE TEST PROGRAM RELIEF REQUEST SNB-3, SNUBBER INSERVICE PROGRAM THIRD INTERVAL EXTENSION dated January 4, 2022. [ADAMS Accession No. ML22004A025]
Dear Sir or Madam:
Pursuant to 10 CFR 50.55a(z)(2), Vistra Operations Company LLC ("Vistra OpCo") requests Nuclear Regulatory Commission (NRC) approval of the enclosed supplement to proposed Relief Request SNB-3, Snubber Inservice Program, Third Interval Extension, from the requirements of American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) ISTA-3120, Inservice Test Interval (c)(2) and (d). The relief is to extend the end of the third interval for the Snubber Inservice Program from April 19, 2022 to August 2, 2023. The supplement to the original relief request, as submitted in Reference 1, is provided in Enclosure 1.
This communication contains no new commitments regarding CPNPP Units 1 and 2.
Should you have any questions, please contact Garry Struble at (254) 897-6628 or Garry.Struble@luminant.com.
Sincerely,
~C.1~
Jae.Hicks
Enclosure:
- 1. Supplement to IST Program Relief Request SNB-3
TXX-22009 Page 2 of 2 c (email) - Scott Morris, Region IV [Scott.Morris@nrc.gov]
Dennis Galvin, NRR [Dennis.Galvin@nrc.gov]
John Ellegood, Senior Resident Inspector, CPNPP Uohn.Ellegood@nrc.gov]
Neil Day, Resident Inspector, CPNPP [Neil.Day@nrc.gov]
Enclosure 1 to TXX-22009 Supplement to 1ST Program Relief Request SNB-3
- 1. Title of Project RELIEF REQUEST SNB INSERVICE TESTING {1ST) / SNUBBER INSERVICE PROGRAM
- 2. Licensee Vistra Operations Company, LLC (Vistra OpCo)
- 3. Licensee Contact Garry Struble
- 4. Licensee Contact Phone Number 254-897-6628 ,
- 5. Licensee Contact Email Address Garry.Struble@luminant.com
- 6. Plant Identification Number 227551
- 7. Plant Name Comanche Peak Nuclear Power Plant (CPNPP)
- 8. Plant Units Unit 1 Unit 2
- 9. Docket Numbers 50-445 50-446
- 10. License Numbers NPF-87 NPF-89
- 11. Requested Completion Date March 19, 2022
- 12. Applicable Regulation and lnservice Inspection (ISi} or lnservice Testing (1ST)
Select 10 CFR 50.55a(z)(2) 1ST
- 13. Proposed Alternative Number or Identifier:
SNB-3
- 14. Applicable American Society of Mechanical Engineers {ASME} Boiler and Pressure Vessel {BPV) Code, or ASME Operations and Maintenance (OM) Code, Edition and Addenda:
The applicable Code for the CPNPP third ten-year inservice inspection {ISi) interval and the ISi program is the American Society of Mechanical Engineers {ASME)Section XI, 2007 Edition through the 2008 Addenda.
The applicable Code for the snubber program is ASME Operation and Maintenance of Nuclear Power Plants (OM Code), 2004 Edition through the 2006 Addenda.
- 15. ISi or 1ST Program Interval Number and start/end dates (as applicable):
1ST Program Third Interval Start Date: August 3, 2013 End Date: August 2, 2023 Snubber lnservice Program Third Interval Start Date: April 19, 2012 End Date: April 19, 2022
- 16. ASME Code Class ASME Class 1, 2 & 3
- 17. Applicable Components and or System Description {if applicable):
All Comanche Peak Nuclear Power Plant (CPNPP) Units 1 and 2 snubbers that are included in the scope of the Snubber lnservice Program.
- 18. Describe the Applicable Code Requirements:
ISTA-3120, lnservice Test Interval, states, in part:
(a) The frequency for inservice testing shall be in accordance with the requirements of Section 1ST.
(c) The inservice test intervals shall comply with the following, except as modified by ISTA-3120{d) ...
(2) Successive Test Intervals: 10 years following the previous test interval (d) Each of the inservice test intervals may be extended or decreased by as much as 1 year. Adjustments shall not cause successive intervals to be altered by more than 1 year from the original pattern of intervals.
- 19. Reason for Request:
Pursuant to 10 CFR 50.SSa, Codes and standards, paragraph (z)(2), Vistra OpCo is requesting authorization to extend the Snubber lnservice Program interval to align with the CPNPP lnservice Testing (1ST) Program interval. The basis ofthis request is that compliance with ISTA-3120{c)(2) and {d) represents a hardship without a compensating increase in the level of quality or safety.
The CPNPP Snubber lnservice Program examinations and testing are currently performed in accordance with the ASME OM Code, 2004 Edition through the 2006 Addenda, as required by 10 CFR S0.55a(b){3){v), OM condition: Snubbers /STD (B) Snubbers Second provision. This provision requires licensees to comply with the provisions for examining and testing snubbers in Subsection ISTD of the ASME OM Code when using the 2006 Addenda and later editions of ASME BPV Code Section XI. As required by RIS-2010-6 and EGM-10-001, the snubber program was transitioned from ASME Section XI to the ASME OM Code on April 19, 2012. Since this transition occurred separately from an ISi Program and 1ST Program interval, the Snubber lnservice Program interval was tracked separately as a stand-alone program.
Beginning with the fourth ten-year 1ST Program interval, Vistra OpCo is proposing to extend the ten-year interval dates for the CPNPP Units 1 and 2 Snubber lnservice Program by approximately four months beyond the Code-allowed one-year extension, from April 19, 2022, to August 2, 2023. This extension allows the snubber program interval to be in alignment with the 1ST program fourth ten-year interval, which begins August 3, 2023. The applicable ASME OM Code Edition for the fourth 10-year 1ST interval will be the 2017 Edition {or later, as determined by the final 10 CFR 50.55a rulemaking effective within 18 months of the fourth interval start date).
The OM Code ISTA-3120{d) allows the inservice test interval to be extended by as much as 1 year.
However, since the fourth 1ST interval start date is August 3, 2023, which is beyond the allowed 1-year extension for the snubber program, relief is requested to begin the fourth 1ST interval for snubbers on August 3, 2023. This will allow the snubber program interval to be aligned with the 1ST interval for pumps and valves. The existing snubber program will continue to verify the reliability of the snubber components. Since snubber testing is performed during refueling outages, there will be no changes or lapses in snubber testing activities as a result of extending the interval date to align with the 1ST Program interval update. Therefore, the existing snubber program, which is in accordance with the ASME OM Code, 2004 Edition through the 2006 Addenda, will remain in effect until the updated program is implemented on August 3, 2023.
- 20. Brief Description of the Proposed Alternative (500 characters or less):
Vista OpCo is requesting to align the ten year interval requirements of the OM Code, Section ISTD, "
Snubbers" to the OM Code Sections ISTB and ISTC, "Pumps and valves". Therefore, combining all OM Code 1ST programs into one interval.
- 21. Full Description of the Proposed Alternative:
Proposed Alternative CPNPP is proposing to transition the snubber program for Units 1 and 2 to be in alignment with the 1ST program fourth ten-year interval beginning August 3, 2023. This will result in the Snubber lnservice Program still being implemented in accordance with the ASME OM Code 2004 Edition through the 2006 addenda, until the program is updated as part of the fourth interval 1ST Program update on August 3, 2023, at which time the applicable ASME OM Code Edition will be the 2017 Edition {or later, as determined by the final rulemaking for 10 CFR 50.55a published on or before February 3, 2022).
- 22. If needed, include additional information for Question 21:
NONE
- 23. Description of the Basis for Use:
Aligning the CPNPP Units 1 and 2 Snubber lnservice Program interval with the 1ST program interval will reduce any associated administrative burden and ensures that all lST Code programs (pumps, valves, dynamic restraints) remain in accordance with the same ASME OM Code year and addenda, eliminating any potential for differing governing Code Editions that might arise in subsequent ten-year intervals.
Thus, this proposed alternative is requested pursuant to 10 CFR 50.55a{z){2) on the basis that compliance results in hardship or unusual difficulty without a compensating increase in level of quality or safety.
- 24. If needed, include additional information for Question 23:
NONE
- 25. If requesting an alternative based on 10 CFR 50.55a(z)(2), describe hardship or unusual difficulty without compensating increase in the level of quality and safety associated with compliance with applicable code requirement. For requests under 10 CFR 50.SSa(z)(l), leave this section blank.
Aligning the CPNPP Units 1 and 2 Snubber lnservice Program interval with the 1ST program interval will reduce any associated administrative burden and ensures that all lST Code programs (pumps, valves, dynamic restraints) remain in accordance with the same ASME OM Code year and addenda, eliminating any potential for differing governing Code Editions that might arise in subsequent ten-year intervals.
Thus, this proposed alternative is requested pursuant to 10 CFR 50.55a(z)(2) on the basis that compliance results in hardship or unusual difficulty without a compensating increase in level of quality or safety.
- 26. Proposed duration of the alternative:
Upon approval, the proposed alternative extending the third ten-year interval for snubbers will be implemented at CPNPP Units 1 and 2 beginning April 19, 2022 and continuing through the start of the CPNPP Units 1 and 2 Fourth 10-Year 1ST Interval, August 3, 2023. The ten-year intervals for snubbers, thereafter, will continue to be synchronized with the corresponding 1ST interval.
- 27. Include any additional information, as necessary:
NONE
- 28. Precedents (optional):
Similar relief for aligning snubber programs with 1ST intervals was previously granted to Virginia Electric and Power Company, via safety evaluation, "North Anna Power Station, Unit No. 1- lnservice Inspection Alternative Request Nl-I4-CS-002 (EPID L-2018-LLR-0128), dated May 21, 2019 (ADAMS Accession No.
M L19135A324}.
- 29.
References:
- 1. American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code), 2004 Edition through the 2006 Addenda
- 2. 10CFR50.55a, Code and standards, June 3, 2020.
- 30. Do you have attachments?
NO