Comanche Peak, Units 1 and 2, Transmittal of Year 2011 Radioactive Effluent Release Report
ML12128A193
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/30/2012
From: Flores R, Madden F W
Luminant Generation Co, Luminant Power
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CP-201200347, TXX-12061
Download: ML12128A193 (2)


Text

Rafael Flores Senior Vice President& Chief Nuclear Officer Rafael.flores@Luminant.com Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 Luminant T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-201200347 Log # TXX-12061 Ref. # Tech. Spec. 5.6.3 April 30, 2012 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NOS. 50-445 AND 50-446 TRANSMITTAL OF YEAR 2011 RADIOACTIVE EFFLUENT RELEASE REPORT

Dear Sir or Madam:

In accordance with Comanche Peak Nuclear Power Plant Unit 1 and 2 Technical Specifications (TS) 5.6.3 and Section 6.9.1.4 of the Comanche Peak Offsite Dose Calculation Manual (ODCM), enclosed is the Radioactive Effluent Release Report which covers the reporting period from January 1, 2011 through December 31, 2011.The tabular summaries of radioactive liquid and gaseous releases are provided in the format defined in Appendix B of Regulatory Guide 1.21, Rev. 1, dated June, 1974.During this reporting period there were two revisions to the ODCM. These revisions are discussed in the report and are denoted by change bars in the copy of the ODCM provided in Enclosure 2.If there are any questions regarding this report, please contact Steve Dixon at (254) 897-5482 or Bill Moore at (254) 897-8222.Sincerely, Luminant Generation Company LLC Rafael Flores By: ii272Qu 4Frred" W. Madden /Director, Oversight

& Regulatory Affairs A member of the STARS (Strategic Teaming and Resource Sharing) Alliance 4\-Cir9 Callaway -Comanche Peak -Diablo Canyon Palo Verde

  • San Onofre
  • Wolf Creek U. S. Nuclear Regulatory Commission TXX-12061 Page 2 04/30/2012 Enclosures

-1. 2011 Radioactive Effluent Release Report 2. Comanche Peak Nuclear Power Plant Offsite Dose Calculation Manual (ODCM)Unit 1 and 2, Revision 31 and Revision 32 c -E. E. Collins, Region IV L. K. Gibson, NRR Resident Inspectors, Comanche Peak (w/o Encl 2)