Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 16
ML15167A435
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 06/12/2015
From: James Shea
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-15-101
Download: ML15167A435 (2)


Text

SAFEGUARDS INFORMATION Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-101 June 12, 2015 10 CFR.50.4(b)(4) 10 CFR 50.54(p)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License No. NPF-90 Construction Permit No: CPPR-92 NRC Docket Nos. 50-390 and 50-391

Subject:

Watts Bar Nuclear Plant Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 16 In accordance with Title 10 of the Code of FederalRegulations (10 CFR) 50.54(p), this letter provides Revision 16 of the Watts Bar Nuclear Plant (WBN) Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program.

The Revision Log of the WBN Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent.Fuel Storage Installation Security Program provided in the enclosure describes the recent changes. The revised plan became effective as of April 24, 2015.

Tennessee Valley Authority (TVA) has evaluated the changes contained in this revision and has determined that the revision does not decrease the safeguards effectiveness of the subject plan.

The enclosure to this letter contains Safeguards Information and should be protected in accordance with 10 CFR 73.21 and 10 CFR 73.22. The enclosed plan revision is being sent by certified mail and the signed receipt will signify that the Nuclear Regulatory Commission has received this information.

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION CLASSIFICATION DOES NOT APPLY TO THIS PAGE WHEN SEPARATED FROM THE ENCLOSURE.

SAFEGUARDS INFORMATION U.S. Nuclear Regulatory Commission CNL-15-101 Page 2 June 12, 2015 There are no new regulatory commitments associated with this submittal. If you have any questions regarding this information, please contact Pat Asendorf, Senior Program Manager, Security Regulatory Oversight at (423) 365-8844.

Respectfully, Vice President, Nuclear Licensing