|
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML20196D0071999-06-16016 June 1999 Application for Amend to License DPR-35,changing TS Re Reactivity Control by Incorporating Operating Requirements That Are Consistent with NEDO-21231, Banked Position Withdrawal Sequence ML20206R8101999-05-11011 May 1999 Application for Amend to License DPR-35,requesting NRC Review & Approval of Change to TS Section 3/4.5.C, HPCI, Sys,Section 3/4.5.D, RCIC Sys & Bases Associated with Sections ML20206H9651999-05-0505 May 1999 Application for Amend to License DPR-35,modifying Licensing Basis for EDG on-site Diesel Fuel Storage Requirement & Corresponding TSs ML20203B5721999-02-0505 February 1999 Redacted Application for Amend to License DPR-35, Transferring FOL & Matls License 20-07626-04 from Boston Edison to Entergy Nuclear ML20202B4821999-01-21021 January 1999 Application for Amend to License DPR-35,using New Values for post-accident Containment Pressure in Plant NPSH Analyses Performed for ECCS Pumps.Calculations Supporting Request, Encl ML20198G5731998-12-21021 December 1998 Application for Amends to License DPR-35 & Matls License 20-07626-04,transferring PNPS from Boston Edison to Entergy Nuclear.Proprietary Info Encl.Proprietary Info Withheld. Pages 608 Through 621 of Incoming Submittal Not Included ML20249C7081998-06-26026 June 1998 Application for Amend to License DPR-35,correcting Typos & Updating Bases.Changes Are Considered Administrative ML20217H2681998-03-25025 March 1998 Application for Amend to License DPR-35,modifying Tech Specs 3.6.A.1 & 4.6.A.1 as It Pertains to Primary Sys Boundary, Thermal & Pressurization Limitations & Surveillance Requirements & Basis 3/4.6.A.Calculation Encl ML20203D4851998-02-20020 February 1998 Application for Amend to License DPR-35,to Change TS 3/4.5.B & Bases to Incorporate Ultimate Heat Sink Temperature 75 F, as Required by Amend 173.Request Fulfills Commitment to Submit TS Amend for UHS Temperature by First Quarter 1998 ML20203A0781998-02-11011 February 1998 Application for Amend to License DPR-35 UFSAR Section 10.7, Clarifying Design Basis for Salt Water Svc Water Sys BECO-LTR-97-107, Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is Performed1997-10-24024 October 1997 Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is Performed BECO-97-096, Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-14331997-09-19019 September 1997 Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-1433 BECO-LTR-97-002, Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit Withheld1997-01-24024 January 1997 Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit Withheld ML20135C1271996-11-26026 November 1996 Application for Amend to License DPR-35,modifying Definition 1.M, Primary Containment Integrity, to Include All Instrument Line Flow Check Valves to Make Definition Consistent W/Lco 3/4.7.A.2.a.4 BECO-96-042, Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid Control1996-05-0101 May 1996 Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid Control ML20111B4121996-05-0101 May 1996 Application for Amend to License DPR-35,revising TS to Reflect Implementation of 10CFR50 App J,Option B ML20108C0781996-05-0101 May 1996 Application for Amend to License DPR-35,relocating Administrative Controls Re QA Review & Audit Requirements of Section 6 from Plant TS to Util QA Manual ML20108C0261996-05-0101 May 1996 Application for Amend to License DPR-35 Re Core Alteration & LCO & Surveillance Conditions Associated W/Secondary Containment BECO-LTR-96-040, Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at Plant1996-04-25025 April 1996 Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at Plant BECO-95-074, Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 111995-07-14014 July 1995 Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 11 ML20078N4751995-02-0909 February 1995 Application for Amend to License DPR-35,increasing Reactor High Water Level Isolation Trip Level Setting BECO-94-128, Application for Amend to License DPR-35,revising Suppression Chamber Water Level Operating Range,Increasing & Revises Water Level Recorder Range in Response to Commitment from Insp 50-293/91-2011994-11-22022 November 1994 Application for Amend to License DPR-35,revising Suppression Chamber Water Level Operating Range,Increasing & Revises Water Level Recorder Range in Response to Commitment from Insp 50-293/91-201 ML20078K7881994-11-22022 November 1994 Application for Amend to License DPR-35 to TS Re Change to MSIV Leakage Requirement BECO-94-127, Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from Quarterly1994-11-22022 November 1994 Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from Quarterly BECO-94-126, Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 Days1994-11-22022 November 1994 Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 Days BECO-94-098, Application for Amend to License DPR-35,requesting Change to Reflect Standard TSs Re Maintenance of Filled Discharge Pipe1994-09-0606 September 1994 Application for Amend to License DPR-35,requesting Change to Reflect Standard TSs Re Maintenance of Filled Discharge Pipe ML20072S0741994-09-0606 September 1994 Application for Amend to License DPR-35 Re Proposed TS Change to Standby Gas Treatment & Control Room High Efficiency Air Filtration Sys Requirements ML20072S0331994-09-0606 September 1994 Application for Amend to License DPR-35 Re Proposed TS Change to Setpoint for Reactor Pressure to Isolate Shutdown Cooling Sys ML20072R9891994-09-0606 September 1994 Application for Amend to License DPR-35 Involving Proposed Administrative Change to TSs Re Control Room Annunciator. Amend Involves Relocation of Alarms for Drywell Suppression Vacuum Breakers ML20069M3181994-06-0909 June 1994 Application for Amend to License DPR-35,revising TS to Increase Allowed out-of-service Time from 7 Days to 14 Days for Ads,Hpci & RCIC Sys.Proposed Change Also Made to Section 4.5.H, Maint Of...Discharged Pipe to Reflect Amend 149 ML20067B6941994-02-0909 February 1994 Application for Amend to License DPR-35,proposing Changes to TS by Revising Wording for Page 3 of License DPR-35,adding Clarifying Words to Aid Operators & Removing Obsolete Mechanical Snubber Acceptance Criterion ML20058N0131993-12-10010 December 1993 Application for Amend to License DPR-35,proposing Changes to Ts,Re Request for Changes Supporting 24 Month Fuel Cycle (Submittal 3) ML20062J3311993-10-19019 October 1993 Application for Amend to License DPR-35 Proposing Changes to Remove Low Condenser Vacuum Scram in Order to Reduce Spurious Scrams,Unnecessary Plant Transients & Turbine First Stage Pressure Setpoint BECO-93-133, Application for Amend to License DPR-35 Proposing Changes to TS by Removing Scram & Group 1 Isolation Valve Closure Functions Associated W/Msl Radiation Monitors1993-10-19019 October 1993 Application for Amend to License DPR-35 Proposing Changes to TS by Removing Scram & Group 1 Isolation Valve Closure Functions Associated W/Msl Radiation Monitors ML20046D0411993-08-0909 August 1993 Application for Amend to License DPR-35,proposing 24 Month Fuel Cycle ML20044G1251993-05-20020 May 1993 Application for Amend to License DPR-35,revising TS Re MSIV Turbine Inlet Low Pressure Setpoint to Reduce Potential Spurious Isolations Caused by Existing Higher Setpoint.Ge Repts MDE-70-0586 & NEDO-31296 Encl ML20128P3651993-02-11011 February 1993 Application for Amend to License DPR-35,changing TS to Increase Allowed Fuel Assembly Storage Cells from 2,320 to 3,859 & Changing Max Loads Allowed to Travel Over Spent Fuel Assemblies to 2,000 Lbs.Holtec Rept HI092925 Encl BECO-92-126, Application for Amend to License DPR-35,revising TS Sections 1.0,4.3,4.4,4.5,4.6,4.7 & Associated Bases to Conform SRs for ASME Code Class 1,2 & 3 Pumps & Valves to IST Program, Per 10CFR50.55a(g)(5)(ii)1992-10-30030 October 1992 Application for Amend to License DPR-35,revising TS Sections 1.0,4.3,4.4,4.5,4.6,4.7 & Associated Bases to Conform SRs for ASME Code Class 1,2 & 3 Pumps & Valves to IST Program, Per 10CFR50.55a(g)(5)(ii) BECO-92-121, Application for Amend to License DPR-35,proposing Changes to TS Section 2.1, Safety Limits, to Reflect Use of Advanced GE-10 Fuel Design & Section 3.3.C, Scram Insertion Times, to Correct Error in Control Rod Scram Insertion Time1992-10-23023 October 1992 Application for Amend to License DPR-35,proposing Changes to TS Section 2.1, Safety Limits, to Reflect Use of Advanced GE-10 Fuel Design & Section 3.3.C, Scram Insertion Times, to Correct Error in Control Rod Scram Insertion Time BECO-92-116, Application for Amend to License DPR-35,consisting of Temporary Change to TS Sections 3.7.B.1.C,3.7.B.1.e, 3.7.B.2.a & 3.7.B.2.C,requiring Both Trains of SGTS to Be Operable During Irradiated Fuel Handling Operations1992-10-0808 October 1992 Application for Amend to License DPR-35,consisting of Temporary Change to TS Sections 3.7.B.1.C,3.7.B.1.e, 3.7.B.2.a & 3.7.B.2.C,requiring Both Trains of SGTS to Be Operable During Irradiated Fuel Handling Operations BECO-92-101, Application for Amend to License DPR-35,changing TS 3/4.2 Re HPCI Instrumentation to Support Mod Planned During Refueling Outage 9 of Control Conduit for Several Valves in HPCI Indication in CR Per Reg Guide 1.971992-08-17017 August 1992 Application for Amend to License DPR-35,changing TS 3/4.2 Re HPCI Instrumentation to Support Mod Planned During Refueling Outage 9 of Control Conduit for Several Valves in HPCI Indication in CR Per Reg Guide 1.97 BECO-92-097, Application for Amend to License DPR-35,revising TS Surveillance Requirements & Associated Bases for Station Batteries to Conform W/Industry Practices & Mfg Recommendations1992-08-10010 August 1992 Application for Amend to License DPR-35,revising TS Surveillance Requirements & Associated Bases for Station Batteries to Conform W/Industry Practices & Mfg Recommendations BECO-92-079, Application for Amend to License DPR-35,revising TS Sections 3/4.5,3/4.7 & 3/4.9 & Associated Bases to Incorporate LCO & SRs for Shutdown Cooling Sys & Core Standby Cooling Sys During Shutdown & Refueling Conditions1992-07-24024 July 1992 Application for Amend to License DPR-35,revising TS Sections 3/4.5,3/4.7 & 3/4.9 & Associated Bases to Incorporate LCO & SRs for Shutdown Cooling Sys & Core Standby Cooling Sys During Shutdown & Refueling Conditions BECO-92-039, Application for Amend to License DPR-35,changing TS Section 4.7 Re Primary Containment Integrity to Remove Words Each Operating Cycle for MSIV & Personnel Airlock Door Testing1992-04-0808 April 1992 Application for Amend to License DPR-35,changing TS Section 4.7 Re Primary Containment Integrity to Remove Words Each Operating Cycle for MSIV & Personnel Airlock Door Testing BECO-92-012, Application for Amend to License DPR-35.changing TS to Extend Reactor Protection Sys Instrumentation Surveillance Test Intervals from 1 Month to 3 Months to Provide for 12 & 6 H Allowable out-of-svc Times for Repairs & Tests1992-02-0707 February 1992 Application for Amend to License DPR-35.changing TS to Extend Reactor Protection Sys Instrumentation Surveillance Test Intervals from 1 Month to 3 Months to Provide for 12 & 6 H Allowable out-of-svc Times for Repairs & Tests ML20086J5411991-12-0606 December 1991 Application for Amend to License DPR-35,revising Section 3/4.9, Auxiliary Electrical Sys,To Incorporate Surveillance for Inverters Associated W/Hpci & RCIC Sys BECO-91-136, Application for Amend to License DPR-35,changing Tech Spec 3.5.D.2, RCIC Sys,Under Exigent Circumstances to Provide Limited Extension of 7-day LCO1991-10-24024 October 1991 Application for Amend to License DPR-35,changing Tech Spec 3.5.D.2, RCIC Sys,Under Exigent Circumstances to Provide Limited Extension of 7-day LCO BECO-91-127, Application for Amend to License DPR-35,revising TS Section 3/4.12, Fire Protection, Per Generic Ltr 88-12.Amend Will Relocate Most of Existing Fire Protection TSs Into Fire Protection Program Ref in FSAR1991-10-0707 October 1991 Application for Amend to License DPR-35,revising TS Section 3/4.12, Fire Protection, Per Generic Ltr 88-12.Amend Will Relocate Most of Existing Fire Protection TSs Into Fire Protection Program Ref in FSAR BECO-91-076, Application for Amend to License DPR-35,revising Thermal & Pressurization Limit Curves of Tech Specs Figures 3.6.1 & 3.6.2 & Adding New Curve to Figure 3.6.3 to Cover Operation Between 10 & 32 Effective Full Power Years1991-06-11011 June 1991 Application for Amend to License DPR-35,revising Thermal & Pressurization Limit Curves of Tech Specs Figures 3.6.1 & 3.6.2 & Adding New Curve to Figure 3.6.3 to Cover Operation Between 10 & 32 Effective Full Power Years BECO-91-052, Revised Application for Amend to License DPR-35,changing Tech Spec Re Reactor Coolant Leakage Detection Sys at Plant1991-04-10010 April 1991 Revised Application for Amend to License DPR-35,changing Tech Spec Re Reactor Coolant Leakage Detection Sys at Plant 1999-06-16
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20196D0071999-06-16016 June 1999 Application for Amend to License DPR-35,changing TS Re Reactivity Control by Incorporating Operating Requirements That Are Consistent with NEDO-21231, Banked Position Withdrawal Sequence ML20206R8101999-05-11011 May 1999 Application for Amend to License DPR-35,requesting NRC Review & Approval of Change to TS Section 3/4.5.C, HPCI, Sys,Section 3/4.5.D, RCIC Sys & Bases Associated with Sections ML20206H9651999-05-0505 May 1999 Application for Amend to License DPR-35,modifying Licensing Basis for EDG on-site Diesel Fuel Storage Requirement & Corresponding TSs ML20203B5721999-02-0505 February 1999 Redacted Application for Amend to License DPR-35, Transferring FOL & Matls License 20-07626-04 from Boston Edison to Entergy Nuclear ML20202B4821999-01-21021 January 1999 Application for Amend to License DPR-35,using New Values for post-accident Containment Pressure in Plant NPSH Analyses Performed for ECCS Pumps.Calculations Supporting Request, Encl ML20198G5731998-12-21021 December 1998 Application for Amends to License DPR-35 & Matls License 20-07626-04,transferring PNPS from Boston Edison to Entergy Nuclear.Proprietary Info Encl.Proprietary Info Withheld. Pages 608 Through 621 of Incoming Submittal Not Included ML20249C7081998-06-26026 June 1998 Application for Amend to License DPR-35,correcting Typos & Updating Bases.Changes Are Considered Administrative ML20217H2681998-03-25025 March 1998 Application for Amend to License DPR-35,modifying Tech Specs 3.6.A.1 & 4.6.A.1 as It Pertains to Primary Sys Boundary, Thermal & Pressurization Limitations & Surveillance Requirements & Basis 3/4.6.A.Calculation Encl ML20203D4851998-02-20020 February 1998 Application for Amend to License DPR-35,to Change TS 3/4.5.B & Bases to Incorporate Ultimate Heat Sink Temperature 75 F, as Required by Amend 173.Request Fulfills Commitment to Submit TS Amend for UHS Temperature by First Quarter 1998 ML20203A0781998-02-11011 February 1998 Application for Amend to License DPR-35 UFSAR Section 10.7, Clarifying Design Basis for Salt Water Svc Water Sys BECO-LTR-97-107, Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is Performed1997-10-24024 October 1997 Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is Performed BECO-97-096, Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-14331997-09-19019 September 1997 Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-1433 BECO-LTR-97-002, Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit Withheld1997-01-24024 January 1997 Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit Withheld ML20135C1271996-11-26026 November 1996 Application for Amend to License DPR-35,modifying Definition 1.M, Primary Containment Integrity, to Include All Instrument Line Flow Check Valves to Make Definition Consistent W/Lco 3/4.7.A.2.a.4 ML20108C0261996-05-0101 May 1996 Application for Amend to License DPR-35 Re Core Alteration & LCO & Surveillance Conditions Associated W/Secondary Containment BECO-96-042, Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid Control1996-05-0101 May 1996 Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid Control ML20111B4121996-05-0101 May 1996 Application for Amend to License DPR-35,revising TS to Reflect Implementation of 10CFR50 App J,Option B ML20108C0781996-05-0101 May 1996 Application for Amend to License DPR-35,relocating Administrative Controls Re QA Review & Audit Requirements of Section 6 from Plant TS to Util QA Manual BECO-LTR-96-040, Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at Plant1996-04-25025 April 1996 Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at Plant BECO-95-074, Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 111995-07-14014 July 1995 Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 11 ML20078N4751995-02-0909 February 1995 Application for Amend to License DPR-35,increasing Reactor High Water Level Isolation Trip Level Setting BECO-94-126, Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 Days1994-11-22022 November 1994 Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 Days ML20078K7881994-11-22022 November 1994 Application for Amend to License DPR-35 to TS Re Change to MSIV Leakage Requirement BECO-94-128, Application for Amend to License DPR-35,revising Suppression Chamber Water Level Operating Range,Increasing & Revises Water Level Recorder Range in Response to Commitment from Insp 50-293/91-2011994-11-22022 November 1994 Application for Amend to License DPR-35,revising Suppression Chamber Water Level Operating Range,Increasing & Revises Water Level Recorder Range in Response to Commitment from Insp 50-293/91-201 BECO-94-127, Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from Quarterly1994-11-22022 November 1994 Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from Quarterly ML20072S0741994-09-0606 September 1994 Application for Amend to License DPR-35 Re Proposed TS Change to Standby Gas Treatment & Control Room High Efficiency Air Filtration Sys Requirements ML20072S0331994-09-0606 September 1994 Application for Amend to License DPR-35 Re Proposed TS Change to Setpoint for Reactor Pressure to Isolate Shutdown Cooling Sys ML20072R9891994-09-0606 September 1994 Application for Amend to License DPR-35 Involving Proposed Administrative Change to TSs Re Control Room Annunciator. Amend Involves Relocation of Alarms for Drywell Suppression Vacuum Breakers BECO-94-098, Application for Amend to License DPR-35,requesting Change to Reflect Standard TSs Re Maintenance of Filled Discharge Pipe1994-09-0606 September 1994 Application for Amend to License DPR-35,requesting Change to Reflect Standard TSs Re Maintenance of Filled Discharge Pipe ML20069M3181994-06-0909 June 1994 Application for Amend to License DPR-35,revising TS to Increase Allowed out-of-service Time from 7 Days to 14 Days for Ads,Hpci & RCIC Sys.Proposed Change Also Made to Section 4.5.H, Maint Of...Discharged Pipe to Reflect Amend 149 ML20067B6941994-02-0909 February 1994 Application for Amend to License DPR-35,proposing Changes to TS by Revising Wording for Page 3 of License DPR-35,adding Clarifying Words to Aid Operators & Removing Obsolete Mechanical Snubber Acceptance Criterion ML20058N0131993-12-10010 December 1993 Application for Amend to License DPR-35,proposing Changes to Ts,Re Request for Changes Supporting 24 Month Fuel Cycle (Submittal 3) ML20059J1651993-11-0404 November 1993 Corrected Amend 149 to License DPR-35,correcting Administrative Errors ML20062J3311993-10-19019 October 1993 Application for Amend to License DPR-35 Proposing Changes to Remove Low Condenser Vacuum Scram in Order to Reduce Spurious Scrams,Unnecessary Plant Transients & Turbine First Stage Pressure Setpoint BECO-93-133, Application for Amend to License DPR-35 Proposing Changes to TS by Removing Scram & Group 1 Isolation Valve Closure Functions Associated W/Msl Radiation Monitors1993-10-19019 October 1993 Application for Amend to License DPR-35 Proposing Changes to TS by Removing Scram & Group 1 Isolation Valve Closure Functions Associated W/Msl Radiation Monitors ML20046D0411993-08-0909 August 1993 Application for Amend to License DPR-35,proposing 24 Month Fuel Cycle ML20044G1251993-05-20020 May 1993 Application for Amend to License DPR-35,revising TS Re MSIV Turbine Inlet Low Pressure Setpoint to Reduce Potential Spurious Isolations Caused by Existing Higher Setpoint.Ge Repts MDE-70-0586 & NEDO-31296 Encl ML20128P3651993-02-11011 February 1993 Application for Amend to License DPR-35,changing TS to Increase Allowed Fuel Assembly Storage Cells from 2,320 to 3,859 & Changing Max Loads Allowed to Travel Over Spent Fuel Assemblies to 2,000 Lbs.Holtec Rept HI092925 Encl ML20127P5311993-01-25025 January 1993 Amend 145 to License DPR-35,revising TS SRs for Station Batteries by Replacing Rated Load Discharge Test W/Svc Discharge Test once-per-cycle & Performance Discharge Test Every Five Yrs BECO-92-126, Application for Amend to License DPR-35,revising TS Sections 1.0,4.3,4.4,4.5,4.6,4.7 & Associated Bases to Conform SRs for ASME Code Class 1,2 & 3 Pumps & Valves to IST Program, Per 10CFR50.55a(g)(5)(ii)1992-10-30030 October 1992 Application for Amend to License DPR-35,revising TS Sections 1.0,4.3,4.4,4.5,4.6,4.7 & Associated Bases to Conform SRs for ASME Code Class 1,2 & 3 Pumps & Valves to IST Program, Per 10CFR50.55a(g)(5)(ii) BECO-92-121, Application for Amend to License DPR-35,proposing Changes to TS Section 2.1, Safety Limits, to Reflect Use of Advanced GE-10 Fuel Design & Section 3.3.C, Scram Insertion Times, to Correct Error in Control Rod Scram Insertion Time1992-10-23023 October 1992 Application for Amend to License DPR-35,proposing Changes to TS Section 2.1, Safety Limits, to Reflect Use of Advanced GE-10 Fuel Design & Section 3.3.C, Scram Insertion Times, to Correct Error in Control Rod Scram Insertion Time BECO-92-116, Application for Amend to License DPR-35,consisting of Temporary Change to TS Sections 3.7.B.1.C,3.7.B.1.e, 3.7.B.2.a & 3.7.B.2.C,requiring Both Trains of SGTS to Be Operable During Irradiated Fuel Handling Operations1992-10-0808 October 1992 Application for Amend to License DPR-35,consisting of Temporary Change to TS Sections 3.7.B.1.C,3.7.B.1.e, 3.7.B.2.a & 3.7.B.2.C,requiring Both Trains of SGTS to Be Operable During Irradiated Fuel Handling Operations BECO-92-101, Application for Amend to License DPR-35,changing TS 3/4.2 Re HPCI Instrumentation to Support Mod Planned During Refueling Outage 9 of Control Conduit for Several Valves in HPCI Indication in CR Per Reg Guide 1.971992-08-17017 August 1992 Application for Amend to License DPR-35,changing TS 3/4.2 Re HPCI Instrumentation to Support Mod Planned During Refueling Outage 9 of Control Conduit for Several Valves in HPCI Indication in CR Per Reg Guide 1.97 BECO-92-097, Application for Amend to License DPR-35,revising TS Surveillance Requirements & Associated Bases for Station Batteries to Conform W/Industry Practices & Mfg Recommendations1992-08-10010 August 1992 Application for Amend to License DPR-35,revising TS Surveillance Requirements & Associated Bases for Station Batteries to Conform W/Industry Practices & Mfg Recommendations BECO-92-079, Application for Amend to License DPR-35,revising TS Sections 3/4.5,3/4.7 & 3/4.9 & Associated Bases to Incorporate LCO & SRs for Shutdown Cooling Sys & Core Standby Cooling Sys During Shutdown & Refueling Conditions1992-07-24024 July 1992 Application for Amend to License DPR-35,revising TS Sections 3/4.5,3/4.7 & 3/4.9 & Associated Bases to Incorporate LCO & SRs for Shutdown Cooling Sys & Core Standby Cooling Sys During Shutdown & Refueling Conditions BECO-92-039, Application for Amend to License DPR-35,changing TS Section 4.7 Re Primary Containment Integrity to Remove Words Each Operating Cycle for MSIV & Personnel Airlock Door Testing1992-04-0808 April 1992 Application for Amend to License DPR-35,changing TS Section 4.7 Re Primary Containment Integrity to Remove Words Each Operating Cycle for MSIV & Personnel Airlock Door Testing BECO-92-012, Application for Amend to License DPR-35.changing TS to Extend Reactor Protection Sys Instrumentation Surveillance Test Intervals from 1 Month to 3 Months to Provide for 12 & 6 H Allowable out-of-svc Times for Repairs & Tests1992-02-0707 February 1992 Application for Amend to License DPR-35.changing TS to Extend Reactor Protection Sys Instrumentation Surveillance Test Intervals from 1 Month to 3 Months to Provide for 12 & 6 H Allowable out-of-svc Times for Repairs & Tests ML20086J5411991-12-0606 December 1991 Application for Amend to License DPR-35,revising Section 3/4.9, Auxiliary Electrical Sys,To Incorporate Surveillance for Inverters Associated W/Hpci & RCIC Sys BECO-91-136, Application for Amend to License DPR-35,changing Tech Spec 3.5.D.2, RCIC Sys,Under Exigent Circumstances to Provide Limited Extension of 7-day LCO1991-10-24024 October 1991 Application for Amend to License DPR-35,changing Tech Spec 3.5.D.2, RCIC Sys,Under Exigent Circumstances to Provide Limited Extension of 7-day LCO BECO-91-127, Application for Amend to License DPR-35,revising TS Section 3/4.12, Fire Protection, Per Generic Ltr 88-12.Amend Will Relocate Most of Existing Fire Protection TSs Into Fire Protection Program Ref in FSAR1991-10-0707 October 1991 Application for Amend to License DPR-35,revising TS Section 3/4.12, Fire Protection, Per Generic Ltr 88-12.Amend Will Relocate Most of Existing Fire Protection TSs Into Fire Protection Program Ref in FSAR 1999-06-16
[Table view] |
Text
. .e
,' . ?S BOSTON EDISON fNgom Nuclear Fowet Station FurcLy Hi;l noad Pivmouth. Manachusetts 02300 E. Thomas Boulette, PhD veo hesdent Nudo opnrotons ama siamn owtm October 8. 1992 BECo 92- 116 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 License DPR-35 Docket 50-293 Technical Snecification Tenmgrary Relief Reouest The Boston Edison Company requests a temporary change to Pilgrim Nuclear Power Station Technical Specification sections 3.7.B.1.C, 3.7.B.1.e, 3.7.B.2.a, and 3.7.8.2.C. These sections require both trains of the Standby Gas Treatment System (SGTS) and Control Room High Efficiency Air filtration System (CRiiEAF) to be operable for the initiatinn of fuel movement and during fuel handling operations involving irradiated fuel. The relief supports a planned sequencing of safety -ustems maintenance and/or refurbishment during our next refueling outage, Rf0 #9. Attachment A. "Compari;on of Existing And Proposed Requirements for SGTS and CRHEAf" summarizes existing and proposed requirements.
l The requested changes are described in Attachment B. Revised technical specification pages are included in Attachment C, and existing pages marked up to show the proposed changes are included in Attachment D. A single line diagraia depicting a portion of the station electrical 4.16 KV and 480 V distribution system is included as Attachment E, and a summary of refueling outage activities is included as Attachment F.
Ob000J b 30ttLcN E. T. Boulette Commonwealth of Massachusetts)
County of Plymouth)
Then personally appeared before me, E. T. Boulett% who being duly sworn; did I state that he is Vice President - Nuclear Operations and Station Director of Boston Edison Company and that he is duly authorized to execute and file the submittal contained herein in the name and on behalf of Boston Edison Company and that the statements in said submittal are true to the best of his knowledge and belief.
My commission expires: dd4{ #ff jdh(&bh DATE' NOTARY.UBUC JDK/cic/tschange 9210130167 921000 cc: See Page 2 PDR P
ADOCK 05000293 PDR
[ 8pf j,
' BOSiON EDIsoft COMPANY U. S. tiuclear Regulatory Commission Page 2 cc Mr. R. Laton, Project Manager Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Mail Stop: 1401 U. S. lluclear Regulatory Commission 1 White flint North 11555 Rockville Pike Rockville, MD 20852 U. S. lluclear Regulatory Commission Region 1 475 Allendale Road King of Prussic, PA 19406 Senior NRC Resident inspector Pilgrim Nuclear Power Station Mr. Robert M. Hallisey, Director Radiation Control Program Massachusetts Department of Public Health 305 South Street Jamaica Plain, MA 02130
..____.._m_.-m_ _ _______ __-__ _-.__-_. _.-
ATTACHMENT A .
COMPARISON OF EXISTING AND PROPOSED TECHNICAL SPECIFICATION REQUIREHENTS FOR SGTS AND CRHEAF PROPOSED TECH SPEC 5 PROPOSED TECH SPECS .
EXISTING TECH SPECS DURING REFUELING IF DURING REFUELING IF EQUIPMENT DURING REFUELING "B" SAFETY BUS 0.0.5 "A" SAFETY BUS 0.0.5
'"A" SGTS/CRHEAF ALL NECESSARY NORMAL AND I NORMAL AND 2 OUT OF 3 I NORMAL POWER SOURCE EMERGENCY POWER SOURCES EMERGENCY POWER SOURCES, AS LISTED BELOW:
NORMAL NORMAL NORMAL
- STARTUP TRANSFORMER - STARTUP TRANSFORMER - STARTUP TRANSFORMER OR OR OR
- UNIT AUXILIARY (BACK- - UNIT AUXILIARY (BACK- - UNIT AUXILIARY (BACK-FEED MODE) FEED MODE) FEED MODE)
EMERGENCY EMERGENCY "A" EDG -
"A" EDG AND EITHER
- S/D TRANSFORhER OR
- BLACK 0UT D/G l
l "B" SGTS/CRHEAF ALL NECESSTRY NORMAL AND I NORMAL AND 2 OUT OF 3 l EMERGENCY POWER SOURCES 1 NORMAL POWER SOURCE EMERGENCY POWER S0l'RCES, l AS LISTED BELOW: AS LISTED BELCW:
NORMAL NORMAL NORMAL
- STARTUP TRANSFORMER - STARTUP TRTNSFORMER l - STARTUP TRANSFORMER OR OR I CR
- UNIT AUXILMRY (BACK- - UNIT AUXILIARY (BACK- l - UNIT AUXILIARY (BACK-FEED MODE) FEED MODE) ! FEED MODE)
EMERGENCY EMERGENCY "B" EDG -
"B" EDG AND EITHER
- S/D TRANSFORMER OR
- BLACK 0UT D/G
- n. .
, c m M
ATTACHMENT B Etpfosed Channes The proposed changes to Sections 3.7.B.I.c, 3.7.B.1.e, 3.7.B.2.a. and 3.7.B.2.c add an asterisk referencing a footnote granting relief to allow only one train of the Standby Gas Treatment System (SGTS) and one train of the Control Room High Efficiency Air filtration System (CRHEAF) operable prior to or during activities involving irradiated fuel movement or operations conducted over irradiated fuel during RF0 #9.
Reason for Chanae The Pilgrim Station Technical Specifications require both trains of the SGTS and CRHEAF systems to be operable during irradiated fuel handling operations. In addition, the definition of " operable" requires both normal and emergency electrical -
power sources be available to support the SGTS and CRHEAF function (s).
During Rf0 #9 we are implementing an outage work management concept for Piljrim-Station that takes an entire equipment loop out nf service for maintenance ,
activities. After work is completed on that loop it will be returned to service and the other equipment loop will be removed from service for-maintenance. Attachment F provides a summary schedule of these activities.
The outage work management concept conflicts with Technical Specifications when handling irradiated fuel because removal of an equipment loop makes related emergency electric power source (diesel generator and associated 4kV bus) unavailable to supply power to the associated trains of SGTS and CRHEAF. The .
existing LCO allows a 7 day period to restore the system to operable or discontinue activities involving irradiated fuel. Relief is requested to address this confict-by allowing irradiated fuel activities to commence and continue for a period greater
-than 7 days with the emergency power source out of service.
Safety Considerations The SGTS is one of four subsystems of the Secondary Containment System (SCS). The other subsystems are the Reactor Building, the Reactor Building Isolation and Control System'(RBICS), and the main stack. The SCS_ surrounds the refueling facilities and is designed to provide primary containment for the postulated refueling-accident.
The .SCS uses.four different features to mitigate t_he consequences of a postulated fuel handling accident. The first feature is-a negative pressure barrier which minimizes the ground level release of fission products by exfiltration. The second-feature-is a low leakage containment volume which provides a holdup time for fission
-product decay prior to release. The third feature is-the removal of particulates and iodines by filtration prior to release.
Page 1
=__ ;
..l a
. ATI&CHMENT B The fourtn-feature is the exhausting of the secondkry containment atmosphere through-an elevateo release point which aids in dispersiofof the effluent-by atmospheric diffusion. Each of the features is provided by aidifferent combination of '
-subsystems: the first by the-Reactor Building, the RBICS, and the SGTS exhaust-fans'; the second by the Reactor Building and the RBICS; the third by the SGTS filters; and the fourth by the mair, stack.
The safety objective of the SC3 is to limft the release of radioactive ruaterials to the environs ensuring offsite doses from a postulated DBA will be below the guideline values of 10CFR100.
The safety design bases of the SCS satisfying this safety objective states that the- i SCS shali be designed to be sufficiently leaktight to allow the Standby Gas ,
Trcatment System (SGT5) to reduce the Reactor Building pressure to a minimum !'
subatmospheric pressure of 0.25 inch of water, under neutral wind conditions, when the SG5 fans are exhausting Reactor Building atmosphere ct a maximum of 4,000 f t3/ min.
PNPS Tachnical Specifications Bases state that only one of the two Standby Gas Treatment Systems is needed to maintain the secondary containment at'a 0.25 inch of
~
water negativo pres:,ure upon containment isolation. During Rf0 #o ") intend to i maintain at least one train of SGTS operable with both normal ar- gency safety -i related power sources available, satisfying the need for seconda, ;ntainment.The !
other train will be available using non-safety related power sourt..s but will not-have an emergency backup source. ,
SG1S is only required for fuel handling accidents during refueling operations.
During refueling operations the most limiting postulated event is the worst case fuel handling accident coincident with a loss of offsite power and a random failure of a SGTS component in the train being fed from the emergency diesel generator. The probability of this comb 5ation of events is extremely low, i'
We have restricted fuel movement for 5 days following reactor shutdown as a condition of employing this relief. The 5 day restriction provides decay time for
~
the irradiat d fuel.
The CRHEAF system's safety func.iton is to maintain Control Room habitability after an event that relcases radioactive material. During fuel movement' operations, damagt to irradiated fuei would be tne Event CRHEAF addresses.
The corrpensatory measures # scribed below apply to both SGTS and.CRHEAF and will be adhered to in support of this- proposed- temporary relief. These coinpensatory measures give added assurance SGTS and CRHEAF will not be needed or will perform their designad function although one train will not be operable within the strict application of existing Technical Specification requirements.
Compen,satory Measures
- Fuel movement will not osur until 5 days following reactor shutdown.
. Fuel movement will not occur until the reactor vessel is flooded up to elevation 114' to provide an enlarged con' ant inventory.
Page E
. ATTACHMENT B
. The train of SGTS and CRHEAF without its safety-related bus and without its emergency diesel generator will have power supplied from a normal offsite source via a non safety-related bus. The normal offsite sources consist of either the Startup Transformer or Unit Auxiliary Transformer (Back-feed Mode).
- Prior to and duriag fuel movement, the Station Blackout (SBO) Diesel Generator or the Shutdown Transformer will be required to be operable. This will provide another source of emeroency power to the .afety-related bus still in service, should normal sources of offsite power beccme unavailable.
Determination of No Sianificant Hazards Considere+c_
The Code of Federal Regulations (10CFR50.91) ret . . licensees requesting an amendment to provide an anal) 4 .:ing the .tandards in 10CFR50.92, that determines whether a significant hazards consideration exists. The following analysis is provided in accordance with 10CFR50.91 and 10CFR50.92 for the proposed amendment requesting temporary relief from Technical Specification sections 3.7.B.1 and 3.7.B.2 during acti /ities involving irradiated fuel .
- 1. The operation of Pilgrim Station in accordance with the proposed amendment will not involve a significant increase in the probability or consequences of an accident previously evaluated Technical Specifications 3.7 B.1 and 3.7.B.2 restrict the movement of irradiated fuel when only one tr ain of SGTS or one train of CRHEAF are operable. Irradiated fuel movement may not begin and may only continue for seven days wher the Limiting Condition of Operation is entered.
The temporary relief from these reetrictions does not involve a significant increase in the probability or consequences of an accident previously evaluated because compensatory measures will be in place and because the relief is for a finite, relatively short period.
During the requested relief period, fuel movement will not coinmence until 5 days following plant shutdown and the reactor vessel will he flooded-up to elevation 114'. The 5 day period provides decay-time be' 3 irradiated fuel movement begins. Flooding-up to elevation 114' provides on enlarged inventory reducing the possibility of a loss-of-coolant event exposing fuel such that radioactive g; 2es are produced, an event SBGTS and CRHEAF could mitigate.
Other compensatory measures include requiring the SB0 diesel or the shutdown transformer .o be operable prior to and during fuel movement. This adds defense-in-depth by making available another power supply to the in-service safety-re'>ted bus. Also, the substitution of a non-safety power supply to the SGTS and CRHEAF " inoperable" systems while their safety-grade bus is out-of-service for maintenance will provide offsite power to the " inoperable" train. While this electrical supply is not safety-grade, it is reliable and capable of powering the SGTS and CRHEAF systems. The components of the
" inoperable" trains will be available with power from an alternate power source. The compensatory connection to the non-safety grade bus.gives added confidence these trains can perform their design function although they are not " operable" as defined by Technical Specifications.
Page 3
ATTACHMENT B Operating Pilgrim in accordance with this relief request does not involve a significant increase in the probability or consequences of an accident previously analyzed because the relief is effective for a limited time and because ccmpensatory measures will be in force to: restrict the commencemtnt of irradiated fuel handling or new fuel handling over the spent fuel or core until 5 days following reactor shutdown; provide a reliable source of power to the " inoperable" SGTS and CRHEAf systems; provide an enlarged coolant inventory to protect irradiated fuel from the effects of an inadvertent draindown of the vessel; and provide an additional source of emergency power to the active SGTS and CRHEAF systems by ensuring the operability of the SB0 diesel generator or the Shutdown Transformer.
- 2. The operation of Pilgrim Station in accordance with the proposed amendment will not create the possibility of a new or different kind of acciuent from any accident previously evaluated. -
Planned maintenance activities require removing a safety-related bus and emergency diesel generator powering a train of SGTS and CRHEAF from service.
The redundant trains are not affected. The affected trains of SGTS and CRHEAF will be connected to a non-safety bus, allowing them to operate but not allowing them to be considered operable under the purview of Technical Specifications. The relief requested by this amendment allows refueling activities to commence with one train of SGTS and CRHEAF fully operable and the other train available but not powered by its safety grade bus and associated emergency diesel generator. Compensatory measures will be in effect during refueling activities. The proposed relief does not create the possibility of a new or different kind of accident from the fuel-drop accident previously analyzed. Therefore, operating Pilgrim in accordance with this change will not create the possibility of a new or different kind of accident from any accident previously analyzed.
- 3. The operation of Pilgrim Station in accordance with the proposed amendment will not involve a significant reduction in the margin of safety.
SGIS and CRHEAf contribute to the margin of safety by supporting the Secondary Containment System during fuel-handling by mitigating the consequences of a fuel-handling event. Relief from the requirements to have both trains of SGTS and CRHEAF operable prior to or du 'ing fuel movement activities for a limited time period does not involve a sigsificant reduction in the margin of safety because the first line of defense, ti.' other SGTS and CRHEAF trains, will be operable. The redundant trains will lse be powered and operable in all ways except the " operable" concept required cy Technical Specification. ,
Hence, the actual condition of the equipment allowing it to meet its design function except by the Technical Specification concept of operable, the limited time period allowed by the relief, and the described compensatory measures that will be in effect when the relief is employed, constrain the potential impact on the margin of safety by using the relief; therefore, operating Pilgrim in accordance with this proposed Technical Spccification relief request does not involve a significant reduction in the margin of safety.
Page 4
x; . .
, ATTACHMENT!!
?This proposed change has been reviewed and reconaended- for-approval by the-- .
- . -Operations Review committee, and. reviewed by the Nuclear Safety Review ar.J_ Audit -
~-Committee.
Schedule of Change This change will be implemented within 30 days following BEco's-receipt of its approval by the NRC.
?-
9 4
Page 5
,