 Issue dateTitleTopic
ML20216G58724 September 1999Corrected Page 1 to Amend 182 to License DPR-35,reflecting New Licensee,Entergy
ML20209G37815 July 1999Amend 182 to License DPR-35,modifying TS Table 4.6-3, Reactor Vessel Material Surveillance Program Withdrawal Schedule
ML20196D00716 June 1999Application for Amend to License DPR-35,changing TS Re Reactivity Control by Incorporating Operating Requirements That Are Consistent with NEDO-21231, Banked Position Withdrawal SequenceScram Discharge Volume
Overtravel
ML20206R81011 May 1999Application for Amend to License DPR-35,requesting NRC Review & Approval of Change to TS Section 3/4.5.C, HPCI, Sys,Section 3/4.5.D, RCIC Sys & Bases Associated with Sections
ML20206H9655 May 1999Application for Amend to License DPR-35,modifying Licensing Basis for EDG on-site Diesel Fuel Storage Requirement & Corresponding TSsSafe Shutdown
Abnormal operational transient
Earthquake
ML20203B5725 February 1999Redacted Application for Amend to License DPR-35, Transferring FOL & Matls License 20-07626-04 from Boston Edison to Entergy NuclearSafeguards Contingency Plan
ML20202B48221 January 1999Application for Amend to License DPR-35,using New Values for post-accident Containment Pressure in Plant NPSH Analyses Performed for ECCS Pumps.Calculations Supporting Request, EnclUltimate heat sink
ML20198H55921 December 1998Amend 180 to License DPR-35,authorizing Boston Edison Co to Change Updated FSAR Section 10.7, Salt Service Water System, to Address Single Failure Vulnerability
ML20198G57321 December 1998Application for Amends to License DPR-35 & Matls License 20-07626-04,transferring PNPS from Boston Edison to Entergy Nuclear.Proprietary Info Encl.Proprietary Info Withheld. Pages 608 Through 621 of Incoming Submittal Not Included
ML20198A23211 December 1998Amend 179 to License DPR-35,revising TSs 3/4.5.F.1, Core & Containment Cooling Sys, to Extend Allowed Outage Time for Emergency DieselsShutdown Margin
High Radiation Area
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
Offsite Circuit
Water hammer
ML20195B89310 November 1998Amend 178 to License DPR-35,modifying Various Pilgrim Nuclear Power Station TS Pages to Correct Typographical Errors,Remove Inadvertent Replication of Info & Update Various Bases SectionsOvertravel
ML20236X46331 July 1998Amend 177 to License DPR-35,relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Offsite Dose Calculation Manual,Iaw Recommendations of GL 89-01Safe Shutdown
Shutdown Margin
Packing leak
High Radiation Area
Offsite Dose Calculation Manual
Scram Discharge Volume
Annual Radiological Environmental Operating Report
Safeguards Contingency Plan
Fuel cladding
Pressure Boundary Leakage
Fire Protection Program
Unidentified leakage
ML20236U97328 July 1998Amend 176 to License DPR-35,changing Plant TS 3/4.5.B Bases to Incorporate Ultimate Heat Sink Temp to 75 F as Required by Amend 173Ultimate heat sink
ML20249C70826 June 1998Application for Amend to License DPR-35,correcting Typos & Updating Bases.Changes Are Considered Administrative
ML20249B83119 June 1998Amend 175 to License DPR-35,modifying Plant TS Section 3.6.A.4 W/Respect to Monitoring Requirements for Vessel Flange & Adjacent Shell Differential Temp During Heatup & CooldownHydrostatic
ML20217H26825 March 1998Application for Amend to License DPR-35,modifying Tech Specs 3.6.A.1 & 4.6.A.1 as It Pertains to Primary Sys Boundary, Thermal & Pressurization Limitations & Surveillance Requirements & Basis 3/4.6.A.Calculation EnclHydrostatic
ML20203D48520 February 1998Application for Amend to License DPR-35,to Change TS 3/4.5.B & Bases to Incorporate Ultimate Heat Sink Temperature 75 F, as Required by Amend 173.Request Fulfills Commitment to Submit TS Amend for UHS Temperature by First Quarter 1998Ultimate heat sink
ML20203A07811 February 1998Application for Amend to License DPR-35 UFSAR Section 10.7, Clarifying Design Basis for Salt Water Svc Water SysLoss of Offsite Power
ML20198R70430 October 1997Amend 174 to License DPR-35,adding Footnote to TS 3.7.A.5, Primary Containment. Footnote Provides one-time Exception to Reverse Flow Testing Requirement for Containment Isolation Check Valve 30-CK-432
BECO-LTR-97-107, Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is Performed24 October 1997Application for Emergency Amend to License DPR-35,changing TS 3.7.A.5 as Pertains to Periodic Surveillance Testing of Check Valve 30-CK-432.Exemption from LCO Footnote Provides Would Expire When Testing Is PerformedEnforcement Discretion
Missed surveillance
Grace period
BECO-97-096, Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-143319 September 1997Application to Propose Changes to Tss,Relocating Radioactive Effluent TS & Radiological Environ Monitoring Program to Odcm,Per GL 89-01 & NUREG-1433High Radiation Area
Grab sample
Offsite Dose Calculation Manual
ML20148U6403 July 1997Amend 173 to License DPR-35,evaluating Unreviewed USQ Associated W/Operation of Plant to Credit Use of Containment Overpressure to Suppl NPSH for Emergency Core Cooling Pumps & Increase Accident Analysis Design UHS TempUltimate heat sink
ML20140B02028 May 1997Amend 172 to License DPR-35,revising TSs Definition 1.M, Primary Containment Integrity, Note 6 on Table 3.2.A for High Flow Main Steam Line Instrumentation & Table 3.2.D for TypoEarthquake
ML20137R8057 April 1997Amend 171 to License DPR-35,revises TS Safety Limit 2.1.2, Minimum Critical Power Ratio & Associated Bases Section & Note 5 to Table 3.2.C.1, Instrumentation That Initiates Rod BlocksAnticipated operational occurrence
Fuel cladding
ML20147D87310 February 1997Amend 170 to License DPR-35,revising Definition of operable- Operability,Tss & Associated Bases Section for TSs 3.9.B.2 & 3.9.B.3
BECO-LTR-97-002, Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit Withheld24 January 1997Application for Amend to License DPR-35,requesting Rev to Safety Limit Minimum Critical Power Ratio.Encl Attachment 1 Re Description & Evaluation of Proposed TS Change to Min Critical Power Ratio Safety Limit WithheldSafety Limit Minimum Critical Power Ratio
Affidavit
ML20135C12726 November 1996Application for Amend to License DPR-35,modifying Definition 1.M, Primary Containment Integrity, to Include All Instrument Line Flow Check Valves to Make Definition Consistent W/Lco 3/4.7.A.2.a.4
ML20134L69312 November 1996Amend 168 to License DPR-35,relocating Administrative Controls Re QA Review & Audit Requirements of Section 6, TS 6.5.B.8
ML20128N8564 October 1996Amend 167 to License DPR-35,changing TSs to Implement 10CFR50,App J,Option BExcess Flow Check Valve
ML20116L31412 August 1996Amend 166 to License DPR-35,modifying Definition of Core Alteration & Limiting Condition for Operation,Surveillance Conditions & Bases Section Associated W/Ts 3.7.C
ML20108C0261 May 1996Application for Amend to License DPR-35 Re Core Alteration & LCO & Surveillance Conditions Associated W/Secondary Containment
ML20108C0781 May 1996Application for Amend to License DPR-35,relocating Administrative Controls Re QA Review & Audit Requirements of Section 6 from Plant TS to Util QA Manual
ML20111B4121 May 1996Application for Amend to License DPR-35,revising TS to Reflect Implementation of 10CFR50 App J,Option BIntegrated leak rate test
BECO-96-042, Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid Control1 May 1996Application for Amend to License DPR-35,revising Note 7 to Table 3.1.1,note 6 to Table 3.2.C.1 & Section 3/4.4, Standby Liquid ControlShutdown Margin
BECO-LTR-96-040, Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at Plant25 April 1996Application for Amend to License DPR-35,proposing Part of Overall Effort to Improve Outage Performance at PlantProbabilistic Risk Assessment
Large early release frequency
Loss of Offsite Power
Offsite Circuit
Control Room Habitability
ML20096H26923 January 1996Amend 165 to License DPR-35,revising TS to Convert Current percentage-based Scram Time Limits to notch-based Limits in TS 3.3.C & Updating Bases for notch-based Limits in TS 3/4.3.C
ML20092C57111 September 1995Corrected Tech Spec Page to Amend 164 to License DPR-35, Changing Control Value for Reactor High Pressure Trip Level Setting 76 Psig
BECO-95-074, Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 1114 July 1995Application for Amend to License DPR-35,reflecting Use of Advanced GE-11 Fuel Design in Cycle 11Fuel cladding
ML20086A15522 June 1995Corrected TS Pages of Amend 164 to License DPR-35 for Plant
ML20085K97915 June 1995Amend 164 to License DPR-35,revises Reactor High Water Level Trip Level Setting for Group 1 Isolation
ML20081L88927 March 1995Amend 162 to License DPR-35,reducing Reactor Pressure Setpoint at Which Shutdown Cooling Sys Automatically IsolatesRestart
ML20081J03222 March 1995Amend 160 to License DPR-35 Re Changes to TS to Revise Allowable Leak Rate MSIVs
ML20081H89422 March 1995Amend 161 to License DPR-35,re Changes to Listed TS & Addition of Sections 3.7.B.1.f & 3.7.B.2.e to Require That Both Trains of Standby Gas Treatment & CR Air Filtration Sys OperableShutdown Margin
ML20080T7168 March 1995Amend 159 to License DPR-35,removing TS Requirement, Instrumentation That Initiates Control Rod Blocks to Have Scram Discharge Instrument Volume-Scram Trip Bypassed Operable in Run & Startup Modes
ML20080J72016 February 1995Amend 158 to License DPR-35,relocating Alarms for Drywell to Suppression Chamber Vacuum Breaker to Different Annunciator Panel
ML20078N4759 February 1995Application for Amend to License DPR-35,increasing Reactor High Water Level Isolation Trip Level SettingMoisture Carryover
ML20078Q3282 February 1995Amend 157 to License DPR-35,removing TS Section 4.5.H.4 Which Requires Testing & Calibration of Pressure Switches in Certain ECCS LinesWater hammer
BECO-94-126, Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 Days22 November 1994Application for Amend to License DPR-35,increasing Current EDG Allowed out-of-svc Time in Specification 3.5.F from 72 H to 7 DaysProbabilistic Risk Assessment
Loss of Offsite Power
Offsite Circuit
ML20078K78822 November 1994Application for Amend to License DPR-35 to TS Re Change to MSIV Leakage Requirement
BECO-94-127, Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from Quarterly22 November 1994Application for Amend to License DPR-35,revising Mode Conditions Under Scram Discharge Instrument vol-scram Trip Bypass in Table 3.2.C.1,required to Be Operable & Changes Associated Functional Test Frequency from QuarterlyScram Discharge Volume