rr -
0 4
l L*
U.
l I
i CRYSTAL RIVER UNIT #3 ANNUAL OPERATING REPORT JANUARY I - DECEMBER 31,1984 Nuclear Safety and Reliability Crystal River Unit #3
~
8504160039 841231 PDR ADOCK 05000302
[{ Ag j R
REPORT ON ANNUAL PERSONNEL EXPOSURE FOR 1984 v"T
REPORT YEAR - 1984 STANDARD FORMAT FOR REPORTING NUMBER OF-PERSONNEL AND MAN-REM BY WORK AND JOB FUNCTION
- PERSONNEL ( >100 MREM)
TOTAL MAN-REM WORK & JOB FUNCTION UTILITY. STATION CONTRACT UTILITY STATION CONTRACT.
Reactor Operations & Surveillance
~
Maintenance & Construction 0
1 0
.071
.316
.110 Operations 0
25
-0 0.000 6.934
.480 Haalth Physics & Lab 0
0 0
.084
.263 0.000 Supervisory & Office Staff 0
1 0
.204
.563
.298 Engineering Staff 0
0 0
.243
.036
.221 Routine Plant Maintenance Maintenance & Construction 3
33
'61 1.103 9.837
'14.949 Opera.tions 0
0 0
.015
.377 0.000
. Health Physics & Lab 0
12 17
.036 2.921 4.283 Supervisory & Office Staff 0
0 2
0.000
.272
.725 Engineering Staff 0
2 0
.101
.451
.299
' Inservice Isspection Madntenance & Construction 0
0 0
0.000
.019
.002 Operations 0
0 0.
.091 0.000 0.000 Health Physics & Lab 0
0 0
0.000 0.000 0.000 Supervisory &' Office Staff 0
0 0
.032 0.000 0.000 Engineering Staff 1
0 0
.225.
.132
.054
~
-Special Plant Maintenance
. Maintenance & Construction 0
0 0
.000
.000
.000 Operations.
0 0-0 0.000 0.000 0.000-Health Physics & Lab.
0 0
0 0.000 0.000 0.000' Supervisory & Office Staff 0
0 0
0.000 0.000 0.000 Engineering Staff-0 0
0 0.000
.000.
.000 Waste Processing Maintenance & Construction 0
0-0 0.000
.006
.016 Operations.
0 1
0 0.000
.524 0.000 Health Physics & La'o 0
3 0
0.000 1.598 0.000
. Supervisory & Office Staff 0
'O 1
0.000
.035
.669 Engineering Staff 0
0 0
0.000
.002
.004 Refueling
. Maintenance-& Construction 0
0 0
0.000
.000
.000
. Operations.
0 0
0 0.000 0.000 0.000 Health Physics & Lab 0-0 0
0.000 0.000 0.000.
- Supervisory & Office Staff 0
0 0
0.000-0.000 0.000 Engineering Staff.
0 0
0 0.000-
.000
.000
-Totals
. Maintenance & Construction 3
34 61 1.174 10.177
'15.078 Operations 0
26 0
.106 7.835
.480 Health Physics & Lab 1
15 17
.120 4.696
.4.283-Supervisory & Office Staff 0
1 3
.236
.870 1.692 Engineering Staff 1
2 0
.568
.619
.580
- GRAND TOTALS S
78 81 2.204 24.283 22.070
e WHOLE BODY EXPOSURES FOR CALENDAR YEAR 19_8_4 I
Licensee Reporting (Name & Address)
NRC License No(s).
Florida Power Corporation Crystal River Unit #3 DPR-72 P.O. Box 1228 crverni n4un, vi
,7979 If personnel monitoring was not required to be provided to any individual O during the year, checking this box will constitute a negative report
/
indicating that such personnel monitoring was not required.
OTHERWISE, COMPLETE THE FOLLOWING TABLE:
Estimated Annual Whole Body Exposure Number of Individuals Ranges * (Rems) in Each Range No Measurable Exposure iu9 Measurable Exposure Less Than 0.1 385 0.1 -- 0.25 17s 0.25 -- 0.5 y
0.5 -- 0.75 9
1 0.75 -- 1 0
1 -- 2 0
2 -- 3 3 -- 4 0
4 -- 5 0
5 -- 6 n
6 -- 7 n
0 7 -- 8 8 -- 9 0
9 -- 10 0
0 10 -- 11 11 -- 12 o
>12 0
Total number of individuals reported 1691 The above infonnation is submitted for the total number of individuals for whom personnel monitoring was (check one):
O required under 10 CFR 20.202(a) or 10 CFR 34.33(a) during the calendar year.
@ provided during the calendar year.
- Individual values exactly equal to the values separating exposure ranges shall be reported in the higher range.
REPORT ON REACTOR VESSEL MATERIAL SURVEILLANCE CAPSULES AS REQUIRED BY STS 6.9.1.5(b)
Reporting Period January 1,1984 to December 31,1984 Capsules Currently Installed Holder Capsules Closure Assembly Tube Installed (1)
Installed WZ T-Empty Not Installed B-Empty ZY T-CR3-C 27-113-2007-60-3 B-CR3-A YZ T-OCI-C 27-113-2007-60-2 B-OCI-B YX T-OCII-E 27-113-2007-60-1 B-OCIII-D XV T-CR3-E 27-113-2007-60-5 B-CR3-D WX T-TMI-IC 27-113-2007-60-4 B-CR3-F i
l-The reactor head was not removed during 1984 and therefore no changes have occurred.
l Ownership of Capsules Florida Power Corporation:
CR3-C, CR3-A, CR3-E, CR3-D, CR3-F, CR3-L1, CR3-L2 Duke Power Company:
OCI-C, OCI-B, OCII-E, OCIII-D Metropolitan Edison Company: TMI-IC Irradiation Location See Holder Tube Listing above.
Note:
(1) T = top, B = bottom
.. ~
REPORT ON PRODUCTION FACILITY CIIANGES, TESTS, AND EXPERIMENTS i
l
MAR 76-11-18 Completed 01/26/84 Added two security flood lights to the intake structure area.
MAR 77-01-28 Completed 08/28/84 Installed a 6" relief / vent line from the GS Rupture Disc to the 18" Atmosphere Drain Tank Vent line.
MAR 77-06-28 Completed 01/26/84 Installed an auto fill line (upstream of CIV 69) through a 20 psig regulator to the Cl pump suction.
MAR 77-07-18 Completed 01/26/84 Added a sample point at WDV 330 upstream of PT 123 on the spent resin discharge line.
MAR 78-03-15 Completed 10/17/84 Relocated the following from WD Neutralizer Tank (WDT-1) outlet line to the recirculation line:
1.
Flow indicator (WD-88-FI) 2.
Flow orifice (WD-88-FO) 3.
Isolation valves (WDV 266 & 352)
MAR 78-05-14 Completed 04/02/84 Upgraded pump WDP-19B to Model G.D.-10K-152H-15.
MAR 78-05-14A Completed 04/22/84 Made T-MAR #78-05-14 a permanent installation.
MAR 78-07-10 Completed 05/29/84 Installed rail sweeps on all overhead cranes.
MAR 78-07-15 Completed 05/03/84 Added fire insulation to the air duct in the Cable Spreading Room and in the 480 Volt Switchgear Room.
MAR 77-08-13 Completed 01/27/84 Installed oil level indicators on the reversing gear boxes to the Nuclear Service pumps.
MAR 78-10-64 Completed 09/23/84 Installed copper tubing from each "POC" detector to the Fire Protection System central location in the Cable Spreading Room.
MAR 78-ll-69A Completed 08/17/84 Made T-MAR #78-11-69 a permanent installation.
MAR 78-12-04-01 Completed 09/25/84 Replaced the Make-Up Damper (AHD-F) in the Auxiliary Building exhaust system.
MAR 79-03-11 Completed 07/10/84 Replaced the hoists (main and auxiliary), trolley, and bridge brakes 1
on RCCR-1 with continuous electric brakes.
MAR 79-03-12 Completed 04/13/84 Installed and wired computers, terminals, and printers for the Chem-Rad Data System in the Count Room, Lab Work Area, and the TSC.
T-MAR 79-03-12-01 Completed 04/03/84 Temporarily installed circuit breakers and wiring to provide 480 V AC power from ES MCC (3A) to the Chem-Rad (ALARA) computer.
MAR 79-07-07C Completed 08/23/84 Revised the drawing (CR3-M82-A-0) to include MUV 435,439, and 443.
MAR 79-08-10 Completed 05/07/84 Installed two jib cranes, TBCR 3 (3 ton) and TBCR 4 (5 ton),
above the Turbine Building operating floor.
MAR 79-10-16 Completed 06/11/84 Provide electric and control power for the condensate return pump (CDP-2).
MAR 79-11-77 Completed 09/17/84 Modified the power supplies to the pressurizer heaters such that one group is supplied by ES (A) Bus and the other by ES (B) Bus.
MAR 79-12-62 Completed 05/10/84 Installed permanent rigging supports into the Decay Heat Pits A and B.
MAR 80-01-11-01 Completed 05/31/84 Replaced CAV 1,3 and 126 with Rockwell Hermavalves and Limitorque Corp. operators (type SMB-000).
MAR 80-01-62-01 Completed 05/07/84 Provided electrical and control power to DHV-39 and DHV-40 motor operators.
MAR 80-01-68-01 Completed 04/19/84 Provided electrical power and control to the motor operators of MUV-100,194, and 452.
MAR 80-03-66A Completed 07/12/84 Revised MAR #80-03-66 which instructed how to install Recall Cabinets and Field Cable from Terminal Cabinets to all source cabinets.
MAR 80-03-66B Completed 07/12/84 Revised MAR #80-03-66A. _
MAR 80-03-66-01 Completed 07/12/84 Added 13 more inputs to the original MAR package.
MAR 80-04-71 Completed 06/08/84 Installed the Post Accident Sampling System.
MAR 80-04-71-01 Completed 02/16/84 Installed the piping, tubing, valves, pipe supports, sample coolers, and (liquid and gas) analysis equipment, as well as modified existing R.B. penetration of the Post Accident Sampling System (PASS).
MAR 80-04-71 Completed 01/17/84 Installed an exhaust duct for the Post Accident Sampling Area, elevation 95 foot area.
Installed exhaust hoods and blowers over the Grab Sample mechanism at elevation 95 ft. and 143 ft.
MAR 80-04-71-05 Completed 04/18/84 Provided a supporting platform for the Post Accident Sampling System pump.
MAR 80-04-71-09 Completed 10/10/84 Installed the NUS Chemical Analysis Equipment into PASS.
MAR 80-04-72-01 Completed 11/15/84 Installed a portion of the Post Accident Hydrogen Purge system.
MAR 80-04-72-03 Completed 01/30/84 Installed and seismically qualified piping supports for the installation of Post Accident Hydrogen Purge System pipes.
MAR 80-04-73 Completed 02/28/84 Installed electrical control and indication up to connecting each of the solenoid valves of the R.C. high point vents.
MAR 80-04-73-02 Completed 03/21/84 Installed piping and valves (RCV 157,158,159,160,163,164, 166, and 167), fittings, flow switches (FS-149,150, and 151),
flow orifices (FO-155,156, and 157) portion of the High Point Vent System.
T-MAR 80-05-79 Completed 06/15/84 Temporarily allowed the use of Ankorite 1/32" 425 material to make a gasket for DHP-1B casing.
MAR 80-06-88-01 Completed 05/02/84 Installed 11 pipe hangers for the Auxiliary Steam lines.
MAR 80-06-92 Completed 05/15/84 Hooked up a portable air compressor to the Station Air System.
i 1,
MAR 80-07-61 Completed 02/16/84 Upgraded FHCR-5 in the following ways:
1.
Installed handrails on the west side.
2.
Installed a protective wire mesh around the resistor boxes.
3.
Installed high voltage warning signs.
MAR 80-07-62 Completed 02/16/84 Installed an access ladder to RCCR-1 from the control cab to the R.B. landing.
Installed working platform at the electrical box.
Installed a protective wire mesh around the resistor banks.
M AR 80-07-10A Completed 04/27/84 Added ductwork to the HVAC system supplying the EDG Control Room between the plenum and wall penetration.
T-MAR 80-07-76 Completed 09/17/84 Temporarily installed Helicoils in MSV 43 operator.
MAR 80-07-76A Completed 09/17/84 Made T-MAR #80-07-76 a permanent installation.
T-MAR 80-07-91 A Compicted 05/03/84 Temporarily re-furmanited the strainer cap upstream of GSV-7
^
MAR 80-08-06 Cor.ypleted 10/04/84 Removed AH-357,355,358,356,367,365,368,366-3V fr$m the.
Vital Bus and powered them from central transformers of the s
respective Air Supply Fan, AHF-22A, B,-C and D starters.
M AR'80-08-08 Completed 07/25/84 Installed plastic inserts into receptacles supplied by Vital Bus 3C. Engineering'approvalis needed before using.
7 MAR 80-10-61B Completed 03/05/84 Installed permanent piping to the Allis Chalmers Type C50 pumps, WDP-6A and 6B.
MAR 80-10-66-16 Completed 02/03/8M Moved the Electric Shop from the Control Building, elevation 124', to the Turbine Building, elevation 119', in order to make way for the EFIC room.
MAR 80-11-28-01 Completed 02[29/34 Installed two 15 KW electric heaters (DI.HE-3 and 4) instead of water cooled standy L.O. heaters to EGDG 1 A end.lB.
MAR 80-11-46-01 Completed 11/02/84 Removed the beam at elevation 144'-10" between columns BL-301 and BL-302, and replaced ft with a new number attaching te BL-301 in a north / south direction.
% I
- 4.
(7 4
5 4
L-e m_
_ _ _ _ _M___
L____~___
_______.___________...___.__J
i MAR 80-11-74 Completed 07/13/84 l
Replaced 40 Engineering Safeguard relays with Crydom Series 1 l
solid state relays (Cat. #A2410).
MAR 80-12-05 Completed 08/13/84 Replaced the Data Amplifiers (HP2470A) with Bay Labs Inc.
(Model #3109).
MAR 81-02-72-04 Completed 04/18/84 Provided additional cooling to room 111 in the Technical Support Center (TSC).
T-MAR 81-02-83 Completed 10/16/84 Temporarily replaced the top cover for CWS-1,2,3, and 4 with one made out of stainless steel.
MAR 81-03-06-01 Completed 05/01/84 Provided permanent lead shielding around the R.V. Head Storage Stand (Tag #RCX-2) to reduce radiation levels in the area.
T-MAR 81-03-69 Completed 07/10/84 Temporarily added an alarm to monitor for a steam leak in the Auxiliary Building, elevation 95', between ASV-14 and ASV-20.
}
T-MAR 81-03-80 Completed 09/12/84 Temporarily allowed RMG-9 (Personnel Entry Hatch to R.B.) to monitor radiation.
MAR 81-03-86A Completed 01/06/84
- Added Engineering instructions and termination information to original MAR, which installed bi-metal alarm thermometer and thermowell in weld rod oven door.
T-MAR 81-03-91 Completed 04/05/84 Temporarily relocated DW-10-FR (Waste Disposal Recorder) to behind the R.W. Panel to monitor Miscellaneous Waste Storage Tank Level (WD-49-LI).
MAR 81-04-02 Completed 09/25/84 Replaced field cable circuits (LPR-1, LPR-3) with high temperature 10000F cable.
T-MAR 81-04-63 Completed 09/05/84 Documented the presence of furmanite installed by T-MARS 80-08-73D,80-08-73E, and 80-08-73F which were closed out.
MAR 81-04-66-01 Completed 05/10/84 Upgraded the Reactor Building's and Auxiliary Building's Noble Gas Effluent Monitoring Systems.
T-MAR 81-05-05 Completed 05/21/84 Installed ajumper between terminal points 5 and 8 on terminal strip (TBA, Terminal Box, AH-77) for AHF6A/6B.
E
- - - ~
MAR 81-05-12 Completed 10/16/84 Added a PAX /PA phone in the area of RMA-6.
MAR 81-06-12-01 Completed 08/20/84 Changed the lube oil level indication for EFP 1,2 and EFTB-1 by installing a sight glass.
MAR 81-06-36 Completed 07/16/84 Installed a light between the fire door and the security door at the entrance to the Cable Spreading Room.
MAR 81-06-38-05 Completed 10/22/84 Removed the Deltec dedicated UPS from the Recall Data acquisition cabinets in the EFIC room.
MAR 81-07-04-01 Completed 09/24/84 Installed a walkway at the Intake Structure Trash Rocks.
T-MAR 81-03-18 Completed 07/23/84 Temporarily installea a flow indicator with a wider scale to read system flow over a wider range of operating conditions.
MAR 81-08-18A Completed 06/05/84 Installed a Barton 0-200" H O differential flow meter in 2
place of the Dietrich 0-5 PPH to better measure Nuclear Services Close Cycle Cooling System Pump.
MAR 81-08-21-01 Completed 08/16/84 Upgraded and reorganized the Control Room telephone system.
T MAR 81-09-07 Completed 04/04/84 Temporarily set up a storage trailer on the berm southeast of the Hot Shop and a laundry trailer northeast of the Hot Shop.
MAR 81-10-17 Completed 06/15/84 Changed to Cambridge Hi-Flow (Model #855-8-95) filters for AHFL-2A,2B,2C, and 2D, which are in the Auxiliary Building.
MAR 81-11-18 Completed 10/05/84 Core drilled a 6" diameter hole in the ceiling of the Makeup Prefilter Room, Auxiliary Building, Elevation 130'.
MAR 81-11-28 Completed 09/27/84 Drilled and tapped a 5/16" (diameter) x 1/2" (deep) hole in the AHV-1A and ID actuators to be able to key the shafts.
MAR 81-11-39-01 Completed 09/19/84 Changed all(96) locking assemblies of the Core Support Assembly to the reactor internals with Inconel Special Studs (MK-431),
Inconel Compression Nuts (MK-427), and Locking Cups (MK-436).
).
T-MAR 81-12-01 Completed 06/14/84 Changed the thermocouples in RC-188-TE4,5 and 6.
T-MAR 81-12-12 Completed 04/03/84 Temporarily seal welded the threaded plugs in the bottom of FWV-37 and 38.
MAR 82-01-19 Completed 08/22/84 Hardwired 115V AC power to the Foxboro power supplier for the pressure transmitters; RC-003A-PT3, RC-003-PT4, and RC-003B-PT3.
MAR 82-01-22 Completed 03/29/84 Replaced the Primary Lab fume hood exhaust duct work with duct work made from PVC material.
MAR 82-01-25 Completed 09/26/84 Performed the following changes:
1.
Manufactured and installed a strainer for the oil discharge check valve (SDV-100).
2.
Installed and adjusted a new spring in relief valves (SDV-96 and 97).
3.
Installed a new higher range pressure gauge (SD-27-Pl/PS).
MAR 82-01-28 Completed 05/08/84 Installed a permanent ladder in the new Fuel Storage Pit.
T-MAR 82-01-31 Completed 04/02/84 Temporarily injected furmanite into the man-way cover of MSR "D" cold reheat line.
T-MAR 82-01-35 Completed 07/11/84 Changed the me+ hod of measuring Make Up Tank Level; it went from a dry reference leg to a wet reference leg.
MAR 82-02-05-01 Completed 05/01/84 Modified the RCP mechanical seals in the following ways:
1.
Installed slotted carbide rotating face seal ring on all 3 stages.
2.
Installed improved "U" cup design.
T-MAR 82-02-11 Completed 04/06/84 Temporarily installed instruments to monitor MUV-43 flow vibration as i:;ake up water enters the Reactor Coolant System.
T-MAR 82-04-03-02 Completed 07/11/84 Temporarily provided two stake marks (1800 apart) from the hinge pin to its nut on CFV-1.
T-MAR 82-04-10-02 Completed 06/06/84 Temporarily installed Saligoud continuous monitoring system to record RCP motors' response to system transients..
T-MAR 82-04-14-02 Completed 04/03/84 Installed a TSO computer terminal in the Nuclear Security trailer on the berm.
MAR 82-04-14-04 Completed 04/18/84 Installed TSO terminals in the following areas:
1.
TSO Conference Room 2.
Electrical Shop 3.
Cold Machine Shop Library 4.
Instrument Shop office 5.
Control Room Chart Room MAR 82-04-15-01 Completed 01/06/84 Replaced Chemistry's silica analyzer with an Orion research Chlorine Analyzer.
T-MAR 82-05-06-02 Completed 08/28/84 Temporarily reinjected a leaky furmanite connection (T-MAR #82-05-06-01) into MSV-54.
MAR 82-05-11-01 Completed 08/02/84 Provided the means to lock the handwheels for MUV-2,6 and 10 so they could be throttled.
MAR 82-05-13-01 Completed 04/24/84 Changed out cables and assigned circuit numbers for telephones installed to support the CNSI Solidification Unit.
MAR 82-05-24-08 Completed 09/11/84 Upgraded the valve operators for DHV-5,6,34 and 35 to meet NRC requirement of 10 CFR 50.49.
T-MAR 82-06-13-01 Completed 08/28/84 Temporarily injected furmanite to stop leak in the manway cover of MSRH-A (cold reheat).
MAR 82-06-14-01 Completed 12/04/84 Relocated the RC Evaporator Tank High Level Alarm and the Waste Evaporator Tank High Level Alarm annunciators to the Radwaste Panel, Auxiliary Building.
T-MAR 82-06-26-01 Completed 02/29/84 Temporarily added bracing and changed hardware on 5 conduit supports in the Auxiliary Building.
T-MAR 82-06-26-02 Completed 02/29/84 Temporarily added bracing and changed unistrut hardware on 9 conduit supports. _ _ _
2 T-MAR 82-06-26-05 Completed 03/01/84 Temporarily added bracing on 4 conduit supports in the Control complex.
T-MAR 82-06-26-06 Completed 03/06/84 Temporarily provided structural strengthening of electrical conduits.
MAR 82-06-26-07 Completed 01/27/84 Made T-MARS 82-06-26-01,02,03,04,05 and 06 permanent and was in direct response to NCORs82-167 and 82-169.
MAR 82-07-05-01 Completed 01/27/84 Removed the old OTSG Main Feedwater Sprayhead Nozzles.
MAR 82-07-23-01 Completed 03/28/84 Updated drawing #FD-302-142 and FD-318-142 to reflect deletion of GWV 66 and 70.
T-MAR 82-07-26-01 Completed 11/27/84 Qualified different types of concrete anchor bolts.
MAR 82-08-05-01 Completed 07/19/84 Allowed the use of Dw; tr differential pressure switch model numbers (1640-0 and 1630-0) in the existing Dwyer air handling system location.
MAR 82-08-19-01 Completed 04/27/84 Replaced the existing SC system transmitter, Leads & Northrup (Model #470-314-2B-49-614-802-804) with a wider range.
T-MAR 82-08-21-01 Completed 06/13/84 Temporarily changed to use a cloth reinforced black rubber flapper in SDV-Il6.
MAR 82-08-24-01 Completed 11/05/84 l
Upgraded transmitters, EX-23-PT and EX-29-PT to better withstand system pressure.
T-MAR 82-08-36-01 Completed 10/04/84 Temporarily allowed the use of Fluorocarbons Rubber "O" Rings",
l as well as the original Nitrile (Bunna-N) with the filter assembly for the fuel oil strainer of the Emergency Diesel Generator.
MAR 82-08-36-Ol A Completed 10/04/84 Allowed the use of Fluorocarbon Rubber (Viton)"O" Ring, as well as the original Nitrie (Bunna-N) "O" Ring to be I
used in the fuel oil system of the Emergency Diesel Generators. --
~
MAR 82-08-40-01 Completed 06/01/84 Temporarily modified the capability of the toxic gas monitors to shut the control complex intake dampers.
MAR 82-09-01-01 Completed 10/11/84 Made the change of manufacturer's model numbers for the pressure switches, TB-231-PS and TB-232-PS.
MAR 82-09-42-01 Completed 08/02/84 Replaced the access door on the rear head and added grounding straps on each of the heat exchangers (SWHE-1 A, IB, IC andID).
MAR 82-09-13-05 Completed 02/21/84 Upgraded the typical conduit support drawings.
MAR 82-09-15-01 Completed 04/18/84 Replaced an obsolete part for the MT Inverter Meter Relay System.
T-MAR 82-09-25-01 Completed 06/28/84 Temporarily injected furmanite into the cold heat manway for MSR-B.
MAR 82-10-14-01 Completed 02/01/84 Installed the original PORV (RCV 10) valve, Serial #BL-08901 with the Dresser Mod.-2 design change.
T-MAR 82-10-24-01 Completed 05/08/84 Temporarily replaced SWV 378 with an Anderson Greenwood valve (Model #81P544-4).
MAR 82-10-28-01 Completed 09/11/84 Installed additional PA speakers and fire alarm bells in the TSC.
MAR 82-11-10-01 Completed 07/16/84 Installed a mechanical seal on the lube oil pump, LOP-1.
l MAR 82-11-13-01 Completed 10/24/84 l
Installed a check valve in the instrument air line to the Fire Surge Tank (FST-3).
MAR 82-12 il Completed 06/28/84 Reduced the amount of oxygen instrusion into the secondary system by the following means:
1.
Installed valves on the drain lines for RHV 7,9, 10 and 11.
2.
Removed a portion of the vent stacks for RHV 9, 10,11 and 12 (so they may be capped during start-up and shutdown)..
~
MAR 82-12-04-01 Completed 08/21/84 Allowed the use of a new booster for either EGDG governor.
MAR 82-12-05-02 Completed 07/30/84
. Installed jumpers (new) and removed existing wiring between TSC State Ringdown Panel and FTC interface point in the guard house.
T-MAR 82-12-06-01 Completed 08/27/84 Temporarily replaced SWV 362 and 365 with an Anderson Greenwood valve, Model #81P544-4.
MAR 82-12-06-01 A Completed 08/27/84 Made T-MAR #82-12-06-01 a permanent installation.
MAR 82-12-10-01 Completed 09/27/84 Replaced the blank flange downstream of MSV-475 to be able to drain down the shell side of the steam generators.
T-MAR 82-12-20-01 Completed 05/14/84 Temporaril; 'njected liquid sealant stop leak (Furmanite) into the flanged strainer upstream of GSV-7.
MAR 83-01-08-01 Completed 05/15/84 Installed extra telephone lines in the TSC.
T-MAR 83-01-11-01 Completed 08/27/84 Temporarily installed piping to enable discharging contents of SDT-1 to the settling ponds.
MAR 83-03-07-01 Completed 11/06/84 Changed the internals of FSV 184 to be able to increase the lif ting pressure to 140 psig.
MAR 83-03-10-01 Completed 08/16/84 Replaced SSP-4C with Model #GA-lK-751H-IS.
MAR 83-03-12-01 Cornpleted 08/29/84 Installed 120V AC receptacle to power a Blue Giant Lift.
T-MAR 83-03-11-01 Completed 04/04/84 Temporarily installed electrical power to the Tool Decontamination Trailer just outside the Cold Machine Shop in support of RefuelIV.
MAR 83-03-13-01 Completed 03/30/84 Provide permanent power to the vending machine in the Turbine Building, elevation 119'.
T-MAR 83-03-18-01 Completed 04/25/84 Temporarily installed lead shielding between RCV 14 and the R.C. Pressurizer. __
T-MAR 8%C3-20-01 Completed 09/07/84 Temporarily bypassed and isolated a leaky section of pipe so that the Makeup Tank (MUT) could be sampled and the pipe repaired.
MAR 83-04-06-01 Completed 05/31/84 4
Documented "As Built" holes in the west wall of the Intermediate Building, elevation 119'-0".
MAR 83-04-21-01 Completed 10/23/84 Replaced the existing DP switch (DO-25-PS) with Koenig-Pretempco's Model #DPS-300-P20PA-82582.
T-MAR 83-04-32-01 Completed 09/06/84 Temporarily provided covers for the RCP seals while they were being worked on.
T-MAR 83-04-37-01 Completed 06/07/84 Temporarily installed a rep'acement motor for the Boric
. Acid Mix Tank Mixer, CAMX-3.
T-MAR 83-04-40-01 Completed 01/20/84 Temporarily isolated SWHE-3C and SWHE-3D from the rest of the RW System..
MAR 83-04-52-02 Completed 09/07/84 ~
Installed a key lock switch in the Control Room Rad Monitor Cabinet #3.
MAR 83-04-56-01 Completed 08/03/84 Permitted the substitution (as needed) of fully threaded A193 G.R. B-7 in place of the specified A307 for all Power Piping hangers.
MAR 83-05-05-01 Completed 08/29/84 Repaired small corroded holes in the Inlu Water Box of SWHE-1C.
MAR 83-05-07-01 Completed 05/10/84 Replaced defective RW spool pieces, (RW 26, RW 55F, RW 56, RW 56B, RW 61, and RW 62), with piping having a urethane iger.
T-MAR 83-05-12-01 Completed 09/26/84 Temporarily replaced the quality ES Timer Relay Coll with one that was nonquality.
M AR 83-05-26-01 Completed 06/21/84 Changed the type of wire on the EGDG IB skid from the engine overspeed switch (EOS) to the control relay cabinet.
R MAR 83-05-28-01 Completed 07/12/84 Revised RCPPM set points and time delays as follows:
1.
Low set point - 1150 KW.
2.
High set point - 14,400 KW.
3.
Time delay.84 seconds, nominal (not to exceed
.89 sec.).
MAR 83-05-34-01 Completed 11/29/84 Provided a test connection with a root valve on the Reactor Building side of penetration #339.
MAR 83-05-35-01 Completed 02/17/84 Installed electrical conduits in the Reactor Building.
MAR 83-05-36-01 Completed 9/19/84 Updated the Rochester Instrument System drawing for Everton Recorder (Drawing #B-1013-586, sheet I through 88), and the annunciator / events Recorder Computer Printout List to current "As Built" status.
T-MAR 83-06-02-01 Completed 01/06/84 Temporarily installed a gate at door C121.
MAR 83-06-10-01 Completed 05/23/84 Allowed the use of Byron Jackson's redesigned thermocouples (RC-018 A/B-TE l-6) for each of the four Reactor Coolant Pumps.
MAR 83-06-16-01 Completed 05/04/84 Upgraded some 1-1/2 hour rating fire dampers to 3-hour rating fire dampers.
MAR 83-06-19-01 Completed 06/29/84 Installed the means to test for positive pressure (and adjust the set point) of the low vacuum trip on the Main Condensers.
T-MAR 83424-01 Completed 06/14/84 Temporarily changed MSV 412 terminal box #1 to a Kulka series 601 terminal block.
MAR 83-06-29-01 Completed 07/16/84 Provided Word Processing Department whh computer conn tions to Nuclear Operations and G.O.C. Nuclear Support.
MAR 83-07-08-01 Completed 02/03/84 Changed a series of Diamond Power drawings for the Control Rod Drive Mechanism.
T-MAR 83-07-09-01 Completed 10/09/84 Temporarily relocated the spare receptacles in the Control Rod Drive Control Cabinets #4 and #5 Patch Panels. -
~
MAR SM)7-09-01 A Completed 07/11/84 Relocated the spare receptacles in the Control Rod Drive Control Cabinet #4 Patch Panels and wired to Group 7.
T-MAR 83-07-11-01 Completed 08/28/84 l
Temporarily injected furmanite to stop a body to bonnet leak on FWV-19.
MAR 83-07-14-01 Completed 09/17/84 Installed high temperature wires for the closed position limit switches on MSV 25 and 26.
T-MAR 83-07-17-01 Completed 08/28/84 Injected furmanite into the body / bonnet area of ASV-52.
MAR 83-07-20-01 Completed 07/25/84 Changed the mechanical seal drawing for MUP-1 A, IB and IC.
MAR 83-07-22-01 Completed 08/13/84 Installed permanent rigging in the ceiling of MUP-lC room.
MAR 83-08-05-01 Completed 02/08/84 Modified the existing 10% High Accuracy Generator Metering Cabinet so that the signal going to the Energy Control Center from the Remote Terminal Unit represents the net generation to the System from CR-3.
MAR 83-08-07-02 Completed 07/24/84 Modified conduit support, C-124-232.
MAR 83-08-34-01 Completed 07/17/84 Permitted the use of ASTM A105 plug materialin lieu of ASTM A216 WCB material for EFV-7 and 8.
T-MAR 83-08-32-01 Completed 06/15/84 Temporarily installed a 15V DC electric supply to the Met Tower.
MAR 83-08-33-01 Completed 04/18/84 Installed vital access barriers into the plant.
T-MAR 83-08-36-01 Completed 05/04/84 Temporarily replaced the O-ring with a Teflon 0-ring in CAV 252.
T-MAR 83-08-38-01 Completed 05/10/84 Temporarily injected furmanite into MSV 430.
T-MAR 83-08-40-01 Completed 08/28/84 Temporarily injected furmanite into a pipe p(lug on aline off of the Moisture Separator Re _ _
T-MAR 83-08-42-01 Completed 04/18/84 Temporarily " gagged" Main Steam Safety Relief Valve, MSV 33.
T-MAR 83-09-14-01 Completed 09/05/84 Temporarily furmanited the manway studs in the line under the H.P. Turbine going to MSR 3B and 3C.
MAR 83-09-15-01 Completed 08/17/84 Installed a protective plate in front of the heat trace transformer (HTTR-4B), which is adjacent to the Auxiliary Building elevator, elevation 95'.
MAR 83-09-18-01 Complted 07/17/84 Changed the tag numbers of two valves (1) MSV 33 was changed to MSV 46, and (2) MSV 46 was changed to MSV 33.
T-MAR 83-09-19 Completed 12/12/84 Temporarily replaced the normally closed "TS" contact terminal points 8 and 9 with the normally closed auxiliary "TS" contacts terminal points 12 and 13.
T-MAR 83-09-25-01 Completed 08/27/84 Temporarily injected furmanite into the following valves; HDV 11 and 12, MSV 97, and RHV 14.
MAR 83-09-28-01 Completed 08/21/84 Changed to G.E. type 12HFA151 A2H Century series relays in the MT and EG systems.
T-MAR 83-10-06-01 Completed 04/11/84 Temporarily installed a heavier spring into CAV 6 and 7 in order to overcome system pressure.
MAR 83-10-06-Ol A Completed 05/21/84 Made T-MAR #83-10-06-01 a permanent installation.
MAR 83-10-08-01 Completed 02/08/84 Permitted the use of ASHE SA-182 F304 drain plugs ia lieu of carbon steel plugs in DHP-1 A and IB.
MAR 83-10-10-01 Completed 08/24/84 Replaced the level transmitter, SC-70-LT (Secondary Services Closed Cycle Surge Tank Level) with a Rosemount Model #1151.
T-MAR 83-10-14-01 Completed 02/08/84 Temporarily jumped out battery cells 78 and 97 from battery bank 3B2.
MAR 83-10-20-01 Completed 11/13/84 Replaced and design changed WOPS, A, B.ad C.
T-MAR 83-10-23-01 Completed 08/W/84 Temporarily injected furmanite into a horizontal joint on the H.P. turbine.
MAR 83-10-24-01 Completed 07/30/84 Changed the relief point setting of SWV 398,399 and 400 from 100 psig to 180 psig.
MAR 83-10-25-01 Completed 02/08/84 Repaired two holes in the HVAC ductwork downstream of AHF-14D.
MAR SM0-26-01 Completed 09/04/84 Increase the relief set point from 100 psig to 200 psig on the following valves: DCV 105,106,107,108,109, and 110.
MAR 83-10-27-01 Completed 08/22/84 Modified three small bore pipe supports on the DC cooling water for MUP-lC.
MAR 83-10-28-01 Completed 01/17/84 Installed switches from doors in the Plant Security system.
MAR 83-10-29-01 Completed 04/25/84
~Provided electrical and mechanical tie-in between FPC system and NHS Demineralizer system.
MAR 83-10-34-01 Completed 08/20/84 Authorized the use of Thermexchanger Cooler head on MUP 1 A, IB, or IC.
T-MAR 83-11-06-01 Completed 06/04/84 Temporarily provided pipe supports for MUP 1 A.
MAR 83-11-41-01 Completed 02/08/84 Drilled a 5" diameter hole in the east wall of the Cable Spreading Room, and installed conduit through said hole with a fire seal.
MAR 83-12-03-01 Completed 09/10/84 Added hangers to the seal lube piping of MUP-1A.
MAR 83-12-11-01 Completed 02/08/84 Reconnected the Containment Pressure input to recorder (BS-65-PR).
M AR 83-12-12-01 Completed O'J20/84 Revised the 302 and 318 series flow drawings. ---. -.
MAR 83-12-18-01 Completed 09/27/84 Replaced CDV 95 operator with one which is designed to withstand 100 psig pressure.
MAR 83-12-21-01 Completed 04/11/84 Replaced the existing L&N Model #1970 "SA-4-OT" with a Rosemount Model #1144.
MAR 84-01-04-01 Completed 08/21/84 Added a lockable lid over the emergency feedwater pump turbine speed control knob.
MAR 84-01-07-01 Completed 09/17/84 Revised the set point of pressure switch (RW-63-PS-1) to 12 psig deerssing pressure.
MAR 84-01-08-01 Completed 04/18/84 Changed the material requirements of a Velan Drawing P-35300-1.
MAR 84-01-09-01 Completed 07/25/84 Permitted the use of ASTM A479 Type 316 SS with stellite
- 6 facing on Velan valve disc-drawing #P-35300-20.
T-MAR 84-01-19-01 Completed 07/25/84 Temporarily installed the original type valve (tag #CAV 252) from Control Components, Inc. The old valve manufactured by Casho, Model #1965, had a poor performance record.
MAR 84-01-19A Completed 05/21/84 Documented the permanent installation of Control Components, Inc., Model #MDA 2504-6W for CAV 252.
MAR 84-01-21-01 Completed 10/04/84 Removed the pressure regulators (SCV 644,645,646 and 647) from the cooling water system to the air compressor.
T-MAR 84-01-21-02 Completed 10/17/84 Temporarily allowed parallel cooling water paths to IAP-1B and IAHE-1B.
MAR 84-01-25-01 Completed 05/15/84 Relocated the hangers for the water supply and return to the EFP-2 Governor oil cooler.
MAR 84-02-09-01 Completed 10/03/84 Installed a security barrier to protect a vital area along the south Turbine Building wall.
MAR 84-02-14-01 Completed 10/22/84 Changed FSV 45 to a silent check valve.
MAR 84-02-15-01 Completed 04/18/84 Provided a c'earer vendor print of MUV 62 and 69 and revised material specs. for its operator's stud and nut.
MAR 84-03-12-01 Completed 05/14/84 Documented the change to allow either epoxy coating or emulsion in certain areas of the Auxiliary Building with Plant Manager's authorization.
T-MAR 84-03-15-01 Completed 05/07/84 Temporarily replaced SWV 378 with an Anderson Greenwood valve (Model #81P544-4).
T-MAR 84-03-16-01 Completed 0 * /15/84 Temporarily injected furmanite to stop seal leakage on FWV 135.
MAR 84-04-01-01 Completed 09/12/84 Permitted the ase of an alternate pressure seal ring material (ASTM A-28 GR C, silver plated / lead free) in all Crane pressure seal valves.
MAR 84-04-07-01 Completed 05/22/84 Changed the #9 MFW nozzle flange from a "3" bevel to a butt weld on OTSG "A".
MAR 84-04-08-01 Completed 06/20/84 Allowed the use of ASTM B584 (copper alloy) in the manufacture of the yoke nut of Crane drawings PB 147658 (MSV 21,22,23 and 24).
MAR 84-06-16-01 Completed 08/16/84 Documented the addition of SA 515 Gr 70 to the bill of materials of Crane / Chapman Drawing #PC-149250 of RWV 136.
MAR 84-07-06-01 Completed 10/23/84 Added steps and hand holds to assist personnel entering the condenser water boxes.
MAR 84-07-07-01 Completed 10/23/84 Removed the bottom row of tie rod plates on the Hurricane doors 8A and 8B to allow the door to lower completely.
MAR 84-07-09-01 Completed 10/04/84 Revised the Main Steam flow diagrams and other documents to ensure that MSV 440 is a 600 psig globe valve.
MAR 84-08-09-01 Completed 12/04/84 Allowed the use of plastic spray nozzles in the Screen Wash system.
T-MAR 84-10-05-01 Completed 11/13/84 Temporarily replaced the cap screws on the fuel oil header to the injectors for diesel generator (EGDG-1 A).
[
l I
REPORT ON PRESSURIZER CODE SAFETIES AND 1
l POWER OPERATED RELIEF VALVE FOR 1984 i
t The PORY and the Pressurized Code Safety Valves were not challenged during
- 1984; therefore, no failures occurred.
l l
t l
L 1
4 v-m w-~e n.
. mn e-e m
g
+
en.-
a s e,, - -, -
w-,w ew-
-re,
---ew-w e-<------,ae e--w s-
,---,,wr,--
y r
y e.e
?FICIALC PW le oe) s,,
p 4,y,
eee Florida
~ '# f4E Power "1-vtLr r-N e
C O RPOR ATIO N fG4M February 28,1985 3F0285-16 CoccoVS Dr. 3. Nelson Grace Regional Administrator, Region II Office of Inspection & Enforcement U.S. Nuclear Regulatory Commission 101 Marietta Street N.W., Suite 2900 Atlanta, GA 30323
Subject:
Crystal River U
- f Docket No.
/T Operating License No. DPR-72 1984 Annual Reports
Dear Sir:
Enclosed are the following four annual reports:
1.
1984 Annual Report on Personnel Exposure; as required by 10 CFR 20.407(b) and by Florida Power Corporation's Crystal River Unit 3 Technical Specifications, Section 6.9.1.5(a);
2.
1984 Annual Report on Reactor Vessel Material Surveillance Capsules; as required by Florida Power Corporation's Crystal River Unit 3 Technical Specifications Section 6.9.1.5(b);
3.
1984 Report on Production Facility Changes, Tests and Experiments; as reqitired by 10 CFR 50.59b; and 4.
Report on Challenges to and Failures of Pressurizer Relief and Code Safety i
Valves required by NUREG-0737, November 1980, Section ll.K.3.3, as committed to in FPC's letter to the NRC dated July 21,1980.
- l 8 frae 24/2 GENERAL OFFICE 3201 Thirty fourth Street South e P.O Box 14042, St. Petersburg, Florida 33733 e 813-866-5151
February 28,1985 3F0284-16
' Page 2 If you have any questions regarding these reports, please contact this office.
Sincerely,
!!)
G. R. Westafer Manager, Nuclear Operations Licensing and Fuel Management G3F/feb Enclosures cc:
Director of Nuclear Reactor Regulation (1)
Attn: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Director (1)
Office of Nuclear Regulatory Research U.S. Nuclear Regulatory Commission Washington, DC 20535 O
!