Finding | |
---|---|
Title | Technical Support Center Diesel Generator Not Restored Following Maintenance |
Description | A self revealing Green non-cited violation of 10 CFR 50.47(b)(8) was identified for the failure to maintain adequate facilities to support emergency response. Specifically, the licensee found the technical support center battery disconnect switch had not been restored following maintenance activities. This configuration would have rendered the diesel generator unable to start automatically as designed in the event of a loss of off-site power. The licensee initiated immediate corrective actions to restore the technical support center diesel generator to a functional configuration and has begun implementation of a more formal process for component configuration verification of critical technical support center equipment. The licensee has entered this issue into their corrective action program as Palo Verde Action Request 4165625. The failure to follow Procedure 40OP-9NG01 for performing a functional test of 480V switchgear following maintenance activities is a performance deficiency. This performance deficiency was more than minor because it is associated with the Emergency Preparedness Cornerstone attribute of facilities and equipment and it adversely affected the cornerstone objective to ensure that the licensee is capable of implementing adequate measures to protect the health and safety of the public in the event of a radiological emergency. The inspectors evaluated the significance of the issue under the Significance Determination Process, as defined in Inspection Manual Chapter 0609.04, Initial Characterization of Findings, and Manual Chapter 0609, Appendix B, Emergency Preparedness Significance Determination Process. The finding was determined to be of very low safety significance (Green) because the degraded planning standard function did not result in the loss of technical support center functionality for longer than 7 days. The inspectors determined that the finding had a cross-cutting aspect in the area of human performance associated with resources. Specifically, the licensees work control procedures did not include critical technical support center systems to ensure that technical support center configuration control was maintained commensurate with its significance. |
Site: | Palo Verde ![]() |
---|---|
Report | IR 05000528/2012005 Section 4OA2 |
Date counted | Dec 31, 2012 (2012Q4) |
Type: | NCV: Green |
cornerstone | Emergency Prep |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | M Brown L Carson S Garchow D Allen J Reynoso M Young B Larson J Groom I Anchondo N Hernandez D You |
CCA | H.7, Documentation |
INPO aspect | WP.3 |
' | |