04-05-2010 | On February 3, 2010, with Unit 1 at 100% power, monthly shutdown and control rod testing was being performed. Previously on January 6, 2010, control rod C-5 had been determined to be inoperable, but trippable. During testing on February 3, a second control rod (B-12) was determined to be inoperable, but trippable. Attempts to realign the control rod with its bank were unsuccessful. Consequently, TS 3.0.3 was entered and the Unit was shutdown to Mode 3.
This event is reportable per 10 CFR 50.73(a)(2)(i)(A), "The completion of any nuclear plant shutdown required by the plant's Technical Specifications.
The cause of this event was insufficient removal and dispersion of the.corrosion products originating from the normal fabrication and passivation process of the new CRDM latch assemblies associated with the Unit 1 Replacement Reactor Vessel Head.
All shutdown and control rods remained fully trippable during this event. There were no personnel injuries, no offsite radiological releases, and no damage to other safety-related equipment. |
---|
I. DESCRIPTION OF EVENT
A. REPORTABLE EVENT CLASSIFICATION
This event is reportable pursuant to 10 CFR 50.73(a)(2)(i)(A). South Texas Project (STP) Technical Specification 3.1.3.1.c allows power operation to continue with more than one inoperable but trippable control rod for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. If the rods are not restored to operable (or are expected to not be returned to operable) within the allowed time, TS 3.0.3 is applied, which requires that the plant be in HOT STANDBY within the following six hours, and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. On February 3, 2010, with the Unit at 100% power, monthly shutdown and control rod testing was being performed.
Previously on January 6, 2010, control rod C-5 was determined to be inoperable, but trippable. During testing on February 3, a second control rod (B-12) was determined to be inoperable, but trippable. Attempts to realign the control rod with its bank were unsuccessful.
Consequently, TS 3.0.3 was entered and the Unit was shutdown to Mode 3.
B. PLANT OPERATING CONDITIONS PRIOR TO EVENT
STP Unit 1 was in Mode 1 at 100% power.
C. STATUS OF STRUCTURES, SYSTEMS, AND COMPONENTS THAT WERE INOPERABLE
AT THE START OF THE EVENT AND THAT CONTRIBUTED TO THE EVENT
No other structures, systems, or components were inoperable at the start of the event which contributed to the event.
D. NARRATIVE SUMMARY OF THE EVENT
On January 6, 2010, Unit 1 conducted monthly shutdown and control rod surveillance testing at 100% power. When Shutdown Bank D was inserted and withdrawn, Shutdown Bank D rod C-5 did not withdraw. Attempts to realign rod C-5 were unsuccessful and reactor power was reduced to less than 75% to comply with Technical Specification (TS) 3.1.3.1 actions.
Rod C-5 remained trippable.
On January 14, 2010, Unit 1 conducted shutdown and control rod surveillance testing at approximately 74% power with the full out position set at 259 steps for the remainder of the rods not tested on January 6 (Shutdown Bank E and Control Banks A, B, C, and D). No rod misstepping or rod position anomalies were noted for these rod banks.
On January 19, 2010, with Unit 1 operating in Mode 1 at approximately 75% power, the full out position of all Unit 1 rods was changed to 249 steps in accordapce with a revision to the Core Operating Limits Report and per plant procedure. The shutdown and control banks were inserted to 249 steps. This allowed Unit 1 to be returned to full power operations, since the inoperable rod was now within 12 steps of its group demand position, as required by TS 3.1.3.1.
On February 3, 2010, Unit 1 again conducted monthly shutdown and control rod surveillance testing at 100% power. When Shutdown Bank A was inserted and withdrawn, rod B-12 did not withdraw when demanded. The Operating crew entered TS 3.1.3.1 action c (for more than one rod inoperable but trippable), but attempts to realign rod B-12 with its bank were unsuccessful. Subsequently, TS 3.0.3 was entered and the unit was shutdown to Mode 3.
Rod exercising was conducted to remove corrosion products from the latch assemblies and flush corrosion products from the latch housings. In summary, 13 rod drops, 6 exercises (3 for traces and 3 for cleanup) for all banks and SBB exercising (to free up N-7) were performed for a total of approximately 5000 withdrawl and 1500 inward steps. SBB was stepped approximately an additional 1300 steps to free up N-7.
This event had no adverse impact on the health and safety of the public.
E. METHOD OF.DISCOVERY Control Rods C-5 and B-12 were determined to be inoperable, but trippable during monthly surveillance testing.
II. EVENT-DRIVEN INFORMATION
A. SAFETY SYSTEMS THAT RESPONDED
No safety systems were required to respond during this event.
B. DURATION OF SAFETY SYSTEM INOPERABILITY
Shutdown control rod C-5 was declared inoperable (but trippable) on January 6, 2010.
Technical Specification 3.1.3.1 allows continued operation with one control rod inoperable but trippable. Shutdown control rod B-12 was declared inoperable but trippable on February 3, 2010, and the Unit was subsequently shutdown in accordance with TS 3.0.3. The duration of inoperability for rod C-5 was approximately 28 days. Rod B-12 was declared inoperable on February 3, 2010 at 1244 hours0.0144 days <br />0.346 hours <br />0.00206 weeks <br />4.73342e-4 months <br /> and Unit 1 subsequently entered Mode 3 1739 hours0.0201 days <br />0.483 hours <br />0.00288 weeks <br />6.616895e-4 months <br />.
The duration of concurrent inoperability for rods C-5 and B-12 was approximately 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.
C. SAFETY CONSEQUENCES AND IMPLICATIONS OF THE EVENT
Technical Specification Requirements:
Technical Specification 3.1.3.1 requires in Modes 1 and 2 that all full-length shutdown and control rods shall be operable and positioned within 12 steps (indicated position) of the group 5 step counter demand position.
Design Description:
The rod control system is a solid state system that controls the electrical power to the Control Rod Drive Mechanisms (CRDMs). The CRDMs are magnetic jacking mechanisms that move each shutdown and control rod within the reactor core by sequencing power to the three magnetic coils of each CRDM, producing a jacking or stepping rod motion.
The rod control system is designed to maintain reactor coolant system temperature within +/ 1.5 F of programmed temperature, by regulating reactivity within the core. Additionally, the rod control system is designed to automatically respond to design transients (such as step changes in turbine load, or power runbacks) and allows for temperature control by either manual operator action or automatic control by the rod control circuitry.
The rod control system is a non-safety related system. However, the design safety function of the shutdown and control rods themselves is to insert negative reactivity into the core in response to a. reactor trip signal. The rod misstepping experienced by rods C-5 and B-12 did not affect their ability to trip.
Extent of Condition:
Lessons learned from rod misstepping experienced in Unit 1 will be applied to startup and power operations following replacement of Unit 2's reactor vessel head.
Risk Assessment:
The event is considered to have low safety significance. All shutdown and control rods remained fully trippable during this event. Although the rod insertion limit was not met for Shutdown Bank rod B-12 (not at full out position), and potentially not met for Control Bank C Rod H-2 (misalignment observed affecting bank overlap at approximately 20% power), shutdown margin was satisfied and core power distribution limits were not challenged.
Equipment considered in the Configuration Risk Management Program (CRMP) was not affected by this event and remained available to support the plant shutdown. This event is not considered an at-power initiating event; the reactor was manually shutdown to Mode 3 in a controlled manner. Although this event is not an initiating event, the Conditional Core Damage Probability (CCDP) associated with a general reactor trip event, approximately 1E-07, can be used to bound the potential risk impact due to the plant shutdown to Mode 3.
III. CAUSE OF THE EVENT
The cause of this event was insufficient removal and dispersion of corrosion products originating from the normal fabrication and passivation process for the new CRDM latch assemblies associated with the Unit 1 Replacement Reactor Vessel Head. Analysis results indicate that the passivation process has not yet reached equilibrium and that the control rod drive mechanisms will be susceptible to corrosion product effects for an additional period of time.
IV. CORRECTIVE ACTIONS
Prior to Unit 1 restart, each shutdown and control rod was moved through its full length of travel multiple times, including 10 rod drops from the full out position.
Shutdown and control rod exercising is being performed on a more frequent basis until sufficient performances indicate that passivation has been achieved such that rod misstepping is resolved.
V. PREVIOUS SIMILAR EVENTS
On January 5, 2006, Unit 2 control rod D-4 misaligned by approximately 7 steps. The rod was declared inoperable but trippable and TS 3.1.3.1 Action b.2 was entered. The grippers were exercised (no rod motion) and the control rod was successfully realigned with its bank. The monthly shutdown and control rod surveillance test was then performed satisfactorily as a post-maintenance test.
VI. ADDITIONAL INFORMATION
None.
|
---|
|
|
| | Reporting criterion |
---|
05000220/LER-2010-001 | Reactor Scram Due to Inadequate Post Maintenance Testing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000410/LER-2010-001 | Reactor Scram Due to Inadvertent Actuation of the Redundant Reactivity Control System During Maintenance | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000395/LER-2010-001 | Reactor Building Cooling Units Reduced Air Flow Rate Below Technical Specification Limits | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000382/LER-2010-001 | Spent Fuel Pool Cooling Single Failure | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | 05000374/LER-2010-001 | High Pressure Core Spray System Declared Inoperable Due to Failed Room Ventilation Control Relay | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000373/LER-2010-001 | Unauthorized Individual Gained Access to the Protected Area. | | 05000370/LER-2010-001 | Loose connection in a panel board serving a Solid State Protection System Train concurrent with redundant train maintenance could have prevented fulfillment of a safety function. | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000261/LER-2010-001 | Emergency Diesel Generator Inoperable in Excess of Technical Specifications Allowed Completion Time | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000263/LER-2010-001 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000255/LER-2010-001 | Potential Loss of Safety Function Due to a Service Water Pump Shaft Coupling Failure | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000266/LER-2010-001 | Engineered Safety Features Steam Line Pressure Dynamics Modules Discovered Outside of Technical Specification Values | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000306/LER-2010-001 | Unit 2 Turbine Trip during Reactor Shutdown Resulting in a Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000305/LER-2010-001 | Safety Injection Pump Recirculation Line Isolation Results in Violation of Technical Specifications | | 05000298/LER-2010-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2010-001 | Standby Shutdown Facility Letdown Line Orifice Strainer Blocked by Valve Gasket Material | 10 CFR 50.73(a)(2)(i)(b) | 05000282/LER-2010-001 | Unanalyzed Condition Due to Postulated High Energy Line Break On Cooling Water System | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000277/LER-2010-001 | Multiple Slow Control Rods Results in Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i) | 05000361/LER-2010-001 | Broken Manual Valve Prevents Timely Condensate Storage Tank Isolation | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000483/LER-2010-001 | Emergency Core Cooling System MODE 4 Operating Practices Prohibited by current Technical Specification 3.5.3 | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000498/LER-2010-001 | Unit Shutdown Required by Technical Specifications | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000316/LER-2010-001 | Valid Actuation of Auxiliary Feedwater System in Response to Valid Steam Generator Low-Low Levels | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000321/LER-2010-001 | Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000336/LER-2010-001 | Millstone Power Station Unit 2 Reactor Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000413/LER-2010-001 | Technical Specification Violation Associated with Failure to Perform Offsite Circuit Verification | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2010-001 | Invalid Isolation Signal Results in Shutdown Cooling Interruption | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | 05000424/LER-2010-001 | Breaker Failure Results in I B Train Containment Cooling System Being Declared Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000416/LER-2010-001 | Automatic Reactor Scram On Decreasing Reactor Water Level Due To Inadvertent Reactor Feed Pump Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000249/LER-2010-001 | OPRM Power Supply Failure during Maintenance Results in Unit 3 Automatic Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2010-001 | Two Shutdown Bank Rods Were Dropped from Fully Withdrawn Position | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(iv), System Actuation | 05000261/LER-2010-002 | Plant Trip due to Electrical Fault | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2010-002 | Condition that Could Have Prevented the Fulfillment of a Safety Function | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000335/LER-2010-002 | Opened ECCS Boundary Door in Violation of Identified Compensatory Measures | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000334/LER-2010-002 | 270 Degree Circumferential Flaw Found on Residual Heat Removal System Drain Valve Socket Weld | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000316/LER-2010-002 | Containment Divider Barrier Seal Mounting Bolts Not Properly Installed | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000250/LER-2010-002 | Fuel Transfer Pump Failure Renders 3B Emergency Diesel Generator Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2010-002 | Manual Reactor Trip due to 1A1 and 1A2 Reactor Coolant PumDHigh Vibration Indication | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000315/LER-2010-002 | Manual Auxiliary Feedwater Actuation in Response to Main Feedpump Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000271/LER-2010-002 | Inoperability of Main Steam Safety Relief Valves due to Degraded Thread Seals | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000277/LER-2010-002 | Improperly Fastened Rod Hanger Results in Inoperable Subsystem of Emergency Service Water | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000413/LER-2010-002 | Discovery of Reactor Coolant System Pressure Boundary Leak at Thermowell 1NCTW5850 Seal Weld. | | 05000282/LER-2010-002 | Postulated Flooding of Unit 1 Fuel Oil Transfer Pump Motor Starters Could Have Resulted In Reduced Fuel Oil Inventory | | 05000414/LER-2010-002 | Duke Energy Corporation Catawba Nuclear Station 4800 Concord Road York, SC 29745 803-701-4251 803-701-3221 fax December 15, 2010 U.S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, D.C. 20555
Subject:�Duke Energy Carolinas, LLC (Duke Energy)
Catawba Nuclear Station, Unit 2
Docket No. 50-414
Licensee Event Report 414/2010-002
Pursuant to 10 CFR 50.73(a)(1) and (d), attached is Licensee Event Report 414/2010-002, Revision 0 entitled, "Technical Specification Violation Involving Mode Change with Inoperable Auxiliary Feedwater System Train Due to Closed Pump Discharge Valves". This report is being submitted in accordance with 10 CFR 50.73(a)(2)(i)(B). There are no regulatory commitments contained in this letter or its attachment. This event is considered to be of no significance with respect to the health and safety of the public. If there are any questions on this report, please contact L.J. Rudy at (803) 701-3084. Sincerely, faius4- A James R. Morris LJR/s Attachment www.duke-energy.corn (14 Document Control Desk Page 2 December 15, 2010 xc (with attachment): L.A. Reyes Regional Administrator U.S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 J.H. Thompson (addressee only) NRC Project Manager U.S. Nuclear Regulatory Commission Mail Stop 8-G9A 11555 Rockville Pike Rockville, MD 20852-2738 G.A. Hutto, Ill NRC Senior Resident Inspector Catawba Nuclear Station INPO Records Center 700 Galleria Place Atlanta, GA 30339-5957 NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 10/31/2013 (10-2010) Estimated burden per response to comply with this mandatory collection request: 80 hours. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send commentsLICENSEE EVENT REPORT (LER) regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-mail to infocollectssesource@nre.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used(See reverse for required number of to impose an information collection does not display a currently valid OMB control number, the NRCdigits/characters for each block) may not conduct or sponsor, and a person is not required to respond to, the info(mation collection. 1.. FACILITY NAME 2. DOCKET NUMBER I3. PAGE Catawba Nuclear Station, Unit 2 05000414 1 OF 7 4. TITLE Technical Specification Violation Involving Mode Change with Inoperable Auxiliary Feedwater System Train Due to Closed Pump Discharge ValvesD • | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000306/LER-2010-002 | Unit 2 Turbine Shutdown Due To the Loss of a Main Feed Water Pump That Resulted in a Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2010-002 | Piping Leak Results in Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000382/LER-2010-002 | Main Feedwater Isolation Valve B exceeded allowed outage time due to tubing connection failure | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000370/LER-2010-002 | ref Energy® REGIS T. REPKO Vice President McGuire Nuclear Station Duke Energy MGO1VP / 12700 Hagers Ferry Rd. Huntersville, NC 28078 980-875-4111 980-875-4809 fax regis.repko(Codu ke-energy.corn 10 CFR 50.73 May 10, 2011 U.S. Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, D.C. 20555 Subject: D Duke Energy Carolinas, LLC McGuire Nuclear Station, Unit 2 Docket Nos. 50-370 Licensee Event Report (LER) 370/2010-02, Supplement 1 Problem Investigation Process (PIP) M-10-05982 Pursuant to 10 CFR 50.73 Sections (a) (1) and (d), attached is Supplement 1 to Licensee Event Report 370/2010-02, regarding past inoperability of the Unit 2 "A" Train Nuclear Service Water System and satisfies the commitment to supplement the LER following completion of the root cause analysis This supplement to LER 370/2010-02 supersedes the LER previously submitted December 20, 2010. Completion of the root cause analysis has not affected the original reporting criteria which was completed in accordance with 10 CFR 50.73 (a) (2) (i) (B), an Operation Prohibited by Technical Specifications, and 10 CFR 50.73 (a) (2) (v) (B), any Event or Condition That Could Have Prevented Fulfillment of the Safety Function needed to remove residual heat. Additionally, the supplement did not affect the significance of the event which was considered to be of no significance with respect to the health and safety of the public. There are no regulatory commitments contained in this report. If questions arise regarding this LER, contact Rick Abbott at 980-875-4685. Very truly yours, Zi1:77 Regis T. Repko Attachment www. duke-energy. corn U.S. Nuclear Regulatory Commission May 10, 2011 Page 2 cc:�V. M. McCree, Regional Administrator U.S. Nuclear Regulatory Commission, Region II
Marquis One Tower
245 Peachtree Center Ave., NC, Suite 1200
Atlanta, Georgia 30303-1257
Jon H. Thompson (Addressee Only)
Senior Project Manager (McGuire)
U.S. Nuclear Regulatory Commission
11555 Rockville Pike
Rockville, MD 20852-2738
J. B. Brady
Senior Resident Inspector
U.S. Nuclear Regulatory Commission
McGuire Nuclear Station
W. L. Cox Ill, Section Chief North Carolina Department of Environment and Natural Resources Division of Environmental Health Radiation Protection Section 1645 Mail Service Center Raleigh, NC 27699-1645 NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB. NO 3150-0104 EXPIRES: 08/31/2013 (10-2010) Estimated burden per response to comply with this mandatory collection request: SO hours. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA/Privacy Section (T-5 F53), U.S. Nuclear Regulatory Commission. Washington, DC 20555-0001, or by Internet e-mail to info (See reverse for required number of collects resmirceOnrc.gov, and to the Desk Officer, Office of Information and Regulatory digits/characters for each block) Affairs, NEOB-10202, (3150-01041, Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. LICENSEE EVENT REPORT (LER) 1. FACILITY NAME 2. DOCKET NUMBER 3. PAGE McGuire Nuclear Station,2Unit 2 05000-212
0370 OF-7 4. TITLE Unit 2 Nuclear Service Water System "A" Train Past Inoperable due to
Failed Strainer Differential Pressure Instrument. | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000369/LER-2010-002 | | | 05000456/LER-2010-002 | Limiting Condition for Operation Action Not Completed Within the Required Time | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000249/LER-2010-003 | Steam Leak Results in HPCI Inoperability | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000251/LER-2010-003 | Damaged Speed Sensor Caused the 4A Emergency Diesel Generator to be Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|