Technical Specification On February 1, (TS) " AC Power Sources 2010, 3.8.1, - Operating" was violated for Units 1 and 2. The violation occurred following the racking out.of a 6.9 kV bus tie breaker for preventive maintenance. Due to unclear TS Bases, plant personnel did not recognize that with the tie breaker racked out, one offsite circuit was inoperable.
Licensed Operations personnel failed to adequately evaluate and perform the required actions associated with the inoperability of the offsite circuit in a timely manner. (SR) Surveillance Requirement 3.8.1.1 was not performed within one hour as required to verify that the other offsite circuit was operable. SR 3.8.1.1 was subsequently performed for both units and the tie breaker was subsequently racked back in, thereby restoring the inoperable offsite circuit to operable status. Planned corrective actions include enhancing the affected TS Bases. Throughout this event, all 4.16 kV Engineered Safety Feature buses remained energized and backed by available Diesel Generators. The health and safety of the public were not adversely affected by this event. |
LER-2010-001, Technical Specification Violation Associated with Failure to Perform Offsite Circuit VerificationDocket Number |
Event date: |
|
---|
Report date: |
|
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
---|
4132010001R00 - NRC Website |
|
BACKGROUND
This event is being reported under the following criterion:
10 CFR 50.73(a)(2)(i)(B), any operation or condition which was prohibited by the plant's Technical Specifications.
Catawba Nuclear Station Units 1 and 2 are Westinghouse four-loop Pressurized Water Reactors (PWRs) [EIIS: RCT].
The unit Essential Auxiliary Power Distribution System [EIIS: EB] AC sources consist of the offsite power sources (normal and alternate), and the onsite standby power sources (Train A and Train B Diesel Generators (DGs) [EIIS: EK]). As required by 10 CFR 50, Appendix A, General Design Criterion 17, the design of the AC electrical power system provides independence and redundancy to ensure an available source of power to the Engineered Safety Feature (ESF) systems [EIIS:
JE].
The onsite Class 1E AC Distribution System is divided into redundant load groups (trains) so that the loss of any one group does not prevent the minimum safety functions from being performed. Each train has connections to two preferred offsite power sources and a single DG.
From the transmission network, two electrically and physically separated circuits provide AC power, through step down station auxiliary transformers [EIIS: XFMR], to the 4.16 kV ESF buses [EIIS:
BU]. A qualified offsite circuit consists of all breakers [EIIS: 52], transformers, switches [EIIS: IS], interrupting devices [EIIS: GFI], cabling [EIIS: CBL], and controls [EIIS: JC] required to transmit power from the offsite transmission network to the onsite Class 1E ESF bus(es).
The onsite standby power source for each 4.16 kV ESF bus is a dedicated DG. DGs A and B are dedicated to ESF buses ETA and ETB, respectively.
Two qualified circuits between the offsite transmission network and the onsite Essential Auxiliary Power System and separate and independent DGs for each train ensure availability of the required power to shut down the reactor and maintain it in a safe shutdown condition after an Anticipated Operational Occurrence or a postulated Design Basis Accident.
TS Limiting Condition for Operation (LCO) 3.8.1 governs the AC sources while in Modes 1, 2, 3, and 4. LCO 3.8.1 requires two offsite circuits and two DGs to be operable for each unit. With one offsite circuit inoperable, Condition A allows for continued operation for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Additionally, Surveillance Requirement (SR) 3.8.1.1 (verify correct breaker alignment and indicated power availability for each offsite circuit) must be performed for the operable offsite circuit within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.
SR 3.8.1.8 (verify automatic and manual transfer of AC power sources from the normal offsite circuit to each alternate offsite circuit) is required to be performed every 18 months. Transfer of each 4.16 kV ESF bus power supply from the normal offsite circuit to the alternate offsite circuit demonstrates the capability of the alternate circuit distribution network to power the shutdown loads. The alternate circuit distribution network consists of an offsite power source through a 6.9 kV bus incoming breaker, its associated 6.9 kV bus tie breaker, and the aligned 6.9/4.16 kV transformer to the essential bus.
The requirement of this SR is the transfer from the normal offsite circuit to the alternate offsite circuit via the automatic and manual actuation of the 6.9 kV bus tie breaker and 6.9 kV bus incoming breakers upon loss of the normal credited offsite source.
The following table depicts the relationship between the offsite circuits, the tie breakers, and the ESF buses supported for Unit 1 and Unit 2.
Offsite Circuit Tie Breaker� ESF Bus Supported 1A�N/A Normal to lETA 1TD7 Alternate to lETB 1B N/A Normal to lETB 1TA7 Alternate to lETA 2A�N/A Normal to 2ETA 2TD7 Alternate to 2ETB 2B N/A Normal to 2ETB 2TA7 Alternate to 2ETA On February 1, 2010, when this event occurred, Units 1 and 2 were in Mode 1 at 100% power operation.
EVENT DESCRIPTION
(Certain event times are approximate.) Date/Time�Event Description 02/01/10/0445 Tie breaker 1TA7 was racked out for preventive maintenance.
1130 Preventive maintenance work was recognized by Operations as being complete.
1320 Operations experienced difficulty racking 1TA7 back in.
1618 Work request written concerning the difficulty experienced racking 1TA7 back in.
1730-1745 Operations and Regulatory Compliance discussed the implication of 1TA7 being racked out on operability. It was noted that since SR 3.8.1.8 was not met with 1TA7 racked out, that LCO 3.8.1 was not met.
1830�Offsite circuit 1A was declared inoperable.
1938 SR 3.8.1.1 was performed for Unit 1.
-2210 �1TA7 was racked in 02/02/10/0030 Operations logged the inoperability into the Technical Specification Action Item Log (TSAIL) and noted the impact on Unit 2. SR 3.8.1.1 was subsequently performed for Unit 2.
CAUSAL FACTORS
The root cause of this event was that the TS Bases for SR 3.8.1.8 are unclear in relation to the design basis requirements for the 6.9 kV bus tie breakers. This is a legacy issue and the lack of clarity subsequently led to a lack of understanding of the importance of the tie breakers by various plant groups.
The TS Bases for SR 3.8.1.8 do not delineate which offsite circuit is to be considered inoperable if a particular tie breaker is incapable of performing its function. Additionally, there is no design basis document information available related to this issue. From a review of design documents, this lack of clarity dates back to the original design of the system and to the documentation of the TS SR Bases. This lack of clarity has therefore affected the operational control of the tie breakers since 1996 (refer to the last paragraph of this section).
Once it was recognized that an offsite circuit was inoperable, SR 3.8.1.1 was not performed within one hour as required by TS 3.8.1, Required Action A.1. Due to multiple ongoing activities, licensed Operations personnel failed to adequately evaluate and perform the required actions associated with the inoperability of the 1A offsite circuit in a timely manner. Additionally, personnel failed to adequately apply 1TA7's cascading effects to Unit 2. (The cascading effects result from the fact that Catawba has two safety related shared motor control centers, one for each train, which can be powered from either unit and which support the operation of certain shared safety related equipment.) Timely application of these cascading effects would have led to verification of the operable offsite circuit within the one-hour time limit.
Events similar to this could have potentially occurred at Catawba as far back as 1996. In 1996, the preventive maintenance work on the 6.9 kV bus tie breakers was moved from outage to innage with a five-year maintenance frequency. Prior to 1996, work on these tie breakers would have occurred during the respective unit outage(s); therefore, this event was not considered to have been a credible occurrence prior to 1996.
CORRECTIVE ACTIONS
Immediate:
1.Tie breaker 1TA7 was racked in, thereby restoring operability to the affected offsite circuit.
2.Plant personnel verified that the breaker issue had no impact on the overall plant risk profile.
3.A comment was placed within the tagging system to alert plant personnel as to the importance of the tie breakers relative to offsite circuit operability.
Subsequent:
1.A lessons learned communication was provided to all shift Operations personnel concerning this event.
2.PT/1,2/A/4350/003, "Electrical Power Source Alignment.
Verification" were revised to add a weekly check of the applicable tie breakers being racked in and open. Information was also added regarding the critical nature of the tie breakers.
3.OP/0/A/6350/010, "Operation of Station Breakers and Disconnects" was revised to add information regarding the tie breakers and their relevance to TS 3.8.1.
Planned:
1.The TS Bases for SR 3.8.1.8 will be revised to clarify the design basis of the offsite circuits and the relationship to the tie breakers.
2.The Design Basis Document for the 4.16 kV Essential Auxiliary Power System will be revised to include a clear design basis for the tie breakers.
There are no NRC commitments contained in this LER.
SAFETY ANALYSIS
There was no safety significance to:this .event. At no time was offsite power lost to either of the 4.16 kV ESF buses ETA 'or ETB. With the tie breaker removed from service, the only adverse- effect: upon,the plant was the inability to comply with SR 3.8.1..8. Although SR 3.8.1.1 was performed late, the surveillance demonstrated that the required offsite circuits were, in fact, operable. Also, both train's DGs remained available throughout this event, thereby ensuring that standby emergency power was available to the ESF buses, ha.d it been required.
The health and safety of the public were not adversely affected by this event.
ADDITIONAL INFORMATION
'Within the previous three years,.there.were no LER .events involving the failure to perform SR 3.8.1.1 within one hour as required by TS 3.8.1.
Therefore, this event .is considered to be non-recurring.
Energy Industty Identification System (EIIS) codes are identified in the text'as [EIIS: XX]. 'This event-is not considered reportable to the EqUipment Performance and Information Exchange (EPIX)'.program.
This event is not considered to constitute. a Safety System Functional Failure.
- There was no release.of radioactive 'material, radiation overexposure, or personnel injury associated with the event described in this LER.
|
---|
|
|
| | Reporting criterion |
---|
05000220/LER-2010-001 | Reactor Scram Due to Inadequate Post Maintenance Testing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000410/LER-2010-001 | Reactor Scram Due to Inadvertent Actuation of the Redundant Reactivity Control System During Maintenance | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000395/LER-2010-001 | Reactor Building Cooling Units Reduced Air Flow Rate Below Technical Specification Limits | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000382/LER-2010-001 | Spent Fuel Pool Cooling Single Failure | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | 05000374/LER-2010-001 | High Pressure Core Spray System Declared Inoperable Due to Failed Room Ventilation Control Relay | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000373/LER-2010-001 | Unauthorized Individual Gained Access to the Protected Area. | | 05000370/LER-2010-001 | Loose connection in a panel board serving a Solid State Protection System Train concurrent with redundant train maintenance could have prevented fulfillment of a safety function. | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000261/LER-2010-001 | Emergency Diesel Generator Inoperable in Excess of Technical Specifications Allowed Completion Time | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000263/LER-2010-001 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000255/LER-2010-001 | Potential Loss of Safety Function Due to a Service Water Pump Shaft Coupling Failure | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000266/LER-2010-001 | Engineered Safety Features Steam Line Pressure Dynamics Modules Discovered Outside of Technical Specification Values | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000306/LER-2010-001 | Unit 2 Turbine Trip during Reactor Shutdown Resulting in a Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000305/LER-2010-001 | Safety Injection Pump Recirculation Line Isolation Results in Violation of Technical Specifications | | 05000298/LER-2010-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2010-001 | Standby Shutdown Facility Letdown Line Orifice Strainer Blocked by Valve Gasket Material | 10 CFR 50.73(a)(2)(i)(b) | 05000282/LER-2010-001 | Unanalyzed Condition Due to Postulated High Energy Line Break On Cooling Water System | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000277/LER-2010-001 | Multiple Slow Control Rods Results in Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i) | 05000361/LER-2010-001 | Broken Manual Valve Prevents Timely Condensate Storage Tank Isolation | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000483/LER-2010-001 | Emergency Core Cooling System MODE 4 Operating Practices Prohibited by current Technical Specification 3.5.3 | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000498/LER-2010-001 | Unit Shutdown Required by Technical Specifications | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000316/LER-2010-001 | Valid Actuation of Auxiliary Feedwater System in Response to Valid Steam Generator Low-Low Levels | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000321/LER-2010-001 | Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000336/LER-2010-001 | Millstone Power Station Unit 2 Reactor Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000413/LER-2010-001 | Technical Specification Violation Associated with Failure to Perform Offsite Circuit Verification | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2010-001 | Invalid Isolation Signal Results in Shutdown Cooling Interruption | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | 05000424/LER-2010-001 | Breaker Failure Results in I B Train Containment Cooling System Being Declared Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000416/LER-2010-001 | Automatic Reactor Scram On Decreasing Reactor Water Level Due To Inadvertent Reactor Feed Pump Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000249/LER-2010-001 | OPRM Power Supply Failure during Maintenance Results in Unit 3 Automatic Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2010-001 | Two Shutdown Bank Rods Were Dropped from Fully Withdrawn Position | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(iv), System Actuation | 05000261/LER-2010-002 | Plant Trip due to Electrical Fault | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2010-002 | Condition that Could Have Prevented the Fulfillment of a Safety Function | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000335/LER-2010-002 | Opened ECCS Boundary Door in Violation of Identified Compensatory Measures | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000334/LER-2010-002 | 270 Degree Circumferential Flaw Found on Residual Heat Removal System Drain Valve Socket Weld | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000316/LER-2010-002 | Containment Divider Barrier Seal Mounting Bolts Not Properly Installed | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000250/LER-2010-002 | Fuel Transfer Pump Failure Renders 3B Emergency Diesel Generator Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2010-002 | Manual Reactor Trip due to 1A1 and 1A2 Reactor Coolant PumDHigh Vibration Indication | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000315/LER-2010-002 | Manual Auxiliary Feedwater Actuation in Response to Main Feedpump Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000271/LER-2010-002 | Inoperability of Main Steam Safety Relief Valves due to Degraded Thread Seals | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000277/LER-2010-002 | Improperly Fastened Rod Hanger Results in Inoperable Subsystem of Emergency Service Water | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000413/LER-2010-002 | Discovery of Reactor Coolant System Pressure Boundary Leak at Thermowell 1NCTW5850 Seal Weld. | | 05000282/LER-2010-002 | Postulated Flooding of Unit 1 Fuel Oil Transfer Pump Motor Starters Could Have Resulted In Reduced Fuel Oil Inventory | | 05000414/LER-2010-002 | Duke Energy Corporation Catawba Nuclear Station 4800 Concord Road York, SC 29745 803-701-4251 803-701-3221 fax December 15, 2010 U.S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, D.C. 20555
Subject:�Duke Energy Carolinas, LLC (Duke Energy)
Catawba Nuclear Station, Unit 2
Docket No. 50-414
Licensee Event Report 414/2010-002
Pursuant to 10 CFR 50.73(a)(1) and (d), attached is Licensee Event Report 414/2010-002, Revision 0 entitled, "Technical Specification Violation Involving Mode Change with Inoperable Auxiliary Feedwater System Train Due to Closed Pump Discharge Valves". This report is being submitted in accordance with 10 CFR 50.73(a)(2)(i)(B). There are no regulatory commitments contained in this letter or its attachment. This event is considered to be of no significance with respect to the health and safety of the public. If there are any questions on this report, please contact L.J. Rudy at (803) 701-3084. Sincerely, faius4- A James R. Morris LJR/s Attachment www.duke-energy.corn (14 Document Control Desk Page 2 December 15, 2010 xc (with attachment): L.A. Reyes Regional Administrator U.S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 J.H. Thompson (addressee only) NRC Project Manager U.S. Nuclear Regulatory Commission Mail Stop 8-G9A 11555 Rockville Pike Rockville, MD 20852-2738 G.A. Hutto, Ill NRC Senior Resident Inspector Catawba Nuclear Station INPO Records Center 700 Galleria Place Atlanta, GA 30339-5957 NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 10/31/2013 (10-2010) Estimated burden per response to comply with this mandatory collection request: 80 hours. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send commentsLICENSEE EVENT REPORT (LER) regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-mail to infocollectssesource@nre.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used(See reverse for required number of to impose an information collection does not display a currently valid OMB control number, the NRCdigits/characters for each block) may not conduct or sponsor, and a person is not required to respond to, the info(mation collection. 1.. FACILITY NAME 2. DOCKET NUMBER I3. PAGE Catawba Nuclear Station, Unit 2 05000414 1 OF 7 4. TITLE Technical Specification Violation Involving Mode Change with Inoperable Auxiliary Feedwater System Train Due to Closed Pump Discharge ValvesD • | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000306/LER-2010-002 | Unit 2 Turbine Shutdown Due To the Loss of a Main Feed Water Pump That Resulted in a Reactor Scram | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2010-002 | Piping Leak Results in Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000382/LER-2010-002 | Main Feedwater Isolation Valve B exceeded allowed outage time due to tubing connection failure | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000370/LER-2010-002 | ref Energy® REGIS T. REPKO Vice President McGuire Nuclear Station Duke Energy MGO1VP / 12700 Hagers Ferry Rd. Huntersville, NC 28078 980-875-4111 980-875-4809 fax regis.repko(Codu ke-energy.corn 10 CFR 50.73 May 10, 2011 U.S. Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, D.C. 20555 Subject: D Duke Energy Carolinas, LLC McGuire Nuclear Station, Unit 2 Docket Nos. 50-370 Licensee Event Report (LER) 370/2010-02, Supplement 1 Problem Investigation Process (PIP) M-10-05982 Pursuant to 10 CFR 50.73 Sections (a) (1) and (d), attached is Supplement 1 to Licensee Event Report 370/2010-02, regarding past inoperability of the Unit 2 "A" Train Nuclear Service Water System and satisfies the commitment to supplement the LER following completion of the root cause analysis This supplement to LER 370/2010-02 supersedes the LER previously submitted December 20, 2010. Completion of the root cause analysis has not affected the original reporting criteria which was completed in accordance with 10 CFR 50.73 (a) (2) (i) (B), an Operation Prohibited by Technical Specifications, and 10 CFR 50.73 (a) (2) (v) (B), any Event or Condition That Could Have Prevented Fulfillment of the Safety Function needed to remove residual heat. Additionally, the supplement did not affect the significance of the event which was considered to be of no significance with respect to the health and safety of the public. There are no regulatory commitments contained in this report. If questions arise regarding this LER, contact Rick Abbott at 980-875-4685. Very truly yours, Zi1:77 Regis T. Repko Attachment www. duke-energy. corn U.S. Nuclear Regulatory Commission May 10, 2011 Page 2 cc:�V. M. McCree, Regional Administrator U.S. Nuclear Regulatory Commission, Region II
Marquis One Tower
245 Peachtree Center Ave., NC, Suite 1200
Atlanta, Georgia 30303-1257
Jon H. Thompson (Addressee Only)
Senior Project Manager (McGuire)
U.S. Nuclear Regulatory Commission
11555 Rockville Pike
Rockville, MD 20852-2738
J. B. Brady
Senior Resident Inspector
U.S. Nuclear Regulatory Commission
McGuire Nuclear Station
W. L. Cox Ill, Section Chief North Carolina Department of Environment and Natural Resources Division of Environmental Health Radiation Protection Section 1645 Mail Service Center Raleigh, NC 27699-1645 NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB. NO 3150-0104 EXPIRES: 08/31/2013 (10-2010) Estimated burden per response to comply with this mandatory collection request: SO hours. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA/Privacy Section (T-5 F53), U.S. Nuclear Regulatory Commission. Washington, DC 20555-0001, or by Internet e-mail to info (See reverse for required number of collects resmirceOnrc.gov, and to the Desk Officer, Office of Information and Regulatory digits/characters for each block) Affairs, NEOB-10202, (3150-01041, Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. LICENSEE EVENT REPORT (LER) 1. FACILITY NAME 2. DOCKET NUMBER 3. PAGE McGuire Nuclear Station,2Unit 2 05000-212
0370 OF-7 4. TITLE Unit 2 Nuclear Service Water System "A" Train Past Inoperable due to
Failed Strainer Differential Pressure Instrument. | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000369/LER-2010-002 | | | 05000456/LER-2010-002 | Limiting Condition for Operation Action Not Completed Within the Required Time | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000249/LER-2010-003 | Steam Leak Results in HPCI Inoperability | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000251/LER-2010-003 | Damaged Speed Sensor Caused the 4A Emergency Diesel Generator to be Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|