Title | Licensee-Identified Violation |
Description | Title 10 CFR 50.55a(g)(5 )(i) , ISI Program Update: Applicable ISI Code Editions and Addenda, requires , in part, that the inservice inspection program for a boiling water - cooled nuclear power facility must be revised by the licensee, as necessary, to meet the requirements of paragraph (g)(4) of this section. Paragraph (g)4 (ii ), Applicable ISI Code: Successive 120- Month Intervals, requires, in part, that inservice examination of components and system pressure tests conducted during successive 120- month inspection intervals must comply with the requirements of the latest edition and addenda of the Code incorporated by reference in paragraph (a) of this section, 12 months before the start of the 120- month inspection interval. Contrary to these requirements, the licensee failed to issue the inspection plan for the fourth 10- year inservice inspection interval in a timely manner . Specifically, the licensee failed to issue the inservice inspection plan until January 27, 2016, even though the third 10- year inservice inspection interval had ended on December 13, 2015. A relief request to allow emergent repairs to be completed under the third 10 -year inservice inspection plan was requested by the licensee on December 16, 2015, and was approved by the NRC ; however, no repairs needed to be completed. The finding was of very low safety significance (Green) because the finding did not represent an actual loss of safety function of a system or train and did not result in the loss of a single train for greater than technical specification 31 allowed outage time. This issue was entered into the licensees corrective action program as A R 00341506. |
Site: | Columbia |
---|---|
Report | IR 05000397/2017002 Section 4OA7 |
Date counted | Jun 30, 2017 (2017Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | G Kolcum R Alexander D Bradley L Brandt L Carson J Drake S Money J O'Donnell M Haire |
Violation of: | 10 CFR 50.55a Technical Specification |
INPO aspect | |
' | |