Title | Failure to provide design control measures to withstand the effects of flooding on the reactor auxiliary building roof |
Description | The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B, Criterion III, because the licensee did not provide design control measures for verifying or checking the adequacy of the features designed to withstand the effects of a probable maximum precipitation (PMP) flooding event on the reactor auxiliary building (RAB) roof areas. Specifically, the licensee did not provide an analysis to demonstrate that adequate flood protection existed from the effects of a PMP flooding event on safety-related components and electrical equipment located on the roof of the RAB in the main steam isolation valve (MSIV) wing areas. As a result, the licensee did not perform an analysis to determine if expected ponding levels from a PMP flooding event would challenge safety-related components and electrical equipment such as the emergency feedwater flow control and isolation valves and cables, main steam isolation valves and cables, atmospheric dump valves, and back-up nitrogen accumulator components. The licensee entered this issue into their corrective action program as CR-WF3-2012- 7520. The immediate corrective actions taken to restore compliance included the performance of a preliminary analysis to show that the installed scuppers and roof drains have margin to protect against a local PMP flooding event and that the ponding depth would have little or no affect on the safety-related equipment and cables located in the MSIV wing areas. The failure to provide design control measures for verifying or checking the adequacy of the features designed to withstand the effects of a local PMP on the RAB roof areas was a performance deficiency. The performance deficiency was more than minor because it was associated with the design control attribute of the Mitigating System cornerstone and affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the safety-related equipment located on the RAB roof in the MSIV wing areas are required to safely shutdown and maintain the reactor in a cold shutdown condition following accidents and anticipated operational occurrences. The inspectors used the NRC Inspection Manual Chapter 0609, Attachment 4, Initial Characterization of Findings and Appendix A, The Significance Determination Process for Findings At-Power, to evaluate this issue. The inspectors determined that the finding was of very low safety significance (Green) because it did not involve the loss or degradation of equipment or function specifically designed to mitigate a seismic, flooding, or severe weather initiating event. The inspectors concluded that the finding reflected current licensee performance and involved a cross-cutting aspect in the corrective action program component of the problem identification and resolution area in that the licensee did not identify potential flooding issues completely, accurately, and in a timely manner commensurate with their safety significance. |
Site: | Waterford ![]() |
---|---|
Report | IR 05000382/2013003 Section 1R01 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.01 |
Inspectors (proximate) | M Davis G George D Allen R Azua M Baquera N Okonkwo M Williams D Bradley |
Violation of: | 10 CFR 50 Appendix B Criterion III, Design Control |
CCA | P.1, Identification |
INPO aspect | PI.1 |
' | |