Finding | |
|---|---|
| Title | Licensee-Identified Violation |
| Description | According to 10 CFR 50.74, each licensee shall notify the NRC within 30 days of a change in an operators or senior operators status including termination of any operator or senior operator. Contrary to this requirement, in NOTF 20727574, PSEG identified that Hope Creek staff did not notify the NRC of the resignation of a licensed reactor operator. The licensed reactor operator resigned on November 12, 2015, but PSEG did not notify the NRC of the change in status until May 9, 2016. This issue meets the criteria for a SL IV violation because the May 9, 2016, notification did not result in increased inspection activities or cause the NRC to reconsider a regulatory position. |
| Site: | Hope Creek |
|---|---|
| Report | IR 05000354/2016002 Section 4OA7 |
| Date counted | Jun 30, 2016 (2016Q2) |
| Type: | TEV: Severity level IV |
| cornerstone | Mitigating Systems |
| Identified by: | Licensee-identified |
| Inspection Procedure: | |
| Inspectors (proximate) | F Bower J Hawkins M Draxton R Nimitz S Haney |
| Violation of: | 10 CFR 50.74 |
| INPO aspect | |
| ' | |
Finding - Hope Creek - IR 05000354/2016002 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Hope Creek) @ 2016Q2
Self-Identified List (Hope Creek)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||