| Q | CCA | Title |
---|
05000338/FIN-2009002-02 | 2009Q1 | H.13 | Failure to Accomplish Procedures Renders Both Trains of High Head Safety Injection System Inoperable |
05000338/FIN-2009002-01 | 2009Q1 | | Degradation of the Containment Sump |
05000338/FIN-2009003-01 | 2009Q2 | | Degradation of a Flood Protection Feature |
05000338/FIN-2009003-02 | 2009Q2 | H.8 | Failure to Repair or Rework Nonconforming Parts in Accordance with Documented Procedures |
05000338/FIN-2009003-03 | 2009Q2 | P.2 | Failure to promptly identify and correct a condition adverse to quality involving inadequate tornado missile protection for the EDG day tank vents |
05000338/FIN-2009004-04 | 2009Q3 | | LHSI/ORS Pump Discharge Piping Interference |
05000338/FIN-2009004-07 | 2009Q3 | P.2 | Failure to Determine Cause and Related Corrective Action Results in Loss of a Required Offsite Power Supply |
05000338/FIN-2009004-06 | 2009Q3 | | Failure to Adequately Design and Install Oil Collection Devices for Reactor Coolant Pump Motor Stator Air Coolers |
05000338/FIN-2009004-03 | 2009Q3 | | Degradation of a Flood Protection Feature |
05000338/FIN-2009004-02 | 2009Q3 | | Fire Brigade Performance |
05000338/FIN-2009004-01 | 2009Q3 | | Control of Transient Combustibles |
05000338/FIN-2009004-05 | 2009Q3 | H.9 H.2(b) | Preconditioning of the Low Head Safety Injection Motor Operated Valves |
05000338/FIN-2009007-03 | 2009Q4 | | Failure to Ensure the Adequacy of Control Voltage to the 4160 and 480 VAC Equipment |
05000338/FIN-2009007-02 | 2009Q4 | H.7 | Failure to Ensure RSST A LTC Controller Settings were Correctly Implemented |
05000338/FIN-2009008-03 | 2009Q4 | H.7 | Inadequate Procedure for Powering Credited Components for Fire in Cable Vault & Tunnel |
05000338/FIN-2009008-02 | 2009Q4 | | Failure to Adequately Address the Potential for CO2 Over-Pressurization Within the Unit 2 Cable Vault & Tunnel |
05000338/FIN-2009007-01 | 2009Q4 | | Failure to Perform Periodic TOL Testing on Unit 1 |
05000338/FIN-2009201-01 | 2009Q4 | | Security |
05000338/FIN-2009005-04 | 2009Q4 | | Development of Work Orders |
05000338/FIN-2009005-03 | 2009Q4 | | Units 1 and 2 Station Battery Cable Installation Issues |
05000338/FIN-2009005-02 | 2009Q4 | | Feedwater Pipe Support Issues |
05000338/FIN-2009005-01 | 2009Q4 | | Inspection of Underground Cables |
05000338/FIN-2009008-01 | 2009Q4 | | Qualification of Fire Barrier Floor/Wall Penetration of Aluminium Conduit Through Sleeve |
05000338/FIN-2009005-05 | 2009Q4 | | Inadequate Procedure Results in Excess Letdown Heat Exchanger Leakage |