Finding | |
|---|---|
| Title | Inadequate Procedure For Technical Specification |
| Description | The inspectors identified a finding of very low safety significance (Green) and an associated NCV of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure to have appropriate procedures to complete TS-required surveillances. Specifically, OSP-CCI-004, Containment Isolation Valve Verification, did not contain adequate steps to complete a TS-required airlock door check and the procedure did not include six manual containment isolation valves (CIVs) that should have been included in the procedure for position verification. The licensee corrected the procedure and entered the issue into its CAP as CRs 464355, 464494, and 467560, and planned to perform an ACE. The inspectors determined that the finding was more than minor in accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, because the finding was associated with the Barrier Integrity Cornerstone attribute of procedure quality and affected the cornerstone objective of providing reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, inspectors found seven examples in OSP-CCI-004 where either the procedure steps were not adequate or CIVs were missing that should have been included in the procedure for position verification. The inspectors determined the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 - Initial Screening and Characterization of Findings, Table 4a for the Barrier Integrity Cornerstone, dated January 10, 2008. The inspectors answered No to the Containment Barrier questions and screened the finding as having very low safety significance (Green). This finding has a cross-cutting aspect in the area of human performance, resources, because the licensee did not ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety was supported. Specifically, OSP-CCI-004 did not get an approval review during the procedure review process and the supervisory review that was conducted did not identify the procedural errors. |
| Site: | Kewaunee |
|---|---|
| Report | IR 05000305/2012002 Section 1R22 |
| Date counted | Mar 31, 2012 (2012Q1) |
| Type: | NCV: Green |
| cornerstone | Barrier Integrity |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.22 |
| Inspectors (proximate) | D Mcneil K Riemer R Krsek K Barclay A Shaikh |
| CCA | H.2, Field Presence |
| INPO aspect | LA.2 |
| ' | |