| Title | Licensee-Identified Violation |
| Description | Technical Specification 5.8.1 requires in part, that procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Appendix A of Regulatory Guide 1.33, Revision 2. That appendix states, in part, that maintenance that can affect the performance of safety-related equipment should be performed in accordance with written procedures appropriate to the circumstances. Contrary to the above, maintenance that can affect the performance of safety-related equipment was not performed in accordance with written procedures appropriate to the circumstances. Specifically, maintenance that can affect the performance of safetyrelated valves was not performed in accordance with a procedure that required the licensee to review all diagnostic test results for compliance with the setpoint criteria for all diagnostic tests performed. As described in CR-2012-01601-017, the licensee restored compliance by writing and implementing procedure ER-FC- 410-AD-SETPOINT, Air-Operated Valve Setpoint Control, Revision 0. This procedure requires, in part, that the licensee review all diagnostic test results for compliance with the setpoint criteria for all diagnostic tests performed. The licensees failure to complete maintenance that can affect the performance of safety-related valves in accordance with written procedures appropriate to the circumstances was a performance deficiency that is more-than-minor because it adversely affected the Procedure Quality attribute of the Mitigating Cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, this performance deficiency resulted in valve HCV-2987, High Pressure Safety Injection Alternate Header Isolation, being not able to fulfill its design safety function from February, 2013, through July, 2013. Using Manual Chapter 0609, Attachment 4, Initial Characterization of Findings, dated June 19, 2012, the inspectors determined that the finding should be processed through Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, dated July 1, 2012. Using Appendix A, Exhibit 2, Mitigating Systems Screening Questions, the inspectors determined that the finding was not a design or qualification deficiency but represented a loss of train function for greater than the outage time allowed by Technical Specifications. Therefore, a Region IV senior reactor analyst performed a detailed risk evaluation in accordance with Manual Chapter 0609, Appendix A, Section 6.0, Detailed Risk Evaluation. The analyst determined that the condition of valve HCV-2987 inoperability would affect only the plants response to a large-break loss-of-coolant accident followed by the failure of the instrument air system. The analyst calculated the initiating-event frequency to be 2.63 x 10-10 /year. Also, the analyst determined that the finding did not affect external initiator risk and would not involve a significant increase in the risk of a large, early release of radiation. Therefore, this violation has very low (Green) safety significance. |
| Site: | Fort Calhoun |
|---|---|
| Report | IR 05000285/2016007 Section 4OA7 |
| Date counted | Mar 31, 2016 (2016Q1) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | Licensee-identified |
| Inspection Procedure: | |
| Inspectors (proximate) | A Allen B Baca B Hagar D Dodson J Sowa |
| Violation of: | Technical Specification - Procedures Technical Specification |
| INPO aspect | |
| ' | |