Finding | |
---|---|
Title | Failure to Update the Final Safety Analysis Report Update with Current Plant Design Criteria |
Description | The inspectors identified a noncited violation of 10 CFR Part 50.71 after Pacific Gas and Electric failed to update the Final Safety Analysis Report Update with current plant design criteria. The Final Safety Analysis Report Update stated that Diablo Canyon was designed to comply with the Atomic Energy Commission General Design Criteria for Nuclear Power Plant Construction Permits, published in July 1967. The inspectors identified that the Diablo Canyon Safety Evaluation Report stated that the NRC used General Design Criteria published in July 1971 to review the plant design. In addition, during the initial licensing process, the licensee stated that the plant was evaluated against the 1971 design criteria during the licensing process. The inspectors evaluated this finding using the traditional enforcement process because the failure to update the Final Safety Analysis Report affected the NRCs ability to perform its regulatory function. The inspectors concluded that the failure to update the Final Safety Analysis Report was a Severity Level IV violation based on the General Statement of Policy and Procedure for NRC Enforcement Actions, Supplement I Reactor Operations, dated January 14, 2005, because the erroneous information was not used to make an unacceptable change to the facility or procedures. The inspectors concluded that this finding had a crosscutting aspect in the area of problem identification and resolution associated with the corrective action program component because the licensee did not take appropriate corrective actions to address safety issues and adverse trends in a timely manner P.1(d)(Section 40A2 |
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2009003 Section 4OA2 |
Date counted | Jun 30, 2009 (2009Q2) |
Type: | TEV: Severity level IV |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | D Overland G Kuzo J Laughlin J O'Donnell L Carlson L Micewski L Ricketson M Brooks M Peck N O'Keefeg Guerram Brown M Peck V Gaddy |
CCA | P.3, Resolution |
INPO aspect | PI.3 |
' | |