Finding | |
---|---|
Title | Inadequate Design Control for the Emergency Diesel Generator |
Description | The inspectors identified a noncited violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, after Pacific Gas and Electric failed to provide adequate design control measures for verifying the emergency diesel generators meet the design basis. The inspectors requested to review the design control measures that Pacific Gas and Electric maintained to demonstrate compliance with General Design Criteria 17, Electric Power Systems, design basis. The licensee was not able to retrieve the requested design control measures for the onsite electrical power systems. The licensee provided unit specific diesel loading calculations. The inspectors identified that the licensee failed to include all design basis accidents, a single limiting failure, consider bus frequency and voltage fluctuations, motor starting currents, or manually initiated loads in the calculation. In response to the inspectors observations, the licensee performed an operability evaluation. The inspectors reviewed the evaluation and concluded that the emergency diesel generators remained operable and capable of performing their intended safety function. The licensee has entered this issue into the corrective action program as Notification 50163396. This finding is greater than minor because the design control attribute of the Mitigating Systems Cornerstone and the cornerstones objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences are affected. The inspectors used Inspection Manual Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection Findings for At-Power Situations, to analyze the significance of this finding. The inspectors concluded the finding is of very low safety significance because the condition was a design or qualification deficiency confirmed not to result in loss of operability or functionality. The inspectors did not assign a crosscutting aspect because the finding represented a latent design issue. Pacific Gas and Electric revised the calculations in September 2006 and did not have a recent opportunity to identify this issue. (Section 4OA5 |
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2008005 Section 4OA5 |
Date counted | Dec 31, 2008 (2008Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | |
Inspectors (proximate) | L Ricketson G Guerra M Brown M Peck P Elkmann V Gaddy M Runyan R Kellar A Fairbanks |
INPO aspect | |
' | |