05000271/FIN-2011002-04
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | None |
| Description | Technical Specification 3.6.0, Safety and Relief Valves, requires the reactor to be shut. down and pressure brought below 150 psig within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with two (2) or more SRVs inoperable. Contrary to the above, Entergy determined that two (2) of the four (4) SRVs were inoperable for a period of time greater than allowed by Technical Specifications. This determination was based on pneumatic actuator thread seal leakage that was identified during testing of the pneumatic SRV actuators in the 2010 refueling outage. Entergy determined the leakage was in excess of design requirements, thereby rendering the SRV manual depressurization function inoperable. This condition has been entered in the licensee\'s corrective action program (CR-VTY-2010-2187) and corrective actions have been developed. The inspectors determined that this finding was more than minor because it adversely affected the Mitigation Systems cornerstone objective of ensuring the reliability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined that the function for core decay heat removal was affected, since the ability to manually discharge steam from core decay heat to the suppression pool was degraded by the thread seal leakage. The inspectors determined that this finding is not greater than Green, because subsequent laboratory analysis and engineering evaluation documented in Entergy Operability Recommendation VTY 2011-0631 concluded that sufficient margin was available in the safety-class backup supply to the pneumatic actuation system. The inspectors reviewed Entergy\'s laboratory results and Operability Recommendation, and concluded that the SRV manual depressurization function would have been met under the worst case leakage for all design basis condition |
| Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
|---|---|
| Report | IR 05000271/2011002 Section 4OA7 |
| Date counted | Mar 31, 2011 (2011Q1) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | Licensee-identified |
| Inspection Procedure: | |
| Inspectors (proximate) | D Jackson D Spindler S Rich |
| INPO aspect | |
| ' | |
Finding - Vermont Yankee - IR 05000271/2011002 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Vermont Yankee) @ 2011Q1
Self-Identified List (Vermont Yankee)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||