05000263/LER-2013-007, Regarding Unanalyzed Condition Due to Inadequate Flooding Procedures

From kanterella
Jump to navigation Jump to search
Regarding Unanalyzed Condition Due to Inadequate Flooding Procedures
ML13302C070
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 10/28/2013
From: Fili K
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-13-106 LER 2013-007-00
Download: ML13302C070 (5)


LER-2013-007, Regarding Unanalyzed Condition Due to Inadequate Flooding Procedures
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition

10 CFR 50.73(a)(2)(viii)(B)

10 CFR 50.73(a)(2)(iii)

10 CFR 50.73(a)(2)(ix)(A)

10 CFR 50.73(a)(2)(iv)(A), System Actuation

10 CFR 50.73(a)(2)(x)

10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat

10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown

10 CFR 50.73(a)(2)(v), Loss of Safety Function

10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor
LER closed by
IR 05000263/2016004 (13 February 2017)
2632013007R00 - NRC Website

text

&XcelEnergy Monticello Nuclear Generating Plant 2807 W County Road 75 Monticello, MN 55362 October 28, 2013 L-MT-13-106 10 CFR 50.73 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License No. DPR-22 LER 2013-007 "Unanalyzed Condition Due to Inadequate Flooding Procedures" A Licensee Event Report (LER) for this occurrence is attached.

Summary of Commitments This letter contains no new commitments and no revisions to existing commitments.

Karen D. Fill Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company-Minnesota Enclosure cc:

Regional Administrator, Region III, USNRC Project Manager, Monticello Nuclear Generating Plant, USNRC Resident Inspector, Monticello Nuclear Generating Plant, USNRC

NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES 10/3112013 (10-2010)

, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

3. PAGE Monticello Nuclear Generating Plant 05000 - 263 1 OF 4
4. TITLE Unanalyzed Condition Due to Inadequate Flooding Procedures
5. EVENT DATE
6. LER NUMBER
7. REPORT DATE
8. OTHER FACILITIES INVOLVED I

FACILITY NAME DOCKET NUMBER MONTH DAY YEAR YEAR SNEUMBER NO MONTH DAY YEAR 05000 FACILITY NAME DOCKET NUMBER 08 29 12013 2013 - 007 - 00 10 28 2013 05000

9. OPERATING MODE
- 11.

THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply)

Ul 20.2201(b)

EU 20.2203(a)(3)(i)

[- 50.73(a)(2)(i)(C) 0 50.73(a)(2)(vii) 1 20.2201(d)

EU 20.2203(a)(3)(ii)

EU 50.73(a)(2)(ii)(A)

EU 50.73(a)(2)(viii)(A)

U 20.2203(a)(1)

EU 20.2203(a)(4) 2 50.73(a)(2)(ii)(B)

El 50.73(a)(2)(viii)(B)

__ 20.2203(a)(2)(i)

EU 50.36(c)(1)(i)(A)

EU 50.73(a)(2)(iii) 0 50.73(a)(2)(ix)(A)

10. POWER LEVEL El 20.2203(a)(2)(ii)

[] 50.36(c)(1)(ii)(A)

U 50.73(a)(2)(iv)(A)

E] 50.73(a)(2)(x)

EU 20.2203(a)(2)(iii)

[U 50.36(c)(2)

[

50,73(a)(2)(v)(A)

U 73.71(a)(4) 100%

[1 20.2203(a)(2)(iv)

EU 50.46(a)(3)(ii)

E 50.73(a)(2)(v)(B)

U 73.71(a)(5)

Ul 20.2203(a)(2)(v)

EU 50.73(a)(2)(i)(A)

E 50.73(a)(2)(v)(C)

U OTHER Specify in Abstract below or in E_ 20.2203(a)(2)(vi) 0 50.73(a)(2)(i)(B) 0 50.73(a)(2)(v)(D)

EVENT DESCRIPTION

Prior to discovery of the condition Monticello Nuclear Generating Plant (MNGP) was in Mode 1 at 98% power.

On August 28, 2013, Northern States Power Minnesota (NSPM) was notified of the NRC's final significance determination for a finding involving the failure to maintain a procedure addressing all of the effects of an external flooding scenario. Specifically, NSPM failed to maintain flood Procedure A.6, "Acts of Nature," for MNGP such that it could support the timely implementation of flood protection activities within the 12-day timeframe credited in the design basis as stated in the Updated Safety Analysis Report (USAR).

Licensee Event Report (LER) 2013-003-01, "Inadequate External Flooding Procedure," provides an analysis of the issues related to the flooding deficiencies previously reported to the NRC.

This LER (2013-007) is focused on the issues, causes and corrective actions related to the preliminary NRC finding issued on June 11, 2013, and as finalized on August 28, 2013. The NRC identified a Yellow finding with substantial safety significance and associated apparent violation of Technical Specification 5.4.1 for the licensee's failure to maintain a flood plan to protect the MNGP from external flooding events (a probable maximum flood (PMF)).

NSPM did not maintain an adequate flood plan consistent with the USAR because the necessary flood mitigation actions could not be completed in the time required. The resultant flood waters could negatively impact much of the station's accident mitigation equipment.

The finding is not a current safety concern. On February 15, 2013, actions were completed to reduce the flood mitigation plan timeline to less than 12 days by developing an alternate plan for flood protection features, pre-staging equipment and materials, improving the quality of the A.6 procedure, and preplanning work orders necessary to carry out Procedure A.6 actions. This is no longer considered an unanalyzed condition.

EVENT ANALYSIS

This event is reportable in accordance with 10 CFR 50.73(a)(2)(ii)(B) as an unanalyzed condition that significantly degraded plant safety. This event is also reportable in accordance with 10 CFR 50.73(a)(2)(i)(B)

(multiple safety systems potentially unable to respond to a PMF event) as a condition prohibited by the plant's Technical Specifications.

Finally, this event is also reportable in accordance with 10 CFR 50.73(a)(2)(v)(A), (B), (C) and (D), 10 CFR 50.73(a)(2)(vii) (for at least one train in multiple systems) and 10 CFR 50.73(a)(2)(ix)(A) (for two or more trains in different systems) as an event or condition that as a result of a single cause could have prevented the fulfillment of the safety function of structures or systems that are needed to:

  • Shut down the reactor and maintain it in a safe shutdown condition; Remove residual heat; Control the release of radioactive material; or Mitigate the consequences of an accident.

SAFETY SIGNIFICANCE

MNGP is required to be protected from flooding as described in the licensing basis. The procedural inadequacies affected the ability to protect the site during a PMF event. Since there has been no external flood approaching the PMF elevation, there were no adverse consequences to the health and safety of the public or the plant and its personnel as a result of the identified deficiencies. The root cause investigation did not identify any additional risks to the health and safety of the public resulting from this event.

CAUSE

After receipt of the finding, NSPM performed a RCE and identified the following root cause:

Management did not ensure proper validation of the external flooding mitigation strategy design bases commensurate with safety significance which led to non-conservative decisions.

The contributing causes were that management:

Had not provided the adequate guidance for appropriate screening of modifications and procedure revisions related to infrequent activities planned or anticipated.

Had not ensured self-and independent assessments of station's external flood mitigation activities to assess performance and to identify areas of improvement.

Had not reinforced Corrective Action Program behaviors required for a low threshold for identifying issues related to external flood mitigation.

Did not consistently consider valid technical input from individuals.

CORRECTIVE ACTION

Corrective Actions to Prevent Recurrence (CAPRs) identified in the RCE include the following to correct the identified root cause:

Revise the Leadership Training Program Description to include delivery of a case study for the continual reinforcement of behaviors and attributes associated with ensuring proper validation of MNGP design bases.

" Create a formal engineering program to manage MNGP External Flood Mitigation to ensure proper validation of the external flooding strategy design bases.

Clarify in appropriate station documents, including, but not limited to, the USAR, external flooding section of procedure A.6, and Design Bases Document for External Flooding, that the PMF antecedent conditions are required to be assumed present and that actions to mitigate a PMF must be preplanned.

Revise procedure A.6, Section 5.0 to be an 8000 Series Special procedure. Control as an Infrequently Performed Test or Evolution (IPTE).

Other corrective actions are identified in the RCE to address contributing causes, the extent of condition and the extent of cause. Effectiveness reviews have been established to ensure adequate review of the results of

the corrective actions are achieved.

PREVIOUS SIMILAR EVENTS

On November 26, 1990, the site identified, in a LER, that there were procedural inadequacies with the external flooding procedure related to protective measures for the Emergency Diesel Generator Fuel Oil Transfer House. The LER was supplemented April 24, 1991 with additional detail, including the cause of the event, which was procedural inadequacy.

On September 30, 2013, the site identified in a LER, that there were inadequacies in the Procedure A.6, "Acts of Nature," to protect the site from a Probable Maximum Flood (PMF). The root cause for this event was determined to be: Station personnel incorrectly understood the 1980 NRC Safety Evaluation Report licensing basis to allow time for preparation of a detailed flood plan based on the presence of identifiable preconditions required for a Probable Maximum Flood (PMF) as stated in USAR, Appendix G. This misunderstanding was institutionalized through inclusion of this position in station documentation.