Finding | |
|---|---|
| Title | |
| Description | The inspectors identified an NCV of 10 CFR 50, Appendix B, Criterion V, when IPEC staff failed to follow fuel handling procedures which ensure that the correct spent fuel pool configuration is used in the development of the core offload plan, ensure that a cell location is visually verified as empty prior to loading, and ensure an evaluation is performed for any situation that results in a large or unexplained change in spent fuel handling machine (SFHM) load which resulted in two fuel assembly interference events in the Unit 2 spent fuel pool. This issue was entered into the licensees corrective action program (CAP) as CRIP2- 2014-1462.This finding is more than minor as it represented a challenge to the human performance attribute of the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding) protect the public from radionuclide releases caused by accidents or events. In accordance with IMC 0609, Significance Determination Process (SDP), Appendix A, The Significance Determination Process for Findings At-Power, Barrier Integrity Screening Questions, Section D, Spent Fuel Pool, the finding screened to be of very low safety significance (Green) when all screening questions were answered no. The event did not result in adverse impact to the decay heat removal capabilities of the spent fuel pool; the event did not result in detectible release of radionuclides; and the event did not result in the loss of spent fuel pool water inventory. The inspectors assigned a cross-cutting aspect in the Human Performance, Avoid Complacency, when the licensee staff failed to recognize and plan for the possibility of mistakes and failed to implement appropriate error reduction tools. |
| Site: | Indian Point |
|---|---|
| Report | IR 05000247/2014002 Section 1R20 |
| Date counted | Mar 31, 2014 (2014Q1) |
| Type: | NCV: Green |
| cornerstone | Barrier Integrity |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.2 |
| Inspectors (proximate) | A Burritt A Patel E Burket E Gray G Newman J Furia J Stewart S Chaudhary S Pindale T. Lamb |
| Violation of: | 10 CFR 50 Appendix B Criterion V |
| CCA | H.12, Avoid Complacency |
| INPO aspect | QA.4 |
| ' | |