05000220/FIN-2018001-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Potential Failure to Submit an 8-Hour Event Notification for a Valid Actuation of HPC |
Description | On March 18, 2018,at 1:18 a.m., during the Unit 1maintenance outage while the unit was in cold shutdown, operators received multiple low level alarms on the GEMAC 11 and 12 level indications. Operators responded by adjusting reactor water cleanup reject flow and the feedwater minimum flow control valve to raise reactor water level. Upon the operators making the adjustment to reactor water level, the feedwater low flow control valve was slow to respond, but eventually opened more rapidly, and the increased flow from feedwater resulted in a rapid rise in reactor water level. At 1:28 a.m., indicated reactor water level rose to the 95-inch trip setpoint for the 11 and 12 Yarway level indication instruments, resulting in a turbine trip and HPCI initiation signal. The HPCI pumps were tagged out and thus did not inject, and the turbine was offline for the shutdown. The 11 and 12 Yarway level indication instruments provide reactor protection system logic inputs for reactor vessel water level; however, the Yarway level indication instruments are not density compensated. Therefore, under cold shutdown conditions, actual reactor vessel water level was lower than indicated water level on the 11 and 12 Yarways. During cold shutdown conditions, the GEMAC level instruments, which are calibrated to cold shutdown conditions, provide an accurate indication of actual reactor vessel water level. The GEMAC instruments both indicated well below the trip setpoint of 95 inches (indicated ~72 inches) when the turbine trip and HPCI initiation signal were received. Exelon determined that this event was not reportable under 10 CFR 50.72.Title 10 CFR 50.72(b)(3)(iv)(A) states, Any event or condition that results in valid actuation of any of the systems listed in paragraph (b)(3)(iv)(B) of this section, except when the actuation results from and is part of a pre-planned sequence during testing or reactor operation. (B) The systems to which the requirements of paragraph (b)(3)(iv)(A) of this section apply are: 10 (5) BWR reactor core isolation cooling system; isolation condenser system; and feedwater coolant injection system. Planned Closure Action(s): The inspectors requested the 10 CFR 50.72 subject matter experts at the Office of Nuclear Reactor Regulation (NRR) and Office of General Council (OGC) to review whether this was a valid actuation and thus reportable. The inspectors are opening an unresolved item (URI) to determine if a performance deficiency exists.Licensee Action(s): Licensee entered the concern into their corrective action program, and communicated with NRC Region I and NRR Staff. Exelons position is that the event was not reportable. Corrective Action Reference:IR 04116336 NRC Tracking Number: 05000220/2018001-01 |
Site: | Nine Mile Point |
---|---|
Report | IR 05000220/2018001 Section 1R20 |
Date counted | Mar 31, 2018 (2018Q1) |
Type: | URI: |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.2 |
Inspectors (proximate) | E Miller B Sienel G Stock R Rolph M Catts |
INPO aspect | |
' | |
Finding - Nine Mile Point - IR 05000220/2018001 | |||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Nine Mile Point) @ 2018Q1
Self-Identified List (Nine Mile Point)
| |||||||||||||||||||||||||||||||||||