U-604788, Fourth Ten-Year Interval Inservice Testing Program Plan Revision 3 | 12 December 2023 | Fourth Ten-Year Interval Inservice Testing Program Plan Revision 3 |
ML23114A252 | 28 April 2023 | Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI |
RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | 30 November 2022 | Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI |
ML22094A001 | 15 April 2022 | Constellation Energy Generation, LLC - Proposed Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles (Epids L-2021-LLR-0057 and L-2021-LLR-0058) |
U-604703, Fourth Ten-Year Interval Inservice Testing Program Plan Revision 2 | 14 April 2022 | Fourth Ten-Year Interval Inservice Testing Program Plan Revision 2 |
ML22111A190 | 31 March 2022 | Submittal of Revision 22 to Updated Safety Analysis Report, Letter and Attachments A-F |
ML22111A192 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 1, Introduction and General Description of Plant |
ML22111A207 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 9, Auxiliary Systems |
ML22111A211 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 13, Conduct of Operations |
ML22111A215 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 17, Quality Assurance |
ML22047A127 | 22 February 2022 | Relief from the Requirements of the American Society of Mechanical Engineers Code |
ML21333A153 | 30 November 2021 | Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval |
ML21280A078 | 27 October 2021 | Proposed Alternative to Use of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-893 (Epids L-2020-LLR-0147 and L-2020-LLR-0148) |
ML21230A206 | 3 September 2021 | Proposed Alternative to Use ASME OM Code Case OMN-28 |
ML21216A220 | 5 August 2021 | Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting |
NMP1L3420, Proposed Alternative to Implement Code Case OMN-28 | 5 August 2021 | Proposed Alternative to Implement Code Case OMN-28 |
ML21166A168 | 25 June 2021 | |
ML21139A185 | 22 June 2021 | Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting |
U-604633, Fourth Ten-Year Interval Inservice Testing Program Plan Revision 1 | 23 May 2021 | Fourth Ten-Year Interval Inservice Testing Program Plan Revision 1 |
ML21117A044 | 26 April 2021 | NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting |
ML21077A177 | 8 April 2021 | Withdrawal of Requested Exemption from Certain Requirement in 10 CFR 50.55a (Epids L-2021-LLE-0014, 0015, & 0016) |
JAFP-21-0014, Exemption Request to Extend the 10-Year ASME Code Updates for the Inservice Inspection, Containment Inservice Inspection, and Inservice Testing Programs | 3 March 2021 | Exemption Request to Extend the 10-Year ASME Code Updates for the Inservice Inspection, Containment Inservice Inspection, and Inservice Testing Programs |
ML21062A065 | 1 March 2021 | NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting |
ML21028A673 | 3 February 2021 | Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011 |
ML21005A061 | 14 January 2021 | Proposed Alternatives to Extend the Safety Relief Valve Testing Interval (EPID L-2020-LLR-0014 Through L-2020-LLR-0018) |
ML20351A283 | 18 December 2020 | Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs |
ML20323A033 | 1 December 2020 | Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs |
ML20269A200 | 30 September 2020 | Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 |
ML20261G732 | 16 September 2020 | Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a |
RS-20-110, Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | 2 September 2020 | Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI |
RS-20-111, Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | 2 September 2020 | Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI |
ML20218A660 | 2 September 2020 | Proposed Alternative I4R-01 to the Requirements of the ASME Code |
ML20232A171 | 1 September 2020 | Request to Use Alternative Code Case OMN-26 |
ML20232A188 | 1 September 2020 | Proposed Alternative I4R-02 to the Requirements of the ASME Code |
U-604555, Fourth Ten-Year Interval Inservice Testing Program Plan Revision 0 | 13 July 2020 | Fourth Ten-Year Interval Inservice Testing Program Plan Revision 0 |
ML20188A264 | 6 July 2020 | Clinton Power Station, R.E. Ginna Station, Limerick Station, Nine Mile Point Station & Peach Bottom Station - Proposed Alternative to Utilize Code Case OMN-26 - Response to Request for Additional Information |
ML20163A717 | 26 June 2020 | Proposed Alternative to the Requirements of the ASME Code |
ML20153A704 | 1 June 2020 | NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 |
RS-20-053, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors | 30 April 2020 | Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors |
ML20099D955 | 17 April 2020 | Request to Use Provisions in the 2013 Edition of the ASME Boiler and Pressure Vessel Code for Performing Non-Destructive Examinations |
ML20105A264 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 13, Conduct of Operations |
ML20105A245 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 1, Introduction and General Description of Plant |
ML20105A260 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 9, Auxiliary Systems |
ML20105A268 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 17, Quality Assurance |
ML20105A243 | 31 March 2020 | 1 to Updated Safety Analysis Report |
RS-20-042, Withdrawal of Proposed Relief Request I4-RS-1 to Use Code Case OMN-13 | 26 March 2020 | Withdrawal of Proposed Relief Request I4-RS-1 to Use Code Case OMN-13 |
ML20028E399 | 4 February 2020 | Proposed Alternative to Use ASME Code Case N-879 |
ML20010E870 | 27 January 2020 | Proposed Alternative to the Requirements of the ASME Code |
ML19269C534 | 27 September 2019 | Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques |
ML19192A244 | 18 July 2019 | Proposed Alternative to Use ASME Code Cases N-878 and N-880 |