64,NehN~~port, I 4816 May 07, 2013 NRC-13-0027 Regional Administrator Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352

References:

1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
2) NRC Letter, "Assessment Follow-Up Letter For Fermi Power Plant, Unit 2," dated February 8, 2013

Subject:

Supplemental Inspection Readiness In Reference 2 the NRC informed Fermi 2 that the NRC will conduct a supplemental inspection using Inspection Procedure 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area" as a result of exceeding the Green-to-White performance indicator threshold for the "Unplanned Scrams per 7000 Critical Hours."

The purpose of this letter is to inform the NRC of Fermi 2's readiness for the NRC to conduct the subject inspection. Based on discussions with the NRC staff, Fermi 2 anticipates this inspection to begin on or about June 10 it, 2013.

No new commitments are being made in this submittal.

Should you have any questions or require additional information, please contact me at (734) 586-5076.

Sincerely, Zackary W. Rad Manager, Nuclear Licensing

USNRC NRC-13-0027 Page 2 cc: NRC Project Manager NRC Resident Office Reactor Projects Chief, Branch 5, Region III Regional Administrator, Region III Supervisor, Electric Operators, Michigan Public Service Commission