ML17328A365

From kanterella
Jump to navigation Jump to search
Workshop on Sharing Operating Experience from Rigging, Lifting and Load Handling Events - Temporary Overhead Crane Failure at Arkansas Nuclear One Presented to IAEA
ML17328A365
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 11/30/2017
From: Geoffrey Miller
NRC/RGN-IV/DRP/RPB-D
To:
Miller G
References
48869, ML13158A242, ML14083A409
Download: ML17328A365 (23)


Text

Temporary Overhead Crane Failure at Arkansas Nuclear One Workshop on Sharing Operating Experience from Rigging, Lifting and Load Handling Events IAEA Headquarters 27-30 November 2017 ADAMS Accession Number ML17328A365 1

Outline

  • Overview of site and planned lift
  • Discussion of the event
  • Response actions
  • Lessons learned (some confirmed)
  • Recovery
  • References 2

Overview Arkansas Nuclear One Russellville, Arkansas 3

Unit 1 Stator Replacement Computer Modelling Lift Move Stator weight ~525 tons Travel path ~90 ft (27 m) horizontal

(~477,000 kg) ~29 ft (9 m) vertical 4

Unit 1 Stator Replacement Animation of Planned Lift Train Bay Tripods H-frame U1 Stator 5

Event Summary Sunday, March 31 0639: Lift begins 0750: Crane fails, immediate loss of offsite power to Unit 1 (switchgear damaged), Unit 2 reactor coolant pump trip (vibration-induced) and reactor trip, fire piping ruptured 0923: Breaker failure from water leakage causes Unit 2 partial loss of offsite power and loss of instrument air to both units 1033: Notification of Unusual Event Declared Saturday, April 6 Offsite power restored to Unit 1 using temporary modifications 6

7 8

NRC Response

  • Senior Resident Inspector immediately responded to control room on site
  • Emergency response mode decision
  • Coordination with OSHA
  • Performed risk evaluation of event to determine inspection response
  • Augmented Inspection Team (second-highest reactive inspection) commenced April 8
  • Repair/recovery inspections prior to restart 9

Cause Evaluation

  • From NRC Augmented Inspection Team Follow Up Inspection Report:

- The overhead temporary hoisting assembly was not properly designed

- The associated calculation was not reviewed

- The assembly was not load tested 10

Lessons Learned

  • Personnel Safety for Suspended Loads

- Be aware the area of impact could be more than beneath the suspended load from falling hoist/crane members or other damaged equipment

- Installed/available cameras can be used to limit observers in the area 11

12 Lessons Learned contd

  • Collateral Damage Possible from Chain Reaction Events

- Water from ruptured piping

- Power failures

  • Expect Complications to Response and Recovery

- Blocked access routes

- Personnel injuries/fatalities 13

14 15 Lessons Learned contd

  • Full Consideration of Plant Risk

- Watch for complacent attitudes associated with high consequence/low probability events

  • Control of Vendors and Contractors

- In U.S., the licensee retains ultimate responsibility

- Additional contractor organizations may be needed for technical review

    • For inspectors: know how the licensee verifies compliance 16

17 Lessons Learned contd

  • Inspector Response to Significant Events Involving Fatalities/Injuries

- Maintain awareness of operator mindset

  • Significant emotional event
  • Licensee management actions to ensure operators remain focused on tasks

- Be familiar with alternate access routes within the plant

- Coordination with other government agencies 18

Lessons Learned contd

  • Maintain Open and Frequent Internal and External Communications

- Coordinate with public affairs representatives and other local/federal government agencies

- Social media a significant and increasing factor: help public affairs representatives stay in front 19

Damaged Stator Removal 20

Turbine Deck Repair 21

Load Test of Replacement Crane 22

References

  • NRC Event Number 48869; Notification of Unusual Event Declared Due to a Breaker Explosion in the Protected Area
  • Information available on the NRC website www.nrc.gov
  • Investigation of the March 31, 2013 Temporary Overhead Crane Collapse At Arkansas Nuclear One Power Plant In London/Russellville, AR - OSHA (www.osha.gov/doc/engineering/pdf/2013_r_04.pdf) 23