MONTHYEARML24299A2222024-10-31031 October 2024 Audit Summary for License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components ML24292A1602024-10-22022 October 2024 Request for Withholding Information from Public Disclosure License Amendment Request to Revise Technical Specification Surveillance Requirements to Increase Safety/Relief Valve Setpoints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary ML24303A4102024-10-17017 October 2024 Dir Results Letter to NRC - Hatch - Hurricane Helene IR 05000321/20244012024-10-10010 October 2024 Security Baseline Inspection Report 05000321-2024401 and 05000366-2024401 ML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 05000321/LER-2024-003, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link 05000321/LER-2024-002-01, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 05000321/LER-2024-002, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 05000366/LER-2024-002, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint 05000321/LER-2024-001, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 September 2, 2008 Mr. Dennis R. Madison Vice President Southern Nuclear Operating Company, Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - EDWIN I. HATCH NUCLEAR PLANT
Dear Mr. Madison:
On August 12, 2008, the NRC staff completed its performance review of Edwin I. Hatch Nuclear Plant for the first half of the 2008 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the Physical Protection/Security cornerstone performance review and resultant inspection plan.
Plant performance for the most recent quarter at Hatch Unit 1 was within the Licensee Response column of the NRC
=s Action Matrix based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at Unit 1.
Plant performance for the most recent quarter at Hatch Unit 2 was within the Regulatory Response column of the NRC
=s Action Matrix based on a Mitigating System Performance Index (MSPI) - High Pressure Injection Systems PI which crossed the threshold from Green to White in the second quarter of 2007. The NRC completed a supplemental inspection in accordance with Inspection Procedure 95001, "Inspection for One or Two White Inputs in a Strategic Performance Area", on March 6, 2008. Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at Unit 2. We also plan on conducting several non-ROP inspections SNC, Inc. 2 including emergency diesel generator technical specification surveillance requirements (Temporary Instruction (TI) 2515/176), site specific implementation of B.5.b phase 2 and 3 mitigation strategies (TI 2515/171), and Emergency Plan PI assessment.
In addition, TI 2515/173, Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative, will be performed at your facility prior to August 30, 2010. In the near term, we will contact you to assess your readiness for this inspection and then finalize our schedule accordingly.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC
=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Scott Shaffer at (404) 562-4521 with any questions you may have regarding this letter or the inspection plan.
Sincerely, /RA/
Leonard D. Wert, Jr., Director Division of Reactor Projects Docket No.: 50-321, 50-366 License No.: DPR-57, NPF-5
Enclosure:
Edwin I. Hatch Nuclear Plant Inspection/Activity Plan cc w/encl: (See page 3)
_________________________ X SUNSI REVIEW COMPLETE /SMS/ OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE SMS /RA for/ SMS /RA/ NAME TLighty SShaeffer JMoorman LWert DATE 08/29/2008 08/29/2008 09/02/2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO SNC, Inc. 3 cc w/encl: Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
Raymond D. Baker Licensing Manager Licensing-Hatch Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
David H. Jones Vice President Engineering Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution
Mr. K. Rosanski Resident Manager Oglethorpe Power Corporation Electronic Mail Distribution
Laurence Bergen Oglethorpe Power Corporation Electronic Mail Distribution
Bob Masse Resident Manager Vogtle Electric Generating Plant Oglethorpe Power Corporation Electronic Mail Distribution Arthur H. Domby, Esq. Troutman Sanders Electronic Mail Distribution
Dr. Carol Couch Director Environmental Protection Department of Natural Resources Electronic Mail Distribution
Cynthia Sanders Program Manager Radioactive Materials Program Department of Natural Resources Electronic Mail Distribution
Jim Sommerville (Acting) Chief Environmental Protection Division Department of Natural Resources Electronic Mail Distribution
Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution
Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution
Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513 SNC, Inc. 4 Letter to Dennis R. Madison from Leonard D. Wert, Jr. dated September 2, 2008
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - EDWIN I. HATCH NUCLEAR PLANT Distribution w/encl:
C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC R. Martin, NRR C. Gratton, NRR Institute of Nuclear Power Operations (INPO)