| Q | CCA | Title |
---|
05000272/FIN-2016404-01 | 2016Q3 | H.1 | Security |
05000311/FIN-2016404-02 | 2016Q3 | H.2 | Security |
05000272/FIN-2016003-01 | 2016Q3 | | Misclassification of and Lack of Preventative Maintenance for SWC Valve 2GW75 and Relay S62-C1 |
05000311/FIN-2017009-01 | 2016Q3 | H.8 | Failure to Follow Troubleshooting Procedure for BIT Relief Valve Leakage |
05000272/FIN-2016004-01 | 2016Q4 | P.5 | Inadequate Maintenance Procedure for Steam Generator Feedwater Pump Coupling Hub Set Screw Installation |
05000311/FIN-2016004-02 | 2016Q4 | P.2 | Inadequate Surveillance Test Procedure Results in Water Hammer and Reactor Trip |
05000272/FIN-2017001-01 | 2017Q1 | H.5 | Loss of Unit 1C 4kV Vital Bus due to Inadequate Activity Risk Screening |
05000272/FIN-2017001-02 | 2017Q1 | H.5 | Inadequate Fire Risk Assessment and Management |