ML18152A078

From kanterella
Revision as of 19:56, 5 January 2025 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Insp Repts 50-280/97-09 & 50-281/97-09 on 970824-1004. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support
ML18152A078
Person / Time
Site: Surry  Dominion icon.png
Issue date: 10/30/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18152A079 List:
References
50-280-97-09, 50-280-97-9, 50-281-97-09, 50-281-97-9, NUDOCS 9711190189
Download: ML18152A078 (32)


See also: IR 05000280/1997009

Text

Docket Nos:

License Nos:

Report Nos:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

.9711190189 971030

PDR

ADOCK 05000280

G

PDR

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

50-280, 50-281

DPR-32. DPR-37

50-280/97-09 and 50-281/97-09

Virginia Electric and Power Company (VEPCO)

Surry Power Station. Units 1 & 2

5850 Hog Island Road

Surry, VA 23883

August 24 - October 4. 1997

R. Musser. Senior Resident Inspector

K. Poertner. Resident Inspector

P. Byron. Resid~nt Inspector

L. Garner. Project Engineer (Section M8.2)

R. Gibbs. Reactor Inspector (Section M8.1)

W. Miller. Reactor Inspector (Sections F2.1. F2.2. and

F8.1)

D. Payne. Reactor Inspector (Section 05.1)

R. Haag, Chief. Reactor Projects Branch 5

Division of Reactor Projects

Enclosure 1

EXECUTIVE SUMMARY

Surry Power Station. Units 1 & 2

NRC Inspection Report Nos. 50-280/97-09.50-281/97-09

This integrated inspection included aspects of licensee operations.

engineering, maintenance. and plant support.

The report covers a 6-week

period of resident inspection: in addition. it includes the results of

announced inspections by four regional inspectors.

Operations

Licensee actions to repair a minor through wall leak on service water

piping were conducted in a conservative manner.

Operations personnel

exhibited a good questioning attitude during identification of the

leaking service water line (Section 01.2).

The inspectors verified that Technical Specification requirements were

satisfied during Unit 1 operation with both Pressurizer Powered Operated

Relief Valves (PORVs) isolated (Section 01.3).

A Non-cited Violation was identified for an inadequate procedure that

resulted in an inadvertent makeup to the spent fuel pool from the Unit 2

refueling water storage tank.

The inspectors concluded that the

corrective actions implemented should prevent recurrence (Section 01.4).

Hydrogen concentration has continued to decrease within the Unit 1

containment following installation of a portable autocatalytic

recombiner.

The portable recombiner appears to be functioning

appropriately to reduce hydrogen concentration (Section 01.5).

For the specific areas inspected. the Surry Operator Requalification

program fully meets the requirements. and intent of 10 CFR 55.59(c).

The inspectors noted much improvement in the operator requalification

program since the last inspection of the program (Section 05.1).

Maintenance

Maintenance performed on the Emergency Service Water Pumps was completed

in a satisfactory manner.

Problems with marine growth on the pumps have

not been adequately resolved.

An inspection followup item is being

opened to track the licensee's resolution of this matter (Section Ml.1).

The licensee has made an effort to determine the cause of No. 1

emergency diesel generator louver controller failures but has not been

successful. Additional effort is required to repair and return the east

bank of louvers to a fully functional condition.

Maintenance personnel

were deliberate and acted in a professional manner during

troubleshooting activities (Section Ml.2).

Reactor Protection System Logic Testing was performed in an excellent

manner (Section Ml.3).

Enclosure 1

2

The licensee's deferral of the A Reactor Coolant Pump seal inspection

during the upcoming Unit 2 outage could result in a mid-cycle

maintenance outage, but does not preclude safe operation of the unit.

Licensee commitments for the Unit 2 outage were reviewed and found to be

within the scope of the outage (Section Ml.4).

The licensee's actions with regard to surveillance. testing and

maintenance of the auxiliary shutdown panels and the remote monitoring

panels were excellent (Section MB.1).

Foreign material exclusion worker qualification training was considered

a strength in that it personalized the negative affects that foreign

material can have on employee safety and dose. as well as. the economic

impact on the company (Section MB.2).

Engineering

operability was thorough and adequately justified system operability.

The decision to defer modification of the Unit 2 expansion joints inside

the containment for approximately two weeks until a scheduled refueling

outage appeared appropriate (Section El.1).

Plant Support

Health physics practices were observed to be proper (Section Rl).

An Emergency Preparedness exercise was conducted August 26.

Regional

personnel and the resident inspectors participated in the exercise

(Section Pl).

Security and material condition of the protected area perimeter barrier

were acceptable (Section Sl).

Two apparent violations were identified for inadequate fire protection

features which failed to meet the requirements of 10 CFR 50 Appendix R.

The control room complex and safety related vital electrical panels were

not fully protected. such that one train of systems necessary to achieve

and maintain hot shutdown condition from either the control room or

emergency control stations would be free of fire damage (Section F2.1).

Two apparent violations were also identified for the failure of the

licensee to report these discrepancies to the NRC and for the failure to

correct these discrepancies in a timely manner (Section F2.1).

Excellent housekeeping was provided for the Radwaste Facility with good

implementation of the station's fire prevention procedures and

maintenance of the fire protection equipment (Section F2.2).

A justification for changes to the Radwaste Facility building structure.

equipment and facility process was not being maintained. This was

identified as an Inspection Followup Item (Section F2.2).

3

The licensee took positive action to enhance the preventive maintenance

being performed on the storage of spare safety related electric motors

and rotating mechanical components (Section FB.1).

A Non-cited Violation was identified concerning the failure to perform

fire watch tours within the specified one hour time frame (Section

FB.2).

Report Details

Summary of Plant Status

Unit 1 operated at power the entire reporting period.

On September 15 a power

reduction was commenced in anticipation of a Technical Specification (TS)

required shutdown due to an inoperable service water flowpath.

The power

reduction was terminated at 99.25 percent power when the TS action statement

was exited and the unit was returned to 100 percent power.

The unit operated

at power for the remainder of the inspection period.

Unit 2 operated at power the entire reporting period.

On September 10 power

was reduced to approximately 81 percent to repair a leak on the A condenser

waterbox outlet piping. The leak was repaired and the unit returned to 100

percent power that same day.

The unit operated at power for the remainder of

the inspection period.

I. Operations

01

Conduct of Operations

01.1 General Comments (71707. 40500)

The inspectors conducted frequent control room tours to verify proper

staffing. operator attentiveness. and adherence to approved procedures.

The inspectors attended daily plant status meetings to maintain

awareness of overall facility operations and reviewed operator logs to

verify operational safety and compliance with TSs.

Instrumentation and

safety system lineups were periodically reviewed from control room

indications to assess operability. Frequent plant tours were conducted

to observe equipment status and housekeeping. Deviation Reports CDRs)

were reviewed to assure that potential safety concerns were properly

reported and resolved.

The inspectors found that daily operations were

generally conducted in accordance with regulatory requirements and plant

procedures.

01.2 Service Water Piping Leak

a.

Inspection Scope (71707)

The inspectors reviewed licensee actions associated with a through wall

piping leak in the service water system.

b.

Observations and Findings

On September 14. at 11:10 a.m .. operations personnel identified a minor

through wall leak on a service water line located in mechanical

equipment room number 3.

The leak developed in a 6 inch to 4 inch

reducer immediately upstream of valve 2-SW-309.

Initial discussions

with engineering personnel indicated that an operability concern did not

exist. however. subsequent review by engineering determined that the

r

C .

2

through wall leak rendered the line inoperable. This determination was

communicated to the operating crew at approximately 6:42 p.m. and a 24

hour TS action statement on both units was entered.

The TS action was

entered at 11:10 a.m .. the time the leak was identified.

TS 3.14 requires two operable service water flow paths to the charging

pump service water subsystem.

With only one operable flow path TS 3.14.d requires that two flowpaths be restored within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the

unit be placed in hot shutdown.

The location of the leak resulted in

only one operable service water flowpath on both units.

The service

water line was isolated and tagged out at 10:50 p.m. for maintenance.

The line was repaired and returned to service at 10:04 a.m. on September

15.

Prior to the return to service of the second service water flowpath

a power reduction was commenced on Unit 1 at 9:36 a.m. in anticipation

of a required dual unit shutdown if maintenance activities were not

successful in returning the flowpath to an operable condition. The Unit

1 power reduction was terminated with the unit at 99.25 percent power

when the service water line was returned to service. The initiation of

a power reduction was determined not to be reportable to the NRC since

the service water flowpath was returned to service prior to the

expiration of the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> action statement.

Conclusions

Licensee actions to repair a minor through wall leak on a service water

flowpath were conducted in a conservative manner.

Operations personnel

exhibited a good questioning attitude during identification of the

leaking service water line.

01.3 Unit 1 Operation With both Pressurizer Power Operated Relief Valves

CPORVs) Isolated

a.

Inspection Scope (71707)

b.

The inspectors reviewed the TS requirements for unit operation with both

pressurizer PORVs isolated.

Observations and Findings

On September 16. at 7:09 p.m .. the block valve associated with PORV 1-

RC-PCV-1455C was closed to isolate the PORV.

The other PORV block valve

had been closed earlier in the cycle due to PORV seat leakage.

Isolating 1455C resulted in both PORVs being isolated. The block valve

was shut to determine the effect on Reactor Coolant System (RCS) leakage

and Primary Relief Tank (PRT) parameters.

TS 3.1.A.6 allows operation

with both PORVs isolated as long as the PORVs can be manually cycled and

power is maintained on the associated block valve.

The 1455C block

valve was reopened at 9:20 p.m. on September 18.

PORV tailpipe

temperatures decreased when the block valve was shut and PRT parameters

stabilized but RCS leakage was *not affected.

The block valve remained

open for the remainder of the reporting period.

3

c. Conclusions

The inspectors verified that TS requirements were satisfied during Unit

1 operation with both pressurizer PORVs isolated.

01.4 Inadvertent Spent Fuel Pool CSFP) Makeup from Unit 2 Refueling Water

Storage Tank (RWST).

C.

a.

Inspection Scope (71707)

The inspectors reviewed the circumstances surrounding an inadvertent

addition to the SFP from the Unit 2 RWST.

b. Observations and Findings

On August 30. while Unit 1 operators were performing procedure 1-0P-FC-

001. "Spent Fuel Pool Makeup," Revision 3. to makeup to the SFP from the

Unit 1 blender. the operating crew determined that Unit 2 RWST level was

slightly decreasing.

Procedure 1-0P-FC-001 was secured and the makeup

to the SFP was terminated after approximately 1000 gallons of water had

been added.

Investigation determined that procedure 2-0P-CS-005.

"Purifying Unit 2 RWST." Revision 3. was in progress on Unit 2 and this

procedure aligned the Unit 2 RWST through the SFP ion exchanger.

When

procedure 1-0P-FC-001 was initiated the operator opened manual valve

1-FC-69 and this resulted in a flowpath from the Unit 2 RWST to the SFP .

The misalignment was recognized and corrected within 10 minutes.

RWST

level and SFP level remained in the normal operating band. Operations

issued a deviation report documenting that the procedures were

inadequate in that they did nqt properly verify system alignment prior

to commencing a makeup from the Unit 1 blender. The Unit 2 RWST

recirculation procedure was revised to require that valve 1-FC-69 be

tagged closed to prevent an inadvertent addition to the SFP from the

Unit 2 RWST.

The inspectors discussed this event with the operating

crew and operations supervision and reviewed the deviation report and

the procedure change initiated to prevent recurrence.

The inspectors

concluded that procedure 1-0P-FC-001 was inadequate in that it did not

verify proper system alignment prior to initiating a makeup to the SFP

and that the corrective actions implemented should prevent another

inadvertent addition to the SFP from the Unit 2 RWST.

This non-

repetitive. licensee-identified and corrected violation is being treated*

as a Non-cited Violation (NCV) consistent with Section VII.B.1 of the

NRC Enforcement Policy. This matter is identified as NCV 280.

281/97009-01.

Conclusions

A NCV was identified for an inadequate procedure that resulted in an

inadvertent makeup to the SFP from the Unit 2 RWST.

The inspectors

concluded that the corrective actions implemented should prevent

recurrence.

I'

4

01.5 Unit 1 Containment Hydrogen Concentration

  • 05

a.

Inspection Scope (71707)

The inspectors continued to review the licensee's actions related to

detectable hydrogen concentration within the Unit 1 containment.

b.

Observations and Findings

C.

As reported in NRC Inspection Report 280, 281/97-07. the licensee

installed a Portable Autocatalytic Recombiner (PAR) in the Unit 1

containment on August 22. 1997. to remove hydrogen from the containment

atmosphere.

At that time. containment hydrogen concentration was

approximately 0.5 percent. Subsequent to the installation of the PAR.

the inspectors have been monitoring containment hydrogen concentration

and have noted a downward trend.

At the end of the reporting period.

Unit 1 hydrogen concentration was approximately 0.3 percent indicating

that the PAR is performing as expected.

The licensee is continuing to

perform bi-weekly samples of the containment to monitor hydrogen

concentration changes.

Conclusion

Hydrogen concentration has continued to decrease within the Unit 1

containment.

The PAR appears to be functioning appropriately to reduce

hydrogen concentration.

Operator Training and Qualification

05.1 Licensed Operator Requalification Program (71001)

a.

Inspection Scope

During the period September 22-25. 1997. the inspectors reviewed the

licensee's licensed operator requalification program. Specific areas of

review included observation of simulator and plant walkthrough tests.

program implementation procedures. and management involvement in the

program.

b.

Observations and Findings

The inspectors observed three teams of operators from Crew B shift.

This crew was comprised of five Senior Reactor Operators (SROs). six

Reactor Operators (ROs). and two Shift Technical Advisors (STAs).

Each

operator was administered two simulator scenarios and five Job

Performance Measures (JPMs).

The inspectors noted that operator performance was' generally good.

Several operators had performance weaknesses which were identified and

documented by the training department evaluators. Additionally, the

scenarios appeared to be quite good.

They were challenging and

operationally oriented.

Each explored various aspects of the abnormal

5

and emergency procedures as well as TS actions. The JPMs were good as

well.

The inspectors observed that many enhancements had been made in

response to findings of the previous requalification inspection.

The inspectors noted that the licensee's evaluators did an excellent

job, particularly during the simulator evaluations. They were objective

and thorough in identifying and documenting operator strengths and

weaknesses.

These were discussed among all team members immediately

following each scenario to ensure no problems were overlooked and to

ensure they were properly characterized., The evaluation team included

an Operations Department representative. Usually this representative

was the Operations Superintendent.

The inspectors reviewed the licensee's documentation of operator

performance for this crew and that for Crew E.

The inspectors found

that remedial training was identified and conducted when needed.

Operators with minor deficiencies were trained and re-tested before

returning to shift. While remediation appears to be primarily self-

study, some instructor interface was required.

Documentation and follow

through in this area was very good. but the actual retraining identified

in the remedial packages lacked depth.

The inspectors found evidence of strong and continual management

involvement in the requalification training program (as well as other

non-licensed training programs). A file of management observations.

forms for the last two years was reviewed.

The inspectors. found that

the management observer often provided meaningful feedback and

beneficial ideas. The inspectors found several completed observation

forms by the Plant Manager.

Each form had been properly dispositioned.

with corrective action identified where necessary.

c. Conclusions

The inspectors noted much improvement from the last inspection.

It was

evident that the nuclear training department had worked on those areas

where improvement could be made and the positive change in performance

was observable.

The inspectors concluded that the Surry Operator

Requalification training program was in very good condition.

For the

specific areas inspected. the Surry Operator Requalification program

fully meets the requirements and intent of 10 CFR 55.59(c).

08

Miscellaneous Operations Issues (92901)

08.1

(Closed) Violation CVIO) 50~280/96005-01. 50-281/96005-01: inadequate

system isolation.

On May 18. 1996. the control room operator received

ventilation system Vent-Vent ALERT alarms on both the Victoreen (RI-VG-

110) and Kaman (RI-VG-131-1) radiation monitors.

The operator observed

that the overhead gas pressure had decreased by approximately two psi.

The operator isolated the Primary Drains Transfer Tank (POTT) from the

overhead gas header and terminated the release to the Unit 2

containment.

The operators determined that the release path had been

through POTT Cooler Inlet Header Relief Valve. 2-DG-RV-202. which had

I'

6

been removed to perform set point testing. A Root Cause Evaluation

(RCE) team was formed and their findings are contained in RCE S-96-1089.

The RCE Team reviewed Safety Valve/Relief Valve (SV/RV) work practices

and determined that an operator knowledge deficiency existed in the area

of tailpipe system interactions. The operators had not considered that

when removing a single relief valve in the tailpipe system that the

potential for lifting a second active RV in the chain must be considered

before the SV/RV is removed.

The team determined that three other RVs

had been worked with the Residual Heat Removal (RHR) Heat Exchanger

outlet header RV in service.

The tagout of the POTT vent line was not

discussed or considered prior to releasing work on 2-DG-RV-202.

Two

SROs reviewed and concurred with the proposed boundaries and another SRO

approved the hanging of tags.

Work was released for maintenance without

carefully considering that the system downstream of the RV tail pipe was

slightly pressurized by the gaseous waste system (approximately two

psig).

OPAP-0010 requires that a system be depressurized prior to

breaking its pressure boundary for maintenance.

The team determined

that job scoping did not address special circumstances. Unit 1 had

known fuel failures and the outage unit (Unit 2) POTT vent remained

connected to the Unit 1 common waste gas header.

Isolating the Unit 2

POTT vent from the common gaseous waste header was never considered or

discussed.

The RCE Team made three recommendations to site management:

Develop a training synopsis on SV/RV tagging requirements to

include tail pipe system interactions and OPAP-0010 requirements.

Modify Operations Checklist (OC)-9, Outage Readiness Checklist. to

ensure SV/RV tagging/maintenance is addressed.

Evaluate revising existing procedures to establish an alternate

vent path for the POTT during refueling outages.

Management accepted all the recommendations and committed to the NRC

that the first two items would be completed as the corrective actions in

their August 14, 1996. response to the violation.

The inspectors reviewed the training synopses and training attendance

records for the SV/RV training. The inspectors verified that OC-9 was

modified to address the issues. The licensee evaluated Operating

Procedures 1 and 2-MOP-DG-001. "Removal and Return to Service of the

POTT for Maintenance," Revision 0. and as a result issued a PAR to add

alternate vent paths in Step 5.1.3. The inspectors reviewed 1 and 2-

MOP-DG-001. Revision 0. P-1 and verified that the licensee completed all

three recommended corrective actions.

08.2

(Open) Inspection Followup Item CIFI) 280. 281/97002-01: long term

corrective actions to resolve potential Turbine Driven Auxiliary

Feedwater (TDAFW) pump overspeed trips. The inspectors reviewed the

status of licensee corrective actions with regard to this IFI.

The

7

licensee is presently in the early stages of developing a design change

package to enhance the design of the TDAFW pump control circuitry. The

design change. as presently conceived. will add a seal in signal to the

pump start circuitry. _Discussions with the system engineer indicated

that the modification would most likely be implemented during the next*

scheduled refueling outage on the respective units.

The design change

package and schedule for implementation had not been finalized. This

item will remain open until a final resolution is determined and

implemented.

II. Maintenance

Ml

Conduct of Maintenance

Ml.1

Emergency Service Water Pump (ESWP) 1-SW-P-lB Cleaning

a.

Inspection Scope (62707)

On September 11. 1997. ESWP 1-SW-P-lB failed its monthly Operations

Periodic Test (OPT). (O-OPT-SW-002) and was declared inoperable.

The

inspectors observed portions of the licensee's efforts to restore the

pump to operable status.

b. Observations and Findings

On September 11. the licensee performed procedure O-OPT-SW~002.

"Emergency Service Water Pump 1-SW-P-lB." Revision 10-Pl. The licensee

entered a seven day Limiting Condition for Operation (LCD) when Tagout

l-97-SW-0075 was implemented for pump testing. At 4:18 a.m .. the

operator at the low level reported that the pump had failed the OPT in

that it was only able to achieve a flow of 14.750 gpm.

The test

required that the pump achieve a minimum flow of 15.100 gpm.

Divers

were brought in to clean the pump.

The pump was run a number of times.

but CODtinued to exhibit low flow.

Deficiency Report (DR) 97-2528 was

written to track this event.

The inspectors attended a meeting chaired

by Engineering which focussed on causes of the pump to achieve required

flow and corrective actions.

The decision was made to remove and

disassemble the pump. inspect the pump internals. re-baseline. and have

vendor support on site.

Work Order (WO) 374295-01 was issued to

troubleshoot and perform the required maintenance.

On September 12. the pump was removed from the pump bay, disassembled.

and inspected.

The licensee's inspection revealed barnacles

approximately one half inch deep on the pump diffuser and impeller.

The

vendor representative stated that marine growth in excess of one forth

of an inch would significantly affect pump performance.

The licensee

took photographs of the affected areas of the pump.

The inspectors

viewed the photographs and toured the low level to observe the

disassembled pump.

The inspectors observed the craft removing marine

growth from the pump column.

The disassembled pump and the pump bowl .

diffuser and impeller were viewed.

The bowl. impeller. and diffuser

were sent to the shop to remove the barnacles and re-activate the anti-

1*

8

fouling coating.

The licensee had previously coated these components to

inhibit hydroid growth.

The inspectors observed craft performance and also observed that the WO

and the following procedures and documents were at the job site and were

being used.

O-MCM-1910-01. "Diving Procedure.* Revision 2

O-MCM-0114-01. "Emergency Service Water Pump Maintenance."

Revision 5

GMP-C-107. "Rigging and Lifting,* Revision 5

Tagout l-97-SW-0075

The inspectors reviewed WO 374295-01. the tagout. and five of the last

completed O-OPT-SW-002 procedures.

On September 13. the licensee had

reassembled the pump. replaced it in the pump pit. and realigned the

pump assembly.

The pump was placed back in service following Post

Maintenance Testing (PMT) with the pump producing 16.700 gpm.

The

licensee exited the LCO at 10:45 p.m. on September 13.

The licensee

performed the same maintenance on the A and C ESWPs.

Upon removal from

the water. both pumps exhibited barnacle growth similar to the B pump.

Following cleaning. both pumps demonstrated a significant improvement in

performance.

The licensee is evaluating various methods to prevent barnacles from

attaching to the impeller as well as methods to effectively remove the

barnacles without pump disassembly.

Review of the licensee's corrective

actions is identified as IFI 50-280. 281/97009-02.

c.

Conclusions

Maintenance performed on the ESWPs was completed in a satisfactory

manner.

Problems with marine growth on the pumps have not been

adequately resolved.

An IFI is being opened to track the licensee's

resolution of this matter.

Ml.2

No. 1 Emergency Diesel Generator (EOG) Radiator Louvers

a.

Inspection Scope (62707)

The inspectors observed the licensee's troubleshooting efforts to

determine the cause of the failure of the East Radiator Louvers of No. 1

EOG to modulate.

b.

Observations and Findings

On August 12. 1997. an operator observed that the East Radiator Louvers

of No. 1 EOG did not operate properly.

The controller was replaced and

the louvers functioned satisfactorily. This matter was documented in

..

9

NRC Inspection Report 50-280. 281/97-07.

On September 1. during the

troubleshooting effort. the "Hot Engine* alarm came in and cleared

several times during the two hour EOG run.

The east louvers did not

open until 185 degrees F but should have started to open at 165 degrees

F.

The controller was set at 165 degrees Fas a corrective action for

the August event.

DR 97-2463-was issued to track the event.

The

inspectors attended several meetings in which the licensee discussed

potential causes of the failure of the East Louvers to modulate.

No

conclusions were reached on the causes of the failure and Engineering

requested that the EOG be run for data gathering. Operations was

reluctant to unnecessarily operate the EOG for data gathering.

On September 23. the inspectors observed the data gathering run for the

No. 1 EOG.

The licensee instrumented the controls for the East Radiator

Louvers.

The inspectors observed that the instrument cables were routed

between the control cabinet and the door and rested on the upper door

hinge.

The door was free to move and the inspectors believed the cables

could be damaged if the door was accidentally closed. The inspectors

discussed their observation with the licensee who concurred with the

conclusion.

The licensee secured the door in the open position to

prevent it from closing.

The inspectors observed that WO 370314-01. "Repair Louver Control." and

Operating Procedure (OP)-EG-001. "Number 1 Emergency Diesel Generator.*

Revision 7. were at the jobsite and were used by both the craft and the

operators. Craft personnel were methodical and professional in carrying

out their duties.

The inspectors observed that the operators were

performing independent verification of the prestartup procedure steps.

The inspectors reviewed the WO and OP-EG-001.

The No. 1 EOG was started at 10:45 a.m. and was at full load 27 minutes

later. The inspectors observed the run and noted that the west louvers

modulated but the east louvers only opened slightly. The EOG coolant

temperature stabilized and the east louvers had not modulated nor did

the "Hot Engine* alarm initiate. At 11:54 a.m. the EOG load was reduced

when the system engineer determined that no additional data was

required. A review of the data revealed that the controller did not

function properly and DR 97-2655 was issued to track the failure of the

. contra 11 er.

The licensee contacted the controller vendor. Barber-Coleman. and was

informed that the vendor no longer recommends the use of the external

capacitor that is located between the controller and the actuator. A

Request for Engineering Assistance (REA) was submitted to remove the

capacitor from all three EDGs.

The licensee was attempting to obtain

another actuator and planned to replace both the actuator and

controller. The licensee plans to bench test the replacement controller

prior to installation.

The controller is designed to cause the louvers to fully open when the

"Hot Engine* alarm is initiated. The licensee determined that No. 1 EOG

was not inoperable based on their determination that the EOG coolant

I'

C.

10

temperature limits would not be exceeded even if the east lovers failed

to open.

Conclusions

The licensee attempted to determine the cause of No. 1 EOG louver

controller failures. but has not been successful. Additional effort is

required to repair and return the east bank of louvers to a fully

functional condition. The inspectors considered that the craft were

deliberate and acted in a professional manner during troubleshooting

activities.

Ml.3 Surveillance Observations (61726)

On October 4. the inspectors observed portions of procedure 1-PT-8.1.

"Reactor Protection System Logic (For Normal Operations)." Revision 14.

being performed.

The inspectors observed the briefings held in the

Instrumentation & Calibration (I&C) shop. the Control Room. and with the

work planning SRO and the STA.

The briefings were thorough and

detailed. The inspectors observed the train A portion of the

surveillance. The performance of the surveillance was observed in the

relay and switchgear rooms and in the Control Room.

The I&C technicians

were methodical and cautious. Repeat backs and verification were

consistently performed.

The inspectors considered that the technicians

did an excellent job performing the surveillance .

Ml.4 Miscellaneous Unit 2 Outage Issues

a.

Inspection Scope (62707)

The inspectors reviewed the licensee's plans and commitments for the

upcoming Unit 2 refueling outage. This effort included licensee

maintenance deferrals and commitments.

b.

Observations and Findings

Unit 2 Reactor Coolant Pump (RCP) Seal Inspection

The licensee had originally scheduled a RCP seal inspection during the

upcoming Refueling Outage (RFD 15); however. management determined that

the seal inspection of RCPs A and B would be deferred until RFD 16.

The -

RCPs at Surry are Westinghouse Model 93A with a standard eight inch

Aluminum Oxide seal package.

The vendor recommends inspection of the

seals on a frequency of every other cycle.

The licensee asked

Westinghouse in 1994 for recommendations concerning the extension of the

inspection frequency to every third cycle.

In an August 24. 1994.

memorandum. Westinghouse provided recommendations for extending the

operation life of the seals. The recommendations were to be implemented

at the beginning of the three cycle period and included:

1.

Rebuild the Number 1 seal with new internal 0-rings.

2.

3.

4.

5.

6.

7.

11

Replace the Number 1 and 2 inserts regardless of condition.

Install new Number 2 and 3 runners.

Calibrate and repair all RCP seal related instrumentation.

If the

instrumentation is chronically unreliable. replace it.

Install high temperature 0-rings.

Do not use obsolete Aluminum Oxide seal components:

The Silica

Nitride seals of RCP B have better wear characteristics.

Reduce the rating of the seal injection filters.

Westinghouse stated that even with the recommendations fully implemented

the licensee should anticipate some erratic Number 2 seal operation

during the third cycle.

For RCP A. only recommendations Number 1. 2. and 7 were implemented.

All but recommendations Number 4 and 5 had been implemented for RCP B

during 1995.

Engineering recommended that the inspection frequency not

be extended to three cycles for RCP A and that the seal be overhauled

during RFD 15.

Engineering stated that the operation of RCP B for an

additional cycle had its risks. but the condition of the seal was more

conducive to operation for an- additional cycle .

The inspectors were concerned about the deferral of the RCP A seal

inspection and discussed their concerns with licensee management.

The

inspectors were informed that the licensee was aware of the risks

involved and that the deferral of the RCP A seal inspection was an "at-

risk" decision. A factor in this decision was that if the Number 1 seal

failed. it would not be catastrophic failure and the Unit could be

safely shut down.

NRC Commitments To Be Completed During The Unit 2 RFD 15

The licensee has committed to the NRC to perform or complete various

tasks. The following is a list of those significant items which will be

completed during RFD 15:

Install Appendix R isolation breakers between vital buses and

uninterruptable power supplies. (DCP-94-018)

Modify valves 2-SI-MOV-1890A/B to install bonnet cavity pressure

equalization line. CDCP 96-034. WO 350835-01)

Complete the physical verification of differences associated with

documented valve alignments for valves not accessible during

normal plant operation. CIR 50-280. 281/96011)

The inspectors reviewed these commitments and determined that they were

in the scope of the outage.

C.

12

Conclusions

The licensee's deferral of the A RCP seal inspection during the upcoming

Unit 2 outage could result in a forced RCP seal replacement outage, but

does not preclude safe operation of the unit.

Licensee commitments for

the Unit 2 outage were reviewed and found to be within the scope of the

outage.

MB

Miscellaneous Maintenance Issues (92902)

MB.1 Auxiliary Shutdown Facilities Maintenance/Surveillance

a.

Inspection Scope (62700)

b.

This portion of the inspection was conducted to review the licensee's

practices concerning surveillance. testing and maintenance of the

plants* auxiliary shutdown facilities. The purpose of the inspection

was to determine what actions were being taken by the licensee to assure

that the facilities would perform their safety function if called upon

during a plant event.

In order to complete the inspection. the licensee

was requested to provide the following information: a list of all

surveillances. preventive maintenance. and calibrations performed; a

list of all deficiency reports and work orders written on the facility

in the last year. and a list of any design changes implemented on the

facility in the last three years. This information was provided and

reviewed during the course of the inspection. Additionally, the

inspectors reviewed the Updated Final Safety Analysis Report (UFSAR).

TSs and the licensee's Abnormal Procedure AP 20. "Main Control Room

Inaccessibility," Revision 3.

Walkdowns of the auxiliary shutdown panel

(for each unit) and the two remote monitoring panels (located in the

cable spreading room) were conducted. These walkdowns compared

installed equipment to the applicable drawing. verified system lineup to

the applicable site procedure. and included an inspection of the inside

of the auxiliary shutdown panels for material condition.

In addition. a

sample of surveillances. calibrations and periodic tests were reviewed

for technical adequacy.

Observations and Findings

Review of the station deviations and WOs written on the equipment

determined that adequate and appropriate corrective action was being

taken for identified equipment deficiencies.

Review of the UFSAR

determined that there were no differences between the UFSAR and the site

procedures concerning the auxiliary shutdown facility.

Walkdown of the

panels identified one minor problem concerning eight switches. which had

been inadvertently omitted from the switch position verification

checklist in OC-15 (Unit 1) and OC-16 (Unit 2). "Aux Shutdown Panel

Switches." effective date June 23. 1997. This condition was immediately

addressed by the licensee in Deviation Report S97-2653.

The walkdown

determined that the equipment was in good condition. although the inside

of the auxiliary shutdown panel had some dust accumulation.

The

licensee was in the process of establishing a five year preventive

13

maintenance to clean that area.

The inspection determined that the

following surveillance. calibration. and periodic testing was being

routinely conducted by the licensee:

Functional testing of all switches on the auxiliary shutdown

panels was performed in accordance with procedure 1-0SP-ZZ-001.

"Auxiliary Shutdown Panel Functional Surveillance." Revision 2.

Calibration of all meters on the auxiliary shutdown panels and the

remote monitoring panels was performed in accordance with various

site calibration procedures.

An operational check was periodically performed. using Procedure

PT-36.1. "Remote Instrumentation Channel Check." Revision 4. which

compared the readings on the remote meters to those same readings

in the control room.

An operational check was periodically performed which verified the

correct positioning of the auxiliary shutdown panel(s) switches in

accordance with Procedures OC-15 and OC-16.

c. Conclusions

The licensee's actions with regard to surveillance. testing and.

maintenance of the auxiliary shutdown panels and the remote monitoring

panels were excellent. All switches controlling equipment on the

auxiliary shutdown panels were subjected to testing to verify

operability. All meters on all of the panels were in the licensee's

calibration program. There were operational checks that compared the

meter readings on all of the panels to the comparable control room

meters. and checks that periodically verified proper switch positioning

on the auxiliary shutdown panels.

M8.2 (Closed) VIO 50-280. 281/94017-02:

failure to implement corrective

actions to preclude repetition of Foreign Material Exclusion (FME)

deficiencies.

The inspectors reviewed the following documents:

Reply To A Notice Of Violation. dated August 17. 1994

VPAP-1302. "Foreign Material Exclusion Program.* Revision 9

&

VPAP-2002. "Work Request and Work Order Tasks.* Revision 7

Station Nuclear Safety Station Deviation Trend Reports for fourth

quarter 1996 and first and second quarter 1997

Surry Self Assessment 1997 Unit 1 RFD FME Report.

Maintenance Self Assessment First Quarter 1997 Status Report

Lesson plan EMI-6-LP-4. Foreign Material Exclusion Program

14

Various Deviation Reports (DRs) issued for FME problems.

In addition. the inspectors looked at the computer based training

provided for the Nuclear Business Unit employees. attended the FME

worker qualification training presented on September 25. 1997. and

discussed FME issues with Maintenance personnel. Actions to avoid FME

problems included the requirements in VPAP-1302 that personnel entering

a FME area were to have been qualified or be escorted by a qualified

person and specially trained FME coordinators were to be assigned

responsibility for the FME area.

The FME worker qualification training

was considered a strength in that it personalized the negative affects

that foreign material can have on employee safety and dose. as well as.

the economic impact on the company.

The licensee has expended

considerable resources to sensitize workers. both contract and plant

employees. concerning FME issues.

III. Engineering

El

Conduct of Engineering

El.1 Service Water System Safety Evaluation 97-123

a.

Inspection Scope (37551)

The inspectors reviewed safety evaluation 97-123 that justified

continued operation with improperly installed service water Metal

Expansion Joints (MEJs).

b. Observations and Findings

On September 17. a concern was raised by engineering personnel dealing

with the adequacy of the service water MEJs in the recirculation spray

heat exchanger service water lines located inside containment on both

units.

The concern specifically addressed the configuration of the tie

rods and the gap between the nuts on the tie rod and the expansion

joint. The installed configuration allowed unrestrained compression of

the MEJs but did not allow unrestrained extension of the MEJs.

Based on

the as installed configuration of the expansion joint tie rods. an

engineering analysis was performed to determine the effect of this

additional loading on the system.

The analysis determined that the most,

limiting component was the recirculation spray heat exchanger upper

support structure support plate and shear bolts. The associated design

allowable stress values would be exceeded during a design basis seismic

event.

The analysis also determined that the stresses would not exceed

the American Society of Mechanical Engineers.Section III Appendix F

allowables.

Based on the analysis performed. the licensee determined

that the system was degraded but operable.

The Unit 1 MEJ tie rods were configured to the proper configuration

prior to completion of the safety evaluation.

Based on the operability

evaluation. the licensee elected to wait until the scheduled Unit 2

C.

15

refueling outage to modify the expansion joint tie rods inside the Unit

2 containment.

The unit was scheduled to shutdown October 6 for the

refueling outage.

Conclusions

The Safety Evaluation addressing service water expansion joint

operability was thorough and adequately justified system operability.

The decision to defer modification of the Unit 2 expansion joints inside

containment approximately two weeks until a scheduled refueling outage

appeared appropriate.

IV. Plant Support

Rl * Radiological Protection and Chemistry Controls (71750)

On numerous occasions during the inspection period. the inspectors

reviewed Radiation Protection (RP) practices including radiation control

area entry and exit. survey results. and radiological area material

conditions.

No discrepancies were noted. and the inspectors determined

that RP practices were proper.

Pl

Conduct of Emergency Preparedness (EP) Activities

On August 26. an Emergency Preparedness Exercise was conducted.

Regional personnel and the resident inspectors participated in the

exercise. The exercise is discussed in detail in NRC Inspection Report

280. 281/97008.

Sl

Conduct of Security and Safeguards Activities

On numerous occasions during the inspection period. the inspectors

performed walkdowns of the protected area perimeter to assess security

and general barrier conditions.

No deficiencies were noted and the

inspectors concluded that security posts were properly manned and that

the perimeter barrier's material condition was properly ~aintained.

F2

Status of Fire Protection Facilities and Equipment

F2.1

10 CFR 50 Appendix R Isolation and Breaker Coordination

a.

Inspection Scope (64704)

The inspector reviewed an issue identified by the licensee regarding the

electrical isolation and protection provided for the vital electrical

bus panels in the event of a control room fire. Also reviewed was

circuit breaker coordination provided for the vital electrical bus

panels for compliance with the requirements of 10 CFR 50 Appendix R.

b. Observations and Findings

r

16

VITAL BUS ISOLATION

The Surry facility has a common control room for both Units 1 and 2.

The control room complex includes the Unit 1 computer room. the Unit 2

computer room and the control room administrative annex.

These rooms

are in the same fire area.

Each unit has four Uninterruptable Power

Supplies (UPS). UPS A-1. A-2. B-1 and B-2. which supply power to vital

emergency panels. These panels provide power to safety related

equipment and equipment required to achieve safe shutdown in the event

of a control room fire.

UPS lA-1 and lA-2 supply power to panels VB 1-I

and VB 1-III which are located in the Unit 1 computer room.

UPS 2A-1

and 2A-2 supply power to VB 2-I and VB 2-III which are located in the

Unit 2 computer room.

UPS lA-2 supplies the Unit 2 Appendix R safe

shutdown panels and UPS 2A-2 supplies the Unit 1 Appendix R safe

shutdown panels. These Appendix R remote shutdown panels are located in

each unit's emergency switchgear room and in the cable spreading room.

They contain instrumentation required for performing plant shutdowns

from outside the main control room. such as steam generator level. RCS

pressure and temperature. and pressurizer level.

There were no means available to isolate the vital 120 VAC bus panels in

the Unit 1 and 2 computer rooms from the UPS panels. A control room

fire could cause an electrical fault ("short") in vital buses VBs 1-I.

1-III. 2-I and 2-III which could trip the breaker or fuse to the

affected UPS panel. This could result in the loss of power to the

Appendix R shutdown panels. Should this occur. there would be no

instrumentation operable on the Appendix R panels to support the plant

shutdown activities. In addition. power would also be lost to the

emergency communication equipment located adjacent to the remote

Appendix R panels. This communication equipment is required for remote

, shutdown activities. Power to the vital buses could not be restored

until the fault conditions were corrected and any blown fuses replaced.

The failure to provide vital bus isolation does not meet the

requirements of Appendix R Section I II. G and is i denti fi ed as Apparent

Violation EEI 50-280. 281/97009-03

BREAKER COORDINATION

The vital bus panels are supplied power by the UPS.

Each vital bus

panel contains a number of branch circuit breakers and a 100-amp main

circuit breaker.

Each circuit breaker has a thermal unit and a magnetic

unit.

Based on the licensee's engineering evaluations. the thermal

units had inverse time versus current characteristics. so that as

current increased. the trip time decreased.

The magnetic units would

operate instantaneously. * At current less than 1.000 amps. the thermal

units would provide selective tripping to ensure that the branch

breakers would open prior to the main circuit breaker. i.e .. correct

circuit breaker coordination.* However. at currents above 1. 000 amps.

proper selective tripping could not be ensured. This could result in

the opening of either the branch or main circuit breaker.

Most of the

vital bus panels supply power to some Appendix R related functions.

If

17

the main circuit breaker opened. all functions provided by the panel

would be lost. The licensee's analysis found that at least one panel

could be lost due to a coordination issue in the following fire areas:

control room. Unit 1 emergency switchgear room. Unit 2 emergency

switchgear room and the turbine building. These branch circuits supply

electrical power to a number of Appendix Rand safe shutdown components.

This inadequate breaker coordination does not meet the requirements of

10 CFR 50. Appendix R.Section III.Gas implemented by the Surry

Appendix R report. Section 3.9.2 which states "The problem of associated

circuits of concern by common power supply is resolved by ensuring

adequate electrical coordination between the safe shutdown power source

supply breaker and the component feeder breakers or fuses ... " The

failure to meet the requirements of Appendix R for circuit breaker

coordination is identified as Apparent Violation EEI 50-280. 281/97009-

04.

CORRECTIVE ACTIONS

The licensee's Electrical Distribution System Functional Inspection

(EDSFI) assessment performed in 1992 identified the possible loss of

uninterruptable power supplies to equipment required in both units to

achieve and maintain the plant in a safe shutdown condition in the event

of an Appendix R control room fire. The licensee issued Deviation

Report (DR) S-92-1806 which documented that the facility was outside the

plant's design basis and in violation of the requirements of 10 CFR 50

Appendix R.

However. this condition was not reported to the NRC.

A

plant modification request was initiated by Design Change Package (DCP)

93-002-03 to install fuses on the feeders to the vital bus panels. This

DCP was subsequently superseded by DCP 94-018 which was scheduled to be

completed for Unit 1 during the Fall 1998 refueling outage and for Unit

2 during the Fall 1997 refueling outage.

In early 1993. the licensee identified inadequate breaker coordination

between the branch circuits and the main circuit on a number of vital

bus distribution panels. This issue involved the possibility that a

fault condition affecting one of the branch circuits would trip the main

panel circuit breaker in lieu of the branch circuit breaker and result

in the loss of the entire bus panel. This issue was identified as

outside of the plant's design basis and was documented by DR S-93-0109.

This condition was also not reported to the NRC.

DCP 94-018 was revised'

to replace the main input breakers to each of the vital bus distribution

panels with non-automatic switches. i.e .. no fuses or circuit breakers.

On March 24. 1997. following completion of engineering evaluation ET

CCE-96-068 to support DCP 94-018. the licensee concluded that the plant

was not in compliance with the requirements of Appendix R.

This

conclusion was documented by DR S-97-0981 and this issue was discussed

with the NRC resident inspectors; however. this condition was not

formally reported to the NRC.

18

On July 31 and August 5. 1997. the NRC staff had conference calls with

the licensee to discuss these issues. Effective August 14. 1997. the

licensee revised the Fire Contingency Action Procedure O-FCA-1.00.

"Limiting Main Control Room Fire (With 19 Attachments)." Revision 12. to

provide sufficient guidance to ensure that the units would be maintained

in a safe shutdown condition in the event of an Appendix R fire. This

procedure could be accomplished with the normal minimum plant staffing

plus one designated electrician assigned to the operating shift. In

general. the compensatory actions required cutting the supply cables to

vital bus panels VBs 1-I. 1-III. 2-I. and 2-III. This would disconnect

or open the circuit to the fire damaged cables or panels to eliminate an

electrical fault condition.

The vital power supply panels would then be

  • restored to service.

Any blown fuses within the uninterruptable power

supply panels would be replaced.

The electrical tools. fuses and other

equipment required to perform these tasks were stored within the

emergency switchgear room.

Performance of these repair actions would be

required within 30 minutes to meet the time lines for safe shutdown

established in the Surry Appendix R Report. Chapter 5. Attachment 2.

The licensee had performed walkdowns and verified that these actions

could be accomplished within the-required time frame.

Adequate

compensatory measures were implemented in August 1997 to control and

monitor a plant shutdown following an Appendix R type fire until the

permanent modifications were completed.

The compensatory measures for the breaker coordination issue consisted

of restoring the vital buses supplying Appendix R equipment to service

on an as needed basis. Operations personnel had been directed and

Procedure O-FCA-1.00 had been revised to first attempt to reclose an

open circuit breaker on the affected vital bus panel.

If this was not

successful. circuit breakers supplying non-Appendix R equipment would be

opened to allow the main circuit breaker to be successfully closed.

The

compensatory actions implemented in August 1997 were considered adequate

to address this issue until permanent modifications are completed.

The inspectors reviewed Procedure O-FCA-1.00. inspected the repair

supplies and equipment stored in the emergency switchgear room. and

concluded that the proposed compensatory actions were appropriate.

These compensatory actions were first identified in 1993; however. prior

to August 1997. a designated electrician was not always on the site to

perform the required actions and the required ~lectrical tools and

replacement fuses were not stored within the emergency switchgear rooms.

In addition. Procedure O-FCA-1.00 did not adequately address all of the

required compensatory actions. The inspectors concluded that prior to

August 1997. the plant operators may not have been able to activate the

remote shutdown panels and establish remote monitoring of plant

conditions within the required 30 minute time frame.

The Surry Operating License Section 2.I for Units 1 and 2 states that

the licensee is required to implement and maintain the administrative

controls identified in Section 6 of the Fire Protection Safety

Evaluation.

The Surry Appendix R Report. Chapter 12. Section C

19

identified that the Quality Assurance program applies to the fire

protection program. Section C.8 states that measures established to

ensure that conditions adverse to fire protection. such as failures.

malfunctions. deficiencies. deviations. defective components.

uncontrolled combustible materials. and nonconformances are promptly

identified. reported and corrected and are described in Section 17.2.16

of VEP 1-5A. "Operational Quality Assurance Program Topical Report." A

noncompliance to the Appendix R requirements in the event of a control

room fire was identified in 1992 and inadequate breaker coordination

issues were identified in 1993: however. actions were not taken to

promptly correct these issues. The failure to promptly correct these

identified Appendix R fire protection discrepancies is identified as

Apparent Violation EEI 50-280. 281/97009-05.

REPORTABILITY

10 CFR 50.72(b)(l)(ii)(B) and 50.73(a)(2)(ii)(B) require licensees to

notify the NRC of identified plant conditions that are outside the

design basis of the plant. The notification is to be as soon as

practical, but within one hour. of the occurrence followed by a written

Licensee Event Report CLER) within 30 days after the discovery of the

event.

The licensee did not report these issues to the NRC.

The

failure to properly report to the NRC Appendix R fire protection

discrepancies which were outside the design basis of the plant is

identified as Apparent Violation EEI 50-280. 281/97-09-06.

c.

Conclusions

Two apparent violations were identified for inadequate fire protection

features involving the control room complex and for safety related vital

electrical panels.

Because of these deficiencies. at least one train of

systems necessary to achieve and to maintain the plant in a hot shutdown

condition from either th.e control room or emergency control station may

not be protected from fire damage.

Two additional apparent violations

were identified involving the failure to report conditions outside the

design basis of the plant and the failure to correct Appendix R fire

protection discrepancies promptly.

F2.2 Fire Protection Features for Radwaste Facility (64704)

a.

b.

Inspection Scope

The inspectors reviewed the fire protection features provided for the

Radwaste Facility to determine if these features met the NRC guidelines

of NUREG 0800, Section 9.5.1.

Observations and Findings

Document C-20-122K-001. "Safety Analysis for New Radwaste Facility."

Revision 1. dated April 1991. contained a description of the fire

protection features for the Radwaste Facility. The inspectors reviewed

Document C-20-122K-001 and performed a walkdown inspection of the

20

Radwaste Facility. The facility is a six-story non-combustible building

provided with an automatic fire alarm system. fire hose standpipe

system. portable fire extinguishers. and automatic sprinkler systems.

The sprinkler systems only provide partial protection and were installed

in areas containing combustible materials or high radiation.

The design

concept for the facility's fire protection features included provisions

to detect and alert the facility operators of the existence of a fire.

suppress the fire. and prevent the spread of fire to adjacent building

areas.

The fire alarm signals are received in the Radwaste Facility control

room which is continuously manned.

Upon receipt of a fire alarm signal.

the alarm response procedure refers the operator to Radwaste Abnormal

Procedure RAP-26-02,"Fire." Revision 1. T~is procedure directed the

operators to extinguish the fire and to contact the Surry control room

and request Surry Fire Brigade assistance if the fire cannot be

extinguished with one portable fire extinguisher.

The inspectors

verified that the Radwaste Facility operators had received training in

the use of fire extinguishers.

Most of the maintenance and surveillance testing activities for various

equipment in the Radwaste Facility were performed by radwaste personnel.

Previously, the testing of the fire protection equipment had been

performed by Surry station personnel; however. testing of the fire

protection equipment was in the process of being transferred to the

Radwaste Facility personnel.

The Surry fire prevention procedures were used to control transient

combustible materials. combustible and flammable liquids. hot work

activities. and the surveillance and testing of the fire protection

equipment. These were adequate. except operability of the Radwaste

Facility fire protection equipment was not addressed.

To address this

issue. the licensee had implemented a policy in which the Radwaste

Facility personnel were to inform the Surry control room and fire

brigade of any fire protection impairments.

In addition. the area of

the effected impairment was to be monitored approximately every four

hours while the fire protection systems were out of service. The

inspectors concluded that these compensatory actions were appropriate.

During the facility inspection. the inspectors noted that the general

housekeeping in the facility was excellent with appropriate emphasis

being provided for the control of combustible and flammable materials.

Material condition of the fire protection equipment was very good and

the equipment appeared to be well maintained.

However. the inspectors

noted that several changes had been made to the fire protection features

provided for the facility, such as replacing the Halon fire

extinguishers with dry chemical type extinguishers and installation of a

suspended ceiling below the installed fire detection instruments in

several areas.

The licensee stated that no written evaluation was

available to justify these changes.

The safety analysis document for

the Radwaste Facility was prepared as a 10 CFR 50.59 evaluation to

determine if the facility could be constructed. tested and placed in

21

service without NRC approval. This document was apparently not intended

to be maintained as a design basis document.

Currently the licensee

does not have a process to maintain an updated description of the

facility and operational process or a requirement that a justification

be provide for any changes made to the facility. The licensee stated

that this issue would be evaluated. Until the inspectors can review and

assess the licensee's evaluation. this is identified as IFI 50-280.

281/97009-07 ..

The inspectors reviewed the preventive maintenance program records and

verified that periodic inspections and tests of the fire protection

equipment was being performed at the frequency recommended by the

licensee's insurance carrier. This inspection frequency was considered

satisfactory.

c.

Conclusions

Excellent housekeeping was provided for the Radwaste Facility with good

implementation of the station's fire prevention procedures and

maintenance of the fire protection equipment.

An IFI was identified

involving the lack of a design basis type document and no requirement to

provide justifications for changes made to the building structure.

equipment and facility processes.

F8

Miscellaneous Fire Protection Issues (92904)

F8.l (Closed) VIO 50-280. 281/96010-03: inadequate preventive maintenance

performed on spare electric motors.

(Closed) IFI 50-280. 281/96010-04: preventive maintenance requirements

for spare RHR and component cooling water pumps.

The licensee responded to the VIO by letter dated November 26. 1996.

The corrective actions taken on the VIO and IFI were closely related.

The VIO was related to the lack of adequate preventive maintenance being

performed for two large spare safety related component cooling water

pump motors.

The IFI was related to the preventive maintenance

requirements for mechanical equipment in storage. such as safety related

pumps.

As corrective action. the licensee sent the two electric motors to a

vendor for a detailed inspection.

The vendor performed an inspection

and repaired all identified discrepancies.

An assessment was performed

by the licensee of the preventive maintenance requirements for all

electric motors and mechanical components. such as pumps. blowers. air*

compressors. etc .. which were being stored in the site warehouses.

Procedure O-EPM-2302-01. Inspection of Stored Motors. Revision 3. was

revised to enhance the maintenance being provided for the stored motors.

The revision included detailed inspection requirements for all stored

motors and required the shafts be rotated annually for all electric

motors in storage.

In addition. all Appendix R designated motors and

motors more than 50 HP were required to be rotated quarterly. The

..

22

licensee's assessment also identified several motors. such as the two

large motors for the component cooling water pumps, which were required

to be provided with heaters during storage.

The licensee's assessment identified approximately 20 mechanical

components which were required to be included in a preventive

maintenance program.

These mechanical components were inspected and the

component's shafts were rotated at least every 6-months using a routine

maintenance work order.

The inspectors reviewed the work request for the maintenance components

which was completed August 5, 1997. and Procedure O-EPM-2302-01. which

was completed on August 25. 1997. and verified that the required

preventive maintenance for the electric motors and mechanical components

in storage were bei~g performed.

The licensee took positive action to enhance the preventive maintenance

being performed on the storage of spare safety related electric motors

and rotating mechanical components.

F8.2 (Closed) LER 50-280/96007-00: fire watch patrol inspection frequency

exceeds one hour. This event was reported to the NRC when the licensee

failed to complete fire watch inspections within the frequency required

by TS 3.21.B.1 of "at least once per hour."

More specifically, three

fire detection zones were inspected 7 minutes late. two fire detection

zones were inspected 11 minutes late. and three fire detection zones

were inspected 13 minutes late. The cause of this event was attributed

to the fire watch patrol being delayed by station security personnel

following an inadvertent activation of a security alarm.

The licensee* s corrective actions for this event entailed the fo 11 owing;

Cl) Fire watch personnel were instructed that fire detection zone

inspections must be performed in accordance with TSs and security

requirements. (2) Fire watch personnel were further instructed to inform

security officers that they are performing fire watch duties if a

security alarm is activated during the tour so that the tour could be

completed in accordance with TS requirements. and (3) Fire watch

computer based training was revised to emphasize the importance of

compliance with the one hour TS requirement for completing fire watch

tours.

The inspectors reviewed these actions and found them to be

satisfactory.

The failure to perform fire watch tours within the specified one hour

time frame is a VIO of TS 3.21.B.1. This non-repetitive. licensee-

identified and corrected VIO is being treated as a Non-cited Violation

consistent with Section VII.B.1 of the NRC Enforcement Policy. This

matter in identified as NCV 280. 281/97009-08 .

V. Management Meetings

23

Xl

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on.October 10. 1997.

The

licensee acknowledged the findings presented.

The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary.

No proprietary information was

identified.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

M. Adams. Superintendent. Engineering

R. Allen. Superintendent. Maintenance

R. Blount. Assistant Station Manager. Nuclear Safety & Licensing

D. Christian. Station Manager

M. Crist. Superintendent. Operations

B. Shriver. Assistant Station Manager. Operations & Maintenance

T. Sowers. Superintendent. Training

B. Stanley, Director. Nuclear Oversight

W. Thorton. Superintendent. Radiological Protection

IP 37551:

IP 40500:

IP 61726:

IP 62700:

IP 62707:

IP 64704:

IP 71001:

IP 71707:

IP 71750:

IP 92700:

IP 92901:

IP 92902:

Opened

INSPECTION PROCEDURES USED

Onsite Engineering

Effectiveness of Licensee Controls in Identifying, Resolving, and

Preventing Problems

Surveillance Observation

Maintenance Program Implementation

Maintenance Observation

Fire Protection Program

Licensed Operator Requalification Program Evaluation

Plant Operations

Plant Support Activities

Onsite Followup of Written Reports of Nonroutine Events at Power

Reactor Facilities

Followup - Plant Operations

Followup - Maintenance

ITEMS OPENED, CLOSED, AND DISCUSSED

50-280, 281/97009-01

NCV

inadequate SFP makeup procedure

(Section 01.4).

24

50-280. 281/97009-02

IFI

ESWP corrective action followup

(Section Ml .1).

50-280, 281/97009-03

EEI

failure to meet the requirements of

Appendix R for vital bus isolation

( Sect i on F2. 1) .

50-280. 281/97009-04

EEI

failure to meet the requirements of

Appendix R for circuit breaker

coordination (Section F2.1).

50-280. 281/97009-0~

EEI

failure to promptly correct licensee

identified Appendix R fire

protection discrepancies (Section

F2.1).

50-280. 281/97009-06

EEI

failure to report Appendix R fire

protection discrepancies which were

outside the design basis of the

plant (Section F2.l).

50-280. 281/97009-07

IFI

no documentation or evaluations

available for changes made to the

Radwaste Facility (Section F2.2).

50-280. 281/97009-08

NCV

failure to perform fire watch tours

within the specified one hour time

frame (Section F8.2).

Closed

50-280.281/97009-01

NCV

inadequate SFP makeup procedure

(Section 01. 4).

50-280. 281/96005-01

VIO

inadequate system isolation (Section

08.1).

50-280. 281/94017-02

VIO

failure to implement corrective

actions to preclude repetition of

foreign material exclusion

deficiencies (Section M8.2).

50-280. 281/96010-03

VIO

inadequate preventive maintenance

performed on spare electric motors

(Section F8 .1).

50-280. 281/96010-04

IFI

preventive maintenance requirements

for spare RHR and component cooling

water pumps (Section F8.1).

50-280. 281/97009-08

NCV

failure to perform fire watch tours

within the specified one hour time

frame (Section F8.2).

_

_..J

50-280/96007-00

LER

Discussed

280. 281/97002-01

IFI

25

fire watch patrol inspection

frequency exceeds one hour (Section

F8. 2).

long term corrective actions to

resolve potential TDAFW overspeed

trips (Section 08.2)

I'

tlie failure to make a required report to the NRC will be based upon the significance of and the

circumstances surrounding the matter that should have been reported. However, the severity level of an

untimely report, in contrast to no report, may be reduced depending on the circumstances surrounding

the matter. A licensee will not normally be cited for a failure to report a condition or event unless the

licensee was actually aware of the condition or event that it failed to report. A licensee will, on the other

hand, normally be cited for a failure to report a condition or event if the licensee knew of the information

to be reported, but did not recognize that it was required to make a report.

V. PREDECISIONAL ENFORCEMENT CONFERENCES

Whenever the NRC has learned of the existence of a potential violation for which escalated enforcement

action appears to be warranted, or recurring nonconformance on the part of a vendor, the NRC may

provide an opportunity for a predecisional enforcement conference with the licensee, vendor, or other

person before taking enforcement action. The purpose of the conference is to obtain information that will

assist the NRC in determining the appropriate enforcement action, such as: (1) a common understanding

of facts, root causes and missed opportunities associated with the apparent violations, (2) a common

understanding of corrective actions taken or planned, and (3) a common understanding of the

significance of issues and the need for lasting comprehensive corrective action.

If the NRC concludes that it has sufficient information to make an informed enforcement decision, a

conference will not normally be held unless the licensee requests it. However, an opportunity for a

conference will normally be provided before issuing an order based on a violation of the rule on

Deliberate Misconduct or a civil penalty to an unlicensed person. If a conference is not held, the licensee

will normally be requested to provide a written response to an inspection report, if issued, as to the

licensee's views on the apparent violations and their root causes and a description of planned or

implemented corrective actions.

During the predecisional enforcement conference, the licensee, vendor, or other persons will be given an

opportunity to provide information consistent with the purpose of the conference, including an

. explanation to the~RC of the immediate corrective actions (if any) that were taken following

identification of the potential violation or nonconforrnance and the long-term comprehensive actions that

were taken or will be taken to prevent recurrence. Licensees, vendors, or other persons will be told when

a meeting is a predecisional enforcement conference.

A predecisional enforcement conference is a meeting between the NRC and the licensee. Conferences

are normally held in the regional offices and are normally open to public observation. Conferences will

not normally be open to the public if the enforcement action being contemplated:

(1) Would be taken against an individual, or if the action, though not taken against an individual, turns

on whether an individual has committed 1,,vrongdoing;

(2) Involves significant personnel failures where the NRC has requested that the individual(s) involved

be present at the conference;

(3) Is based on the findings of an NRC Office ofinvestigations report that has not been publicly

disclosed; or

(4) Involves safeguards information, Privacy Act information, or information which could be considered

proprietary;

In addition, conferences will not normally be open to the public if:

(5) The conference involves medical misadministrations or overexposures and the conference cannot be

conducted without disclosing the exposed individual's name; or

(6) The conference will be conducted by telephone or the conference will be conducted at a relatively r

small licensee's facility.

Enclosure 2

Notwithstanding meeting any of these criteria, a conference may still be open if the conference involves

issues related to an ongoing adjudicatory proceeding with one or more intervenors or where the

evidentiary basis for the conference is a matter of public record, such as an adjudicatory decision by the

Department of Labor. In addition, notwithstanding the above normal criteria for opening or closing

conferences, with the approval of the Executive Director for Operations, conferences may either be open

or closed to the public after balancing the benefit of the public's observation against the potential impact

on the agency'.s decision-m~ng process in a particular case.

The NRC will notify the licensee that the conference will be open to public observation. Consistent with

the agency's policy on open meetings, "Staff Meetings Open to Public," published September 20, 1994

(59 FR 48340), the NRC intends to announce open conferences normally at least 10 working days in

advance of conferences through (1) notices posted in the Public Document Room, (2) a toll-free

telephone recording at 800-952-9674, (3) a toll-free electronic bulletin board at 800-952-9676, and on

the World Wide Web at the NRC Office of Enforcement homepage (www.nrc.gov/OE). In addition, the

NRC will also issue a press release and notify appropriate State liaison officers that a predecisional

enforcement conference has been scheduled and that it is open to public observation.

The public attending open conferences may observe but may not participate in the conference. It is noted

that the purpose of conducting open conferences is not to maximize public attendance, but rather to

provide the public with opportunities to be informed of NRC activities consistent with the NRC's ability

to exercise its regulatory and safety responsibilities. Therefore, members of the public will be allowed

access to the NRC regional offices to attend open enforcement conferences in accordance with the

"Standard Operating Procedures for Providing Se~urity Support For NRC Hearings and Meetings,"

published November 1, 1991 (56 FR 56251). These procedures provide that visitors may be subject to

personnel screening, that signs, banners, posters, etc., not larger than 18" be permitted, and that

disruptive persoris may be removed. The open conference will be terminated if disruption interferes with

a successful conference. NRC's Predecisional Enforcement Conferences (whether open or closed)

normally will be held at the NRC's regional offices or in NRC Headquarters Offices and not in the

vicinity of the licepsee's facility ..

For a case in which an NRC Office of Investigations (OI) report finds that discrimination as defined

under 10 CFR 50.7 (or similar provisions in Parts 30, 40, 60, 70, or 72) has occurred, the OI report may

be made public, subject to withholding certain information (i.e., after appropriate redaction), in which

case the associated predecisional enforcement conference will normally be open to public observation.

In a conference where a particular individual is being considered potentially responsible for the

discrimination, the conference will remain closed. In either case (i.e., whether the conference is open or

closed), the employee or former employee who was the subject of the alleged discrimination (hereafter

referred to as "complainant") will normally be provided an opportunity to participate in the predecisional

enforcement conference with the licensee/employer. This participation will normally be in the form of a

complainant statement and comment on the licensee's presentation, followed in turn by an opportunity

for the licensee to respond to the complainant's presentation. In cases where the complainant is unable to

attend in person, arrangements will be made for the complainant's participation by telephone or an

opportunity given for the complainant to submit a written response to the licensee's presentation. If the

licensee chooses to forego an enforcement conference and, instead, responds to the NRC's findings in

writing, the complainant will be provided the opportunity to submit written comments on the licensee's

response. For cases involving potential discrimination by a contractor or vendor to the licensee, any

associated predecisional enforcement conference with the contractor or vendor would be handled

similarly. These arrangements for complainant participation in the predecisional enforcement conference

are not to be conducted or viewed in any respect as an adjudicatory hearing. The purpose of the

complainant's participation is to provide information to the NRC to assist it in its enforcement

deliberations.

A predecisional enforcement conference may not need to be held in cases where there is a full

adjudicatory record before the Department of Labor. If a conference is held in such cases, generally the

conference will focus on the licensee's corrective action. As with discrimination cases based on OI

investigations, the complainant may be allowed to participate.

,

Members of the public attending open conferences will be reminded that (1) the apparent violations

discussed at predecisional enforcement conferences are subject to further review and may be subject to

change prior to any resulting enforcement action and (2) the statements of views or expressions of

opinion made by NRC employees at predecisional enforcement conferences, or the lack thereof, are not

intended to repres~nt final determinations or beliefs.

When needed to protect the public health and safety or common defense and security, escalated

enforcement action, such as the issuance of an immediately effective order, will be taken before the

conference. In these cases, a conference may be held after the escalated enforcement action is taken.

VI. ENFORCEMENT ACTIONS

This section describes the enforcement sanctions available to the NRC and specifies the conditions under

which each may be used. The basic enforcement sanctions are Notices of Violation, civil penalties, and

orders of various types. As discussed further in Section VI.D, related administrative actions such as

Notices ofNonconformance, Notices of Deviation, Confirmatory Action Letters, Letters of Reprimand,

and Demands for Information are used to supplement the enforcement program. In selecting the

enforcement sanctions or administrative actions, the NRC will consider enforcement actions taken by

other Federal or State regulatory bodies having concurrent jurisdiction, such as jn transportation matters.

Usually, whenever a violation ofNRC requirements of more than a minor concern is identified,

enforcement action is taken. The nature and extent of the enforcement action is intended to reflect the

seriousness of the violation involved. For the vast majority of violations, a Notice of Violation or a

Notice ofNonconformance is the normal action.

A. Notice of Violation

A Notice of Violation is a written notice setting forth one or more violations of a legally binding

requirement. The Notice of Violation normally requires the recipient to provide a written statement

describing (1) the reasons for the violation or, if contested, the basis for disputing the violation;

(2) corrective steps that have been taken and the results achieved; (3) corrective steps that will be taken

to prevent recurrence; and (4) the date when full compliance will be achieved. The NRC may waive all

or portions of a written response to the extent relevant information has already been provided to the

NRC in writing or documented in an NRC inspection report. The NRC may require responses to Notices

of Violation to be under oath. Normally, responses under oath will be required only in connection with

Severity Level I, II, or III violations or orders.

The NRC uses the Notice of Violation as the usual method for formalizing the existence of a violation.

Issuance of a Notice of Violation is normally the only enforcement action taken, except in cases where

the criteria for issuance of civil penalties and orders, as set forth in Sections VI.B and VI.C, respectively,

are met. However, special circumstances regarding the violation findings may warrant discretion being

exercised such that the NRC refrains from issuing a Notice of Violation. (See Section VII.B, "Mitigation

of Enforcement Sanctions.") In addition, licensees are not ordinarily cited for violations resulting from

matters not within their control, such as equipment failures that were not avoidable by reasonable

licensee quality assurance measures or management controls. Generally, however, licensees are held

responsible for the acts of their employees. Accordingly, this policy should not be construed to excuse

personnel errors.

B. Civil Penalty

A civil penalty is a monetary penalty that may be imposed for violation of (1) certain specified licensing

provisions of the Atomic Energy Act or supplementary NRC rules or orders; (2) any requirement for

which a license may be revoked; or (3) reporting requirements under section 206 of the Energy

Reorganization Act. Civil penalties are designed to deter future violations both by the involved licensee

as well as by other licensees conducting similar activities and to emphasize the need for licensees to

identify violations and take prompt comprehensive corrective action.