MONTHYEARIR 05000250/20240032024-11-13013 November 2024 Integrated Inspection Report - 05000250/2024003 & 05000251/2024003 & Notice of Violation L-2024-188, Supplement to License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-11-12012 November 2024 Supplement to License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis L-2024-187, Supplement to the Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-11-12012 November 2024 Supplement to the Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles ML24305A1482024-11-0606 November 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 ML24276A2162024-11-0101 November 2024 Request for Withholding Information from Public Disclosure L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24291A2882024-10-24024 October 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24276A2302024-10-16016 October 2024 Westinghouse Topical Report – Request for Withholding Information from Public Disclosure ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) IR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24269A1292024-09-24024 September 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24260A2262024-09-18018 September 2024 NRC Examination Results Summary - Examination Reports: 05000250/2024301 and 05000251/2024301 ML24158A0052024-09-17017 September 2024 Completion of Subsequent License Renewal Site Specific Environmental Review and Modification to Subsequent Renewed Facility Operating Licenses L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24207A0342024-09-13013 September 2024 – Exemption from Certain Requirements of 10 CFR 50.46 for Use of Axiom Fuel Rod Cladding – Letter ML24256A1132024-09-13013 September 2024 Regulatory Audit Summary Related to the Review of Regarding the Updated Spent Fuel Pool Criticality Safety Analysis License Amendment Request IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 ML24234A0062024-08-22022 August 2024 Project Manager Assignment L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000250/LER-2024-002-01, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal ML24173A1902024-06-28028 June 2024 Withdrawal of an Amendment Request ML24159A2652024-06-26026 June 2024 Correction of Safety Evaluation for Issuance of Amendment Nos. 298 & 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24135A0942024-05-0909 May 2024 Periodic Update to the Updated Final Safety Analysis Report L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report ML24127A1862024-05-0909 May 2024 Request for Withholding Information from Public Disclosure 2024-09-25
[Table view] |
Text
April 7, 2022 L-2022 - 065
U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555-00001
Re: Turkey Point Unit 4 Docket No. 50-251 Subsequent License Renewal License Condition Completion Notification
In accordance with Turkey Point Unit 4 Subsequent Renewed License No. DPR-41, Subsequent License Renewal License Conditions, Section J.3 (See attached), Florida Power
& Light Company (FPL) notifies the Nuclear Regulatory Commission (NRC) herein that Turkey Point Unit 4 has completed the replacement of a portion of the existing containment spray system carbon steel piping with stainless steel piping during the 2019, 2020 & 2022 Turkey Point Unit 4 Refueling Outages.
The scope of replacement was the carbon steel piping for the two containment spray piping headers (4A and 48) at penetrations P-19A and P-198 to a minimum 65 ft plant elevation inside containment. Condition Report AR# 2340249 documents the elevation of the air-to borated water interface inside the piping. Inspections revealed that the air-to -bo rated-water interface inside the A header piping was located approximately between the 54 and 69 ft elevation. The air-to-borated-water interface inside the 8 header piping was located approximately between the 63 and 75 ft elevation. The actual piping cut line for Containment Spray Piping header 4A was changed to approximately the 71 ft elevation and for the 48 header was changed to the 83 ft elevation to ensure the replaced stainless steel piping provides additional margin to the air-to bo rated-water interface inside the piping.
FPL confirms that any of the remaining carbon steel piping will not be internally exposed to stagnant borated water during the subsequent period of extended operation.
Should there be any questions concerning this report, please contact Mr. Robert J. Hess, Licensing Manager, at 305-246-4112.
Licensing Manager Turkey Point Nuclear Plant
Attachment cc: Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant
Florida Power & Lig ht Com pan y 9760 S.W. 344 1" Street Homestead, FL 33035 L-2022- 065 Attachment
Referenced Section Attached Turkey Point Unit 4 Subsequent Renewed License No. DPR-41, Subsequent License Renewal License Conditions, Section J.3 Pages 7 and 8
7
- 2. The risk assessment approach and methods, shall be acceptable to the NRG, be based on the as-built, as-operated, and maintained plant, and reflect the operating experience of the plant as specified in RG 1.200. Methods to assess the risk from extending the completion times must be PRA methods accepted as part of this license amendment, or other methods approved by the NRG for generic use. If the licensee wishes to change its methods, and the change is outside the bounds of this license condition, the licensee will seek prior NRG approval via a license amendment.
J. Subsequent License Renewal License Conditions
- 1. The information in the Final Safety Analysis Report (FSAR) supplement submitted pursuant to 10 CFR 54.21(d), as revised during the subsequent license renewal application review process, and FPL commitments as listed in Appendix A of the "Safety Evaluation Report Related to the Subsequent License Renewal of Turkey Point Generating Units 3 and 4," dated July 22, 2019, are collectively the "Subsequent License Renewal FSAR Supplement." This Supplement is henceforth part of the FSAR, which will be updated in accordance with 10 CFR 50.71(e). As such, FPL may make changes to the programs, activities, and commitments described in the Subsequent License Renewal FSAR Supplement, provided FPL evaluates such changes pursuant to the criteria set forth in 10 CFR 50.59, "Changes, Tests, and Experiments," and otherwise complies with the requirements in that section.
- 2. The Subsequent License Renewal FSAR Supplement, as defined in renewed license condition (J)(1) above, describes programs to be implemented and activities to be completed prior to the subsequent period of extended operation, which is the period following the April 10, 2033, expiration of the initial renewed license.
- a. FPL shall implement those new programs and enhancements to existing programs no later than 6 months before the subsequent period of extended operation.
- b. FPL shall complete those activities by the 6-month date prior to the subsequent period of extended operation or by the end of the last refueling outage before the subsequent period of extended operation, whichever occurs later.
- c. FPL shall notify the NRG in writing within 30 days after having accomplished item (2)(a) above and include the status of those activities that have been or remain to be completed in item (2)(b) above.
- 3. FPL shall complete the replacement of a portion of the existing containment spray system carbon steel piping with stainless steel piping by December 1, 2024, so that any remaining carbon steel piping will not normally be internally exposed to borated water during the subsequent period of extended operation. The scope of replacement is the carbon steel piping from the stainless steel to the carbon steel dissimilar metal weld for the two containment spray piping headers (4A and 48) at penetrations P-19A and P-198 to a minimum plant elevation of 65 feet inside containment. FPL shall notify the NRG in writing within 60 days following completion of the refueling outage during which the piping replacement is completed. The notification will confirm the elevation of
Subsequent Renewed License No. DPR-41 8
the air-to-borated water interface inside the piping, and confirm that the installation of the stainless steel piping exceeds this elevation.
- 4. This subsequent renewed license is effective as of the date of issuance, and shall expire at midnight April 10, 2053.
FOR THE NUCLEAR REGULATORY COMMISSION
IRA/
Ho K. Nieh, Director Office of Nuclear Reactor Regulation
Attachments:
Appendix A - Technical Specifications for Unit 4 Appendix B - Environmental Protection Plan
Date of Issuance: December 4, 2019
Subsequent Renewed License No. DPR-41