Corrected Monthly Operating Rept for Jul 1985
ML20135B041
Person / Time
Site: Salem PSEG icon.png
Issue date: 07/31/1985
From: Ronafalvy J
Public Service Enterprise Group
To:
Shared Package
ML20135B034 List:
References
NUDOCS 8509100383
Download: ML20135B041 (1)


Text

- . _ _ __ _ -.

t' OPERATING DATA REPORT Docket No.50-272 Date August 10, 1985 Telephone 935-6000 l Completed by J. P. Ronafalvy. Extension 4455 I Operating Status Corrected copy

1. Unit Name Salem No. 1 Notes
2. Reporting. Period July 1985
3. Licensed Thermal Power (MWt) 3338
4. Nameplate Rating (Gross MWe) IT70
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (Gross MWe)1124
7. Maximum' Dependable Capacity (Net MWe) 1079
8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason N/A
9. Power Level to Which Restricted, if any (Net MWe) N/A
10. Reasons for Restrictions, if any N/A This Month Year to Date Cumulative 11.. Hours in Reporting Period 744 5087 70896 12.HNo. of Hrs. Reactor was Critical 744 5069.6 40893.1 13.-Reactor-Reserve Shutdown Hrs.- 0 0 3088.4
14. Hours Generator On-Line 744 5066.7 39225.3
15. Unit Reserve Shutdown Hours 0 0
16. Gross' Thermal Energy Generated (MWH) 2488994 16855385 119623382
17. Gross Elec. Energy Generated (BOGI) 833550 5740870 39656920
18. Net Elec. Energy Generated (MWH) 800369 5518268 37616250
19. Unit Service Factor 100 99.6 55.3
20. Unit Availability Factor 100 99.6 55.3
21. Unit Capacity Factor (using MDCJNet) 99.7 100.5 49.2
22. Unit Capacity Factor (using DER Net) 99.7 99.5 48.7
23. Unit Forced Outage Rate 0 .4 30.2
24. Shutdowns ' scheduled over next 6 months - (type, date and duration of each)

N/A

25. If shutdown at end of Peport Period, Estimated Date of Startup:

N/A

26. Units in Test Status (Prior to Commercial Operation) :

Forecast Achieved Initial Criticality 9/30/76 12/11/76 Initial Electricity- 11/1/76 12/25/76 Commercial Operation 12/20/76 6/30/77 8-1-7.R2 Page of j fhl DOC 2 e