Tech Spec Point Beach, 3.5 Emergency Core Cooling System (ECCS)
ML032671361
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/05/2003
From:
NRC/NRR/DLPM
To:
References
Download: ML032671361 (3)


Text

ECCS - Operating 3.5.2 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS - Operating LCO 3.5.2 Two ECCS trains shall be OPERABLE.


NOTE----------------------------------------

In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to perform pressure isolation valve testing per SR 3.4.14.1.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One ECCS train A.1 Restore train to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable. OPERABLE status.

B. Required Action and B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND B.2 Be in MODE 4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify each ECCS manual, power operated, and 31 days automatic valve in the flow path, that is not locked, sealed, or otherwise secured in position, is in the correct position.

I SR 3.5.2.2 Verify ECCS piping is full of water. 31 days (continued)

Point Beach 3.5.2-1 Unit 1 - Amendment No. 286, 209 Unit 2 - Amendment No. 28e, 214

ECCS - Operating 3.5.2 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY 4

I SR 3.5.2.3 Verify each ECCS pump's developed head at the In accordance test flow point is greater than or equal to the with the required developed head. Inservice Testing Program t

l SR 3.5.2.4 Verify each ECCS automatic valve in the flow 18 months path that Is not locked, sealed, or otherwise secured in position, actuates to the correct position on an actual or simulated actuation signal.

I SR 3.5.2.5 Verify each ECCS pump starts automatically on 18 months an actual or simulated actuation signal.

I SR 3.5.2.6 Verify, by visual inspection, each ECCS train 18 months containment sump suction inlet is not restricted by debris and the suction Inlet debris screens show no evidence of structural distress or abnormal corrosion.

Point Beach 3.5.2-2 Unit 1 - Amendment No. 206, 209 Unit 2 - Amendment No. 2a@, 214

FCr~. - Shiftdnwn 3.5.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.3.1 The following SRs are applicable for all In accordance equipment required to be OPERABLE: with applicable SRs SR 3.5.2.1 SR 3.5.2.4 SR 3.5.2.2 SR 3.5.2.5 I SR 3.5.2.3 SR 3.5.2.6 Point Beach 3.5.3-2 Unit 1 - Amendment No. 296, 209 Unit 2 - Amendment No. i@l, 214