Tech Spec Page for Amendments 230 and 235 TSTF- 491, Revision 2, Removal of Main Steam and Feedwater Valve Isolation Times Technical Specification 3.7.2
ML073180315
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 11/16/2007
From:
NRC/NRR/ADRO/DORL/LPLIII-1
To:
Cushing, Jack /NRR/DORL/LPL3-1, 415-1424
References
TAC MD6079, TAC MD6080
Download: ML073180315 (1)


Text

MSIVs and Non-Return Check Valves 3.7.2 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. (continued) C.3 Verify MSIV and non- Once per 7 days return check valve in the affected flowpath are closed and the MSIV is de-activated.

D. Required Action and D.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition C not AND met.

D.2 Be in MODE 4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.2.1 -------------------- NOTE -------------------------

Only required to be performed in MODE 1.

Verify closure time of each MSIV is within limits. In accordance with the Inservice Testing Program SR 3.7.2.2 -------------------- NOTE---------------

Only required to be performed in MODE 1.

Verify each MSIV actuates to the isolation 18 months position on an actual or simulated actuation signal.

)

SR 3.7.2.3 Verify each main steam non-return check valve In accordance can close, with the Inservice Testing Program Point Beach 3.7.2-2 Unit 1 - Amendment No. 230 Unit 2 - Amendment No. 235