Containment Isolation Valves 3.6.3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D.
Required Action and D. 1 Be in MODE 3.
6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met.
AND D.2 Be in MODE 5.
36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.3.1 Deleted SR 3.6.3.2
NOTE Valves and blind flanges in high radiation areas may be verified by use of administrative controls.
Verify each containment isolation manual valve 31 days and blind flange that is located outside containment and not locked, sealed, or otherwise secured and required to be closed during accident conditions is closed, except for containment isolation valves that are open under administrative controls.
(continued)
Point Beach 3.6.3-4 Unit 1 - Amendment No. 231 Unit 2 - Amendment No. 236