MONTHYEARNL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 NL-23-0295, Reply to a Notice of Violation; EA-22-1012023-05-0101 May 2023 Reply to a Notice of Violation; EA-22-101 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0213, Inservice Inspection Program Owner'S Activity Report for Outage 1R312023-03-21021 March 2023 Inservice Inspection Program Owner'S Activity Report for Outage 1R31 NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0080, Response to Request for Additional Information (RAI) Related to Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.02023-02-0202 February 2023 Response to Request for Additional Information (RAI) Related to Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0 NL-23-0008, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 3.4.10, Pressurizer Safety Valves to Decrease Low Side Setpoint Tolerance Limiting.2023-01-17017 January 2023 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 3.4.10, Pressurizer Safety Valves to Decrease Low Side Setpoint Tolerance Limiting. NL-23-0011, Update to Supporting Documentation Regulatory Conference EA-22-101. Cover Letter Only2023-01-0505 January 2023 Update to Supporting Documentation Regulatory Conference EA-22-101. Cover Letter Only NL-22-0799, License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52022-12-20020 December 2022 License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 NL-22-0897, Supplement to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A,2022-12-0909 December 2022 Supplement to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, NL-22-0887, Cycle 32 Core Operating Limits Report2022-11-21021 November 2022 Cycle 32 Core Operating Limits Report NL-22-0884, Response to NRC Inspection Report 05000348/2022440 and 05000364/2022440 EA-22-1012022-11-17017 November 2022 Response to NRC Inspection Report 05000348/2022440 and 05000364/2022440 EA-22-101 NL-20-0170, Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC2022-10-14014 October 2022 Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC NL-22-0756, Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.02022-09-30030 September 2022 Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0 NL-22-0289, License Amendment Request to Revise Technical Specification 4.3 Fuel Storage to Correct Tabulated Values from the Associated Spent Fuel Pool (SFP) Criticality Analysis2022-09-21021 September 2022 License Amendment Request to Revise Technical Specification 4.3 Fuel Storage to Correct Tabulated Values from the Associated Spent Fuel Pool (SFP) Criticality Analysis NL-22-0608, Interim 10 CFR 21.21(a)(2) Report Regarding Framatome Supplied Siemens Medium Voltage Circuit Breakers2022-08-17017 August 2022 Interim 10 CFR 21.21(a)(2) Report Regarding Framatome Supplied Siemens Medium Voltage Circuit Breakers NL-22-0552, Inservice Inspection Program Owner'S Activity Report for Outage 2R282022-07-28028 July 2022 Inservice Inspection Program Owner'S Activity Report for Outage 2R28 NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20212022-07-14014 July 2022 Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 NL-22-0223, License Amendment to Revise Technical Specification 3.4.10, Pressurizer Safety Valves to Decrease Low Side Setpoint Tolerance Limiting Condition for Operation (LCO) Value2022-06-30030 June 2022 License Amendment to Revise Technical Specification 3.4.10, Pressurizer Safety Valves to Decrease Low Side Setpoint Tolerance Limiting Condition for Operation (LCO) Value NL-22-0361, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 5.5.17, Containment Leakage Rate Testing Program to Increase Calculated Peak.2022-06-20020 June 2022 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 5.5.17, Containment Leakage Rate Testing Program to Increase Calculated Peak. NL-22-0362, Southern Nuclear Operating Company, Inc. - Foreign Ownership, Control, or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2022-06-0101 June 2022 Southern Nuclear Operating Company, Inc. - Foreign Ownership, Control, or Influence Five-Year Renewal Filing and NRC Facility Clearance Update NL-22-0388, Cycle 29 Core Operating Limits Report2022-05-31031 May 2022 Cycle 29 Core Operating Limits Report NL-22-0344, Annual Radiological Environmental Operating Reports for 20212022-05-10010 May 2022 Annual Radiological Environmental Operating Reports for 2021 NL-22-0340, Response to Request for Additional Information Related to Request for License Amendment to Relocate Augmented Piping Inspection Program Details from Technical2022-05-10010 May 2022 Response to Request for Additional Information Related to Request for License Amendment to Relocate Augmented Piping Inspection Program Details from Technical NL-22-0240, SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations2022-03-31031 March 2022 SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations 2024-01-11
[Table view] |
Text
L M. Stinson (Mike) Southern Nuclear Vice President Operating Company, Inc.
40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.5181 Fax 205.992.0341 S %OUTHERN April 1, 2004 COMPANY Energy to Serve Your Wo rld S Docket No.: 50-364 NL-04-0537 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant - Unit 2 Supplement to Request for Relaxation of the First Revised NRC Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors Ladies and Gentlemen:
In a letter dated March 25, 2004, Southern Nuclear Operating Company (SNC) requested relaxation of an inspection coverage requirement for specific penetration nozzles at Unit 2 of the Farley Nuclear Plant (FNP). This request was made in accordance with the requirements of Section IV.F of the February 20, 2004 Commission First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors.
In a March 31, 2004 telephone call with the staff, SNC was asked to supplement this relaxation request by explicitly committing to a contingency regarding crack growth analysis. This contingency was contained in the April 25, 2003 NRC letter which approved certain requested relaxations to the original Order and formed the basis for SNC's inspection plan for the FNP Unit 2 reactor pressure vessel (RPV) head.
Accordingly, SNC commits that if the NRC staff finds that the crack growth formula in industry report MRP-55 is unacceptable, SNC shall revise its analysis justifying relaxation of the Order within 30 days after NRC informs SNC of an NRC-approved crack growth formula. If SNC's revised analysis shows that the crack growth acceptance criteria are exceeded prior to the end of the current operating cycle, the relaxation is rescinded and SNC shall, within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, submit to the NRC written justification for continued operation. If the revised analysis shows that the crack growth acceptance criteria are exceeded during the subsequent operating cycle, SNC shall, within 30 days, submit the revised analysis for NRC review. If the revised analysis shows that the crack growth acceptance criteria are not exceeded during either the current operating cycle or the subsequent operating cycle, SNC shall, within 30 days, submit a letter to the NRC confirming that its analysis has been revised.
Note that no subsequent operating cycle is planned for the FNP Unit 2 RPV head.
Replacement of the RPV head is scheduled at the next FNP Unit 2 refueling outage, in fall 2005.
U. S. Nuclear Regulatory Commission NL-04-0537 Page 2 SNC requests approval of the requested relaxation by April 2, 2004 in order to support the planned re-installation of the FNP Unit 2 RPV head.
If you have any questions, please advise.
Mr. L. M. Stinson states he is a Vice President of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and to the best of his knowledge and belief, the facts set forth in this letter are true.
Respectfully submitted, SOUTHERN NUCLEAR OPERATING COMPANY L. M. Stinson
,Vorn to andsubscribedbefor me this / day of e*~, 2004.
-- .I-- ~ ~ _y _
NoaryP lic
'H~M commiission expires: $4 LMS/DWD/daj cc: Southern Nuclear Operating Company Mr. J. B. Beasley, Jr., Executive Vice President Mr. D. E. Grissette, General Manager - Plant Farley RTYPE: CFA04.054; LC# 14003 U. S. Nuclear Regulatorv Commission Mr. L. A. Reyes, Regional Administrator (2 copies)
Mr. S. E. Peters, NRR Project Manager - Farley Mr. C. A. Patterson, Senior Resident Inspector - Farley Document Control Desk (3 copies)