ML050690417
ML050690417 | |
Person / Time | |
---|---|
Site: | Seabrook |
Issue date: | 02/24/2005 |
From: | Conte R NRC/RGN-I/DRS/OSB |
To: | Roy D Florida Power & Light Energy Seabrook |
Cont R | |
Shared Package | |
ML032810101 | List: |
References | |
Download: ML050690417 (3) | |
Similar Documents at Seabrook | |
---|---|
Category:Letter
MONTHYEARIR 05000443/20240032024-10-30030 October 2024
[Table view]Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 05000443/LER-2024-001, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-038, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-037, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) 2024-09-25 Category:License-Operator MONTHYEARML24022A0652024-01-22022 January 2024
[Table view]Senior Reactor and Reactor Operator Initial License Examinations ML23227A0892023-07-18018 July 2023 Final QA Related Forms ML23356A1592023-03-17017 March 2023 Final QA Related Forms SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters ML22173A0572022-06-22022 June 2022 Senior Reactor and Reactor Operator Initial License Examinations L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment ML21307A2892021-11-0303 November 2021 September 8, 2021, NRC Generic Fundamentals Examination Results for Seabrook Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20254A2722020-09-10010 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3).pdf ML20254A1282020-09-10010 September 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML21025A4052020-09-0707 September 2020 Form ES-401-6 (Folder 1) ML20267A3982020-09-0707 September 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML20267A3992020-09-0707 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20268A3222020-09-0707 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20268C1972020-09-0707 September 2020 Miscellaneous Exam Material (Folder 1) ML21025A4032020-09-0707 September 2020 Final QA Related Forms (Folder 1) ML21026A2282020-09-0707 September 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML20268B4372020-08-10010 August 2020 Handouts to Applicants (Folder 3) ML20267A3922020-06-0909 June 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20267A1582020-06-0303 June 2020 Draft Written Examination (Folder 2) ML19352E3032019-12-17017 December 2019 Senior Reactor and Reactor Operator Initial License Examinations: Seabrook Station Unit No. 1 ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19045A3702019-02-12012 February 2019 March 2019 GFE Cover Letter Ri SBK-L-18082, Response to RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations2018-04-26026 April 2018 Response to RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations ML18058A0592018-02-27027 February 2018 Initial Operator Licensing Written Examination Approval - Seabrook Station, Unit 1 ML18047A2502018-02-15015 February 2018 Initial Operator Licensing Operating Test Approval - Seabrook Station Unit No. 1 ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 SBK-L-17151, Miscellaneous Exam Material (Folder 1)2017-09-22022 September 2017 Miscellaneous Exam Material (Folder 1) ML18120A2362017-09-22022 September 2017 Miscellaneous Exam Material (Folder 1) ML17180A2242017-06-28028 June 2017 Senior Reactor and Reactor Operator Initial License Examinations - Seabrook Station, Unit No. 1 SBK-L-17086, NRC Form 536 Operator Licensing Examination Data2017-05-19019 May 2017 NRC Form 536 Operator Licensing Examination Data ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 SBK-L-16121, Response to RIS-16-09, Preparation and Scheduling of Operator Licensing Examinations2016-07-20020 July 2016 Response to RIS-16-09, Preparation and Scheduling of Operator Licensing Examinations ML16194A0092016-07-11011 July 2016 NRC Generic Fundamentals Examination Results for Seabrook Station (Cover Letter, Enclosures Withheld from Public) ML15274A2802015-10-0101 October 2015 Requalification Program Inspection - Seabrook Station, Unit 1 ML15119A3062015-04-28028 April 2015 Final Qa/Related Forms (Folder 1) ML15119A3102015-04-0202 April 2015 Miscellaneous Exam Material (Folder 1) ML15103A5662015-03-23023 March 2015 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML15098A0592015-03-23023 March 2015 Seabrook - Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15098A1012015-03-23023 March 2015 Handouts to Applicants (Folder 3) ML15098A0552015-03-19019 March 2015 Final Outlines (Folder 3) ML15076A0912015-03-17017 March 2015 Initial Operator Licensing Written Examination Approval (Seabrook Station, Unit 1) ML15098A1262015-03-0909 March 2015 Final Operating Exam (Sections a, B and C) (Folder 3) ML15103A5652015-02-20020 February 2015 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML15103A5692015-02-0505 February 2015 Draft Written Exam (Folder 2) ML15104A0692015-01-22022 January 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15103A5672014-12-22022 December 2014 Draft Outlines (Folder 2) ML13255A0022013-09-10010 September 2013 Requalification Program Inspection - SB 1 IR 05000443/20133012013-08-14014 August 2013 Er 05000443-13-301; 7-15-2013 to 7-24-2013; Seabrook Station, Unit No. 1 Initial Operator Licensing Examination Report ML13295A5462013-07-31031 July 2013 Seabrook - Final Qa/Related Forms (Folder 1) 2024-01-22 Category:Part 55 Examination Related Material MONTHYEARML24022A0652024-01-22022 January 2024
[Table view]Senior Reactor and Reactor Operator Initial License Examinations ML23227A0892023-07-18018 July 2023 Final QA Related Forms ML23356A1592023-03-17017 March 2023 Final QA Related Forms SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters ML22173A0572022-06-22022 June 2022 Senior Reactor and Reactor Operator Initial License Examinations L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20254A2722020-09-10010 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3).pdf ML20254A1282020-09-10010 September 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML20268C1972020-09-0707 September 2020 Miscellaneous Exam Material (Folder 1) ML21025A4032020-09-0707 September 2020 Final QA Related Forms (Folder 1) ML21026A2282020-09-0707 September 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML21025A4052020-09-0707 September 2020 Form ES-401-6 (Folder 1) ML20267A3982020-09-0707 September 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML20268A3222020-09-0707 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20267A3992020-09-0707 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20268B4372020-08-10010 August 2020 Handouts to Applicants (Folder 3) ML20267A3922020-06-0909 June 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20267A1582020-06-0303 June 2020 Draft Written Examination (Folder 2) ML19352E3032019-12-17017 December 2019 Senior Reactor and Reactor Operator Initial License Examinations: Seabrook Station Unit No. 1 ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 SBK-L-18082, Response to RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations2018-04-26026 April 2018 Response to RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations ML18058A0592018-02-27027 February 2018 Initial Operator Licensing Written Examination Approval - Seabrook Station, Unit 1 ML18047A2502018-02-15015 February 2018 Initial Operator Licensing Operating Test Approval - Seabrook Station Unit No. 1 ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18120A2362017-09-22022 September 2017 Miscellaneous Exam Material (Folder 1) SBK-L-17151, Miscellaneous Exam Material (Folder 1)2017-09-22022 September 2017 Miscellaneous Exam Material (Folder 1) ML17180A2242017-06-28028 June 2017 Senior Reactor and Reactor Operator Initial License Examinations - Seabrook Station, Unit No. 1 SBK-L-17086, NRC Form 536 Operator Licensing Examination Data2017-05-19019 May 2017 NRC Form 536 Operator Licensing Examination Data ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 SBK-L-16121, Response to RIS-16-09, Preparation and Scheduling of Operator Licensing Examinations2016-07-20020 July 2016 Response to RIS-16-09, Preparation and Scheduling of Operator Licensing Examinations ML16194A0092016-07-11011 July 2016 NRC Generic Fundamentals Examination Results for Seabrook Station (Cover Letter, Enclosures Withheld from Public) ML15274A2802015-10-0101 October 2015 Requalification Program Inspection - Seabrook Station, Unit 1 ML15119A3062015-04-28028 April 2015 Final Qa/Related Forms (Folder 1) ML15119A3102015-04-0202 April 2015 Miscellaneous Exam Material (Folder 1) ML15098A1012015-03-23023 March 2015 Handouts to Applicants (Folder 3) ML15103A5662015-03-23023 March 2015 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML15098A0592015-03-23023 March 2015 Seabrook - Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15098A0552015-03-19019 March 2015 Final Outlines (Folder 3) ML15076A0912015-03-17017 March 2015 Initial Operator Licensing Written Examination Approval (Seabrook Station, Unit 1) ML15098A1262015-03-0909 March 2015 Final Operating Exam (Sections a, B and C) (Folder 3) ML15103A5652015-02-20020 February 2015 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML15103A5692015-02-0505 February 2015 Draft Written Exam (Folder 2) ML15104A0692015-01-22022 January 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15103A5672014-12-22022 December 2014 Draft Outlines (Folder 2) ML13255A0022013-09-10010 September 2013 Requalification Program Inspection - SB 1 IR 05000443/20133012013-08-14014 August 2013 Er 05000443-13-301; 7-15-2013 to 7-24-2013; Seabrook Station, Unit No. 1 Initial Operator Licensing Examination Report ML13295A5462013-07-31031 July 2013 Seabrook - Final Qa/Related Forms (Folder 1) ML13207A1472013-07-22022 July 2013 June 5, 2013, NRC Generic Fundamentals Examination Results for Seabrook Station (Cover Letter) ML13206A3502013-07-11011 July 2013 Seabrook - Final Operating Exam (Section a, B, and C) (Folder 3) 2024-01-22 |
Text
February 24, 2005 Mr. Daniel G. Roy Manager, Nuclear Training FPL Energy Seabrook, LLC Seabrook Station P.O. Box 300 Seabrook, NH 03874
Dear Mr. Roy:
The purpose of this letter is to inform you of the individual examination results for your applicants on the initial written retake examination conducted on January 28, 2005, and the walkthrough (overall) and/or simulator operating tests administered January 31 to February 4, 2005 at your facility. This meets the intent of section E.1 of the Examiner Standards (ES 501) in NUREG 1021.
Ten individuals were administered the examination and all passed. This information is considered to be "proprietary" in accordance with 10 CFR 2.390 and it supplements the information contained in the related examination report for your facility which will be issued shortly. is the completed ES-501-2, Power Plant Licensing Examination Results Summary, and is a summary of overall examination results. contains the individual results ES-303-1 and 303-2, Operator License Examination Report, for the applicants. Contained therein are the deficiencies noted for each applicant. In accordance with your Systems Approach to Training (SAT) Program, we expect that you will review these results and provide appropriate remedial training for the individual independent of the overall pass status. The applicant has authorized the release of this information to your facility by signing Block 19A of NRC Form 398. is a copy of the licenses.
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5183.
Sincerely,
/RA/
Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket No. 50-443
Mr. Roy License No. NPF-86
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc w/licenses:
M. E. Warner, Site Vice President
Mr. Roy Distribution: w/o enclosures:
Master Exam File DOCUMENT NAME: E:\Filenet\ML050690417.wpd ADAMS PACKAGE: ML032810101 SISP Review: ____RJC_________(Reviewers Initials)
After declaring this document An Official Agency Record it will without enclosures be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OSB RI/DRS/OSB RI/DRS/OSB NAME CJBixler CJB STBarr STB RJConte RJC DATE 02/11/05 02/24/05 02/24/05 OFFICIAL RECORD COPY