Cycle 11 Startup Test Report Summary
ML051670235
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 06/08/2005
From: Landahl S
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA05-051
Download: ML051670235 (11)


Text

ExekIn .

Exelon Generation Company. LLC LaSalle County Station www.exeloncorp.com Nuclear 2601 North 21"Road Marseilles. IL61341-9757 RA05-051 June 8, 2005 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 LaSalle County Station, Unit 2 Facility Operating License No. NPF-18 NRC Docket No. 50-374

Subject:

LaSalle 2 Cycle 11 Startup Test Report Summary Enclosed for your information is the LaSalle County Station (LCS) Unit 2 Cycle 11 Startup Test Report. This report is submitted in accordance with Technical Requirements Manual Section 5.0.b.

LaSalle County Station Unit 2 Cycle 11 began commercial operation on March 16, 2005, following a refueling and maintenance outage. The Unit 2 Cycle 11 core loading consisted of 286 fresh General Electric GE-14 fuel bundles and 478 reload bundles manufactured by Framatome-ANP Power Corporation. Also installed in the Unit 2 Cycle 11 reactor were 10 new GE/Reuter-Stokes NA-300 Local Power Range Monitors (LPRMs), and 23 new General Electric Marathon control rod blades. The inlet mixing sections for all 20 Jet Pumps were replaced.

Attached are the evaluation results from the following tests:

- Reactor Core Verification

- Single Rod Subcritical Check

- Control Rod Friction and Settle Testing

- Control Rod Drive Timing

- Shutdown Margin Test (In-sequence critical)

- Reactivity Anomaly Determination (Critical and Full Power)

- Scram Insertion Times

- TIP Measurement Uncertainty

- Recirculation System Performance ,,, _; (,-p

_O "'D

June 8, 2005 U.S. Nuclear Regulatory Commission Page 2 All test data was reviewed in accordance with the applicable test procedures, and exceptions to any results were evaluated to verify compliance with Technical Specification limits and to ensure the acceptability of subsequent test results.

Should you have any questions concerning this letter, please contact Mr.

Terry Simpkin, Regulatory Assurance Manager, at (815) 415-2800.

Respectfully, Susan Landahl Site Vice President LaSalle County Station Attachment cc: Regional Administrator - NRC Region IlIl NRC Senior Resident Inspector- LaSalle County Station

ATTACHMENT Page 1 of 9 Reactor Core Verification Purpose The purpose of this test is to visually verify that the core is loaded as intended for Unit 2 Cycle 11 operation.

Criteria The as-loaded core must conform to the cycle core design used by the Core Management Organization (General Electric & Nuclear Fuels) in the reload licensing analysis. Any discrepancies discovered in the loading will be promptly corrected and the affected areas re-verified to ensure proper core loading prior to unit startup.

Conformance to the cycle core design will be documented by a permanent core serial number map signed by the audit participants.

Results and Discussion Core verification was performed concurrently with core load and shuffle per core verification guideline NF-AA-330-1 001. The Unit 2 Cycle 11 core verification consisted of a core height, assembly orientation, assembly location, and assembly seating check performed by reactor services and reactor engineering. Bundle serial numbers and orientations were recorded during the videotaped scans for comparison to the appropriate core loading map and Cycle Management documentation. On March 9, 2005 the core was verified as being properly loaded and consistent with the LaSalle 2 Cycle 11 Design Basis Loading Plan per Transmittal of Design Information (TODI) # NF0400236, Revision 0. This was documented in WO# 682320-01.

4.

ATTACHMENT Page 2 of 9 Single Rod Subcritical Check Purpose The purpose of this test is to demonstrate that the Unit 2 Cycle 11 core will remain subcritical upon the withdrawal of the analytically determined strongest control rod.

Criteria The core must remain subcritical, with no significant increase in SRM readings, with the analytically determined strongest rod fully withdrawn.

Results and Discussion The analytically determined strongest rod for the Beginning of Cycle 11 for Unit 2 was determined by Nuclear Fuels to be rod 42-11 per TODI# NF0500021, Revision 0. On March 9, 2005, with a Unit 2 moderator temperature of 79.5 degrees Fahrenheit, rod 42-11 was withdrawn to the full out position (48) and the core remained subcritical with no significant increase in SRM readings. The satisfactory completion of LTP-1600-30, Single Rod Subcritical Check, allows single control rod withdrawals for control rod testing. This information is documented on LTP-1 600-30, Attachment A.

1.

ATTACHMENT Page 3of 9 Control Rod Friction and Settle Testing Purpose The purpose of this test is to demonstrate that excessive friction does not exist between the control rod blade and the fuel assemblies during operation of the control rod drive (CRD) following core alterations.

Criteria With the final cell loading complete for the fuel assemblies in a control cell there shall be no indication of excessive friction on the control rods tested.

Friction testing shall be performed on the respective control rod drives(s) when any condition listed below is applicable:

  • After relocation or replacement of the CRDM.
  • After maintenance or modification of an installed CRDM that could affect the performance of the drive.
  • Following outages, testing shall be performed on the respective control cells when any condition listed below is applicable:
  • After relocation or replacement of the CRDM
  • After maintenance or modification of an installed CRDM that could affect the performance of the drive.
  • Reactor Engineering determines that the control cell is susceptible to channel distortion
  • The Unit Nuclear Engineer or CRD System Engineer determines that testing is appropriate.

Results and Discussion CRD Friction Testing commenced after the completion of the core load verification and single rod subcritical check. There was no indication of excessive friction on the control rods tested.

The testing was completed on March 11, 2005, per WO# 752867-01.

ATTACHMENT Page 4 of 9 Control Rod Drive Timing Purpose The purpose of this test is to check and set the insert and withdrawal speeds of the Control Rod Drives (CRDs).

Criteria LOS-RD-SR5, Control Rod Drive Timing, states the withdraw times from the full in (notch 00) to the full out (notch 48) position should be between 45 and 60 seconds and insert times from the full out to the full in position should be between 40 and 55 seconds.

Results and Discussion LOS-RD-SR5 was performed satisfactory for all CRDMs requiring post maintenance testing.

As found control rod speeds are satisfactory per the UFSAR requirements. Timing was completed on March 14, 2005, perWO 677371-01.

ATTACHMENT Page 5of 9 Shutdown Margin Test Purpose The purpose of this test is to demonstrate, from a normal in-sequence critical, that the core loading has been limited such that the reactor will remain subcritical throughout the operating cycle with the strongest worth control rod in the full-out position (position 48) and all other rods fully inserted.

Criteria If a shutdown margin (SDM) of 0.38% delta K/K + R cannot be demonstrated with the strongest worth control rod fully withdrawn, the core loading must be altered to meet this margin. R is the reactivity difference between the core's beginning-of-cycle SDM and the minimum SDM for the cycle. The R value for Cycle 11 is 0.0% delta K/K per TODl#

NF0500047, Revision 0, so a SDM of 0.38% delta K/K must be demonstrated.

Results and Discussion The beginning-of-cycle SDM was successfully determined from the initial critical data. The initial Cycle 11 critical occurred on March 15, 2005, on control rod 10-39 at position 26, using an A-2 sequence. The moderator temperature was 147 degrees Fahrenheit and the reactor period was 313 seconds. Using rod worth information, moderator temperature reactivity corrections, and period reactivity corrections supplied by Nuclear Fuels in TODI# NF 0500047, the beginning-of-cycle SDM was determined to be 1.66% delta K/K. The SDM exceeded the 0.38% delta K/K that was required to satisfy the Technical Specifications.

ATTACHMENT Page 6 of 9 Reactivity Anomaly Determination Purpose The purpose of this test is to compare the actual and predicted critical rod configurations to detect any unexpected reactivity trends.

Criteria In accordance with the Technical Specifications, the reactivity equivalence of the difference between the actual critical control rod configuration and the predicted critical control rod configuration shall not exceed 1% delta K/K at full power steady state conditions. If the difference does exceed 1% delta K/K, the Core Management Engineers (Nuclear Fuels) will be promptly notified to investigate the anomaly. The cause of the anomaly must be determined, explained, and corrected for continued operation of the unit.

Results and Discussion Two reactivity anomaly calculations were successfully performed during the Unit 2 Cycle 11 Startup Test Program. One reactivity anomaly calculation from the in-sequence critical and one from steady state, equilibrium conditions at approximately 100 percent of full power.

The initial critical occurred on March 15, 2005, on control rod 10-39 at position 26, using an A-2 sequence. The moderator temperature was 147 degrees Fahrenheit and the reactor period was 313 seconds. Using rod worth information, moderator temperature, reactivity corrections, and period reactivity corrections supplied by Nuclear Fuels, the actual critical was determined to be within 0.09% delta K/K of the predicted critical. The anomaly determined is within the 1% delta K/K required for BOC conditions as stated in NF-AB-715.

This'was documented in NF-AB-715 Attachment 3.

The reactivity anomaly calculation for full power steady state operation was performed on March 20, 2005. The data used was from 99.7% power at a cycle exposure of 66.3 MWD/MT at equilibrium conditions. The expected Keff supplied by Nuclear Fuels was 1.0020. The actual Keff was 1.0050. The resulting anomaly was 0.30% delta K/K. This value is within the 1% delta K/K criteria of Technical Specifications.

ATTACHMENT Page 7 of 9 Scram Insertion Times Purpose The purpose of this test is to demonstrate that the control rod scram insertion times are within the operating limits set forth by the Technical Specifications.

Criteria The maximum scram insertion time of each control rod from the fully withdrawn position (48) to notch position 05, based on de-energization of the scram pilot valve solenoids as time zero, shall not exceed 7.0 seconds.

No more than 12 OPERABLE control rods shall be "slow" in accordance with the below table. In addition, no more than 2 Operable control rods that are uslow" shall occupy adjacent locations.

When the scram insertion time of an operable control rod from the fully withdrawn position (48), based on de-energization of the scram pilot valve solenoids as time zero, exceeds any of the following, that control rod is considered "slow":

Notch Position Fully Withdrawn Time (seconds) 45 0.52 39 0.80 25 1.77 05 3.20 Results and Discussion Scram testing was successfully completed on February 13, 2004 per WO# 585790-01 and 02. All 185 rods were scram timed during the reactor pressure vessel leakage testing (Hydro) prior to startup.

Five control rods (34-47, 58-43, 06-27, 42-07 and, 46-19) were determined to be 'slow." Work requests to repair these CRDMs have been written. The results of the testing are given below.

Notch Position Core Average Scram Times of all CRDs (sec) 45 0.384 39 0.683 25 1.398 05 2.457 The Tave was calculated to be 0.683 seconds. These results meet the Option A-B Scram Speeds referenced in the Unit 2 Cycle 11 Core Operating Limits Report (TRM Appendix J).

ATTACHMENT Page 8 of 9 TIP Measurement Uncertainty Purpose The purpose of this test is to verify the core power symmetry.

Criteria The X2 value of the total measured TIP uncertainty must be less than the critical value at the 1% confidence level (i.e., 36.19 for 19 TIP pairs).

The gross check of the TIP signal symmetry should yield a maximum deviation between symmetrically located pairs of less than 25%.

Results and Discussion Core power symmetry calculations were performed based upon data obtained from a full core TIP set (OD-1) performed on March 21, 2005, at approximately 100% power. The TIP set was performed with all 5 TIP machines operable. All traces were obtained. The x2 value was 7.60, which satisfies the test criteria of 36.19 for 19 pairs. The maximum deviation between symmetrical TIP pairs was 4.14%, which is within the 25% acceptance criteria.

ATTACHMENT Page 9 of 9 Recirculation System Performance Purpose The purpose of this procedure is to collect sufficient baseline data at the beginning of cycle to establish the following relationships:

- core thermal power vs. total core flow

- recirculation total drive flow vs. total core flow

- core plate flow vs. total core flow

- recirculation flow control valve position vs. loop drive flow

- jet pump readings vs. loop drive flow Criteria The performance curves used in conjunction with reactor recirculation system flow and differential pressure data will establish baseline data to determine if possible jet pump or recirculation pump degradation exists.

The established baseline performance curves will also be used to verify jet pump operability to determine if jet pump anomalies exist.

Results and Discussion The inlet mixing sections for all 20 Jet Pumps were replaced during this refueling outage.

Throughout startup, including while in low speed Reactor Recirculation, core flow calibrations were performed and Reactor Recirculation data was evaluated to ensure Reactor Recirculation performance was as expected. A dual loop core flow calibration was performed on March 18, 2005 at 100% power. The calibration was performed at a core flow of 99.95 Mlb/hr. The GAFs for the total core flow summer and the loop flow summers were all within the range of 0.98 to 1.02, so no adjustments were required. Reactor Recirculation data was collected from using L2C1 I start up and first load drop data. Data was obtained from computer points for all the points of interest to evaluate the RR System performance. Small changes for all parameters were noted due to the replacement of the mixing sections for all 20 Jet Pumps which resulted in an increase of -4% core flow (from -100.5% to -104.5%).

The data collected was used to generate new curves for L2C1 1. The RR system relationship curves were updated (WO# 613677-01) on April 30, 2005.