MONTHYEARML21075A1582021-03-15015 March 2021 E-mail from T. Silko to J. Parrott, NMSS, Vermont Yankee on the State of Vermont Comments on the Review of the Draft Final SER and EA for 20.2002 Alternate Disposal Request ML21006A0242020-12-22022 December 2020 E-mail from J. Parrott to J. Tierney and N. Creed Vermont Yankee Request to NRC for Alternate Disposal of Wastewater ML20358A0702020-12-22022 December 2020 E-mail Acceptance Review for Request for Indirect License Transfer (License DPR-28, Docket No. 50-271) ML20175A2122020-06-23023 June 2020 Acceptance Review of Request for Alternate Disposal of Wastes Under 10 CFR 20.2002 (License DPR-28, Docket No. 50-271) ML19289A1292019-10-11011 October 2019 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML19288A0292019-10-11011 October 2019 NRC Acceptance Review - Northstar Request for Exemption from 10 CFR 20, App G, Section Iii.E (License DPR-28, Docket No. 50-271) ML19198A2512019-06-20020 June 2019 Alternate Disposal Request - Rail Shipments (License DPR-28, Docket No. 50-271) ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML18289A3622018-10-11011 October 2018 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML18127A5582018-04-25025 April 2018 Email to State of Vermont on Vermont Yankee Nuclear Power Station - Forthcoming Issuance of a License Amendment Regarding the Requirement for the VYNPS to Have a Cyber Security Plan ML18045A0862018-01-25025 January 2018 Email Request for Review of the Draft Safety Evaluation for Implementation of a Revised Emergency Plan at Vermont Yankee to Reflect an ISFSI-only Configuration ML17353A0092017-12-18018 December 2017 E-Mail from William Irwin, Vermont Department of Health to Y. Chen/Dsfm Response: Draft Environmental Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17289A4222017-10-16016 October 2017 E-Mail from Y. J. Chen to W. Irwin Draft Environmental Assessment Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17257A0022017-09-14014 September 2017 Email to VY Shpo W Ltr Re VYNPS Exemption Load Campaign - Sept 2017 ML17229B4842017-08-16016 August 2017 Request for Supplemental Documentation to Support Review of the Physical Security Plan ML17219A0472017-08-0303 August 2017 8/03/2017, E-Mail from Y. J. Chen/Nmss to T. B. Silko/Vermont Yankee Regarding Need for Additional Information Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated May 16, 2017 (ML17142A358) ML17144A0452017-05-23023 May 2017 5/23/2017, E-Mail to I. William/Vermont Dept. of Health from Y. Chen/Nrc Response: Draft Environment Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation (W/Attachment Ltr to Address Comments on EA) ML17080A4752017-03-16016 March 2017 3/16/2017, E-Mail from I. William/Vermont Department of Health to Yen-Ju Chen/Dsfm/Sflb, Providing Comments on Draft Environmental Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for CoC No. 72-1014, Amendm ML17055A6262017-02-24024 February 2017 Cover Email from VY Shpo W Concurrence on No Effects Determination ML17040A3372017-02-0909 February 2017 Email and Letter to Vermont Shpo ISFSI Exemption No Effects Determination ML17038A4682017-02-0707 February 2017 2/07/2017, E-mail from Yen-Ju Chen/NRC-DSFM to W. Irwin/Vermont Dept. of Health Draft Environment Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for Certificate of Compliance No. 72-1014, Amendment 10 ML17012A2472017-01-11011 January 2017 E-mail - State of Vermont Comments Regarding Vermont Yankee'S 10 CFR 20.2002 Request ML16349A2492016-12-13013 December 2016 E-Mail to T. B. Silko/Entergy from Yen-Ju Chen/Dsfm Regarding Need for Supplemental Information for Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated November 9, 2016 (ML16319A102) ML17013A2502016-12-12012 December 2016 Email Requesting Review of Draft EA and SER for Vermont Yankee Request to NRC for Alternate Disposal of Waste ML16231A0282016-08-11011 August 2016 Response to NRC Questions Related to Request for 20.2002 Disposal of Contaminated Water ML16231A2192016-07-28028 July 2016 Follow-up Questions Related to Entergy Request for 20.2002 Disposal of Contaminated Water ML16069A0952016-03-0303 March 2016 Request for 20.2002 Disposal, Request for Additional Information ML16053A5152016-02-17017 February 2016 Comment (037) of Emma Stamas on ANPR-26, 50, 52, 73, and 140 - Regulatory Improvements for Decommissioning Power Reactors ML15329A1802015-11-24024 November 2015 E-mail from J. Whited Draft RAIs Re Duke License Amendment Request to Adopt TSTF-523 (CAC Nos. MF6413 Through MF6422) ML15295A2132015-10-21021 October 2015 NRR E-mail Capture - VY RAI for Off-site Insurance Exemption (10 CFR 140.11) - MF3980 ML15289A6002015-09-24024 September 2015 La 3 - Vermont Yankee Draft Responses or Edits 9 24 15.docx ML15289A6012015-09-23023 September 2015 La 3 - Nrr_Vermont Yankee Nuclear Power Station Decommissioning Status.Docx ML15288A3532015-09-21021 September 2015 La 3 - VY Dtf LAR - Status ML15257A6172015-09-14014 September 2015 La 3 - Testing the New Profile for Vermont Yankee La 3 - Public ML15195A3592015-07-14014 July 2015 NRR E-mail Capture - Acceptance Review for Vermont Yankee Amendment -Revise Cyber Security Plan Implementation ML15289A0022015-06-17017 June 2015 La 3 - Question from Ma ML15289A5982015-06-0909 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 5 2015 Letter from Vermont, Vynpc, and Gmp to NRC Attached ML15289A0072015-06-0505 June 2015 La 3 - Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15289A2432015-06-0404 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 4 2015 Vermont Letter to NRC Attached ML15289A0062015-06-0404 June 2015 La 3 - FW: Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15288A3592015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3602015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3622015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A4822015-05-22022 May 2015 La 3 - Vermont Reply to NRC & Entergy Answers Re VY LA-3 ML15289A0042015-05-19019 May 2015 La 3 - New Proposal Dates for Phone Call with VT ML15289A0052015-05-11011 May 2015 La 3 - ML Numbers for Disbursement Letters for Vermont Yankee ML15289A5992015-05-0808 May 2015 La 3 - Call with State of VT ML15289A0032015-05-0707 May 2015 La 3 - Other than for Comanche Peak, ML15289A1252015-05-0606 May 2015 La 3 - FRN Review - VY Dtf Exemption ML15128A0232015-04-27027 April 2015 NRR E-mail Capture - Petitioners Response to Request for Comments on the Proposed Director'S Decision on the 2.206 Petition Regarding Financial Qualifications of Entergy 2021-03-15
[Table view] |
Text
I Rick Ennis - Suppl 30 attachment 13 u~ 30 attachment_13ta=_ Pagie 1 RikEni.-:
From: "Daflucas, Ronda" <rdafluc@entergy.com>
To: "Rick Ennis" <RXE~nrc.gov>
Date: 8/2/05 11:13AM
Subject:
Suppl 30 attachment 13 Rick, Attached are Attachment 13 and the cover sheet for Attachment 11.
Len will be sending you the exhibits.
Ronda Daflucas Vermont Yankee Project Manager, NRR Entergy Nuclear Operations, Inc.
802-258-4232 CC: "Gucwa, Len" <LGUCW90@prod.entergy.com>, "Faison, Charlene"
<CFaison entergy.com>
- - -
l c:\temp\GW}0-00 01.TM P Pagie 1 11 c:\temD\GWIOOOO1.TMP Paae I II Mail Envelope Properties (42EF8D8B.OC8: 9: 24776)
Subject:
Suppl 30 attachment 13 Creation Date: 8/2/05 11:08AM From: "Daflucas, Ronda" <rdafluc(entergy.com>
Created By: rdafluc(entergy.com Recipients nrc.gov ov f4_po.OWFNDO RXE (Rick Ennis) entergy.com CFaison CC (Charlene Faison) prod.entergy.com LGUCW90 CC (Len Gucwa)
Post Office Route owf4_po.OWFNDO nrc.gov entergy.com prod.entergy.com Files Size Date & Time MESSAGE 225 08/02/05 11:08AM TEXT.htm 2195 Att 11 cover.pdf 14793 Att 13,pdf.pdf 63639 Mime.822 112264 Options Expiration Date: None Priority: Standard Reply Requested: No Return Notification: None Concealed
Subject:
No Security: Standard
VBW 05-072 Docket No. 50-271 Attachment 11
.Vermont Yankee Nuclear Power Station Proposed Technical Specification Change No. 263 - Supplement No. 30 Extended Power Uprate Response to Request for Additional Information Exhibits Exhibit SPSB-C-52-1 Exhibit SPSB-C-52-2 Exhibit SPSB-C-52-3 Exhibit SPSB-C-52-4 Exhibit SPSB-C-52-5 Exhibit SPSB-C-52-6 Exhibit EMEB-1-1 38-1 Exhibit EMEB-B-1 38-2 Exhibit EMEB-B-138-3 Exhibit SRXB-A-1 8-1
BVY 05-072 Docket No. 50-271 Attachment 13 Vermont Yankee Nuclear Power Station Proposed Technical Specification Change No. 263 - Supplement No. 30 Extended Power Uprate Response to Request for Additional Information Commitments l Total number of pages In Attachment 13 1 (excluding this cover sheet) Is 1. I
V 'V 'I ENN NON-QUALITY RELATED EN-LI-106 Revision I NUCLEAR ADMINISTRATIVE
.0,0W.
1.OE MANAGEMENT MANUAL INFORMATION USE
'V Page 1 of 1 a a a Licensee Identified Commitment Form This form Identifies actions discussed Inthis letter for which Entergy Nuclear Operations, Inc. (Entergy) commits to perform. Any other actions discussed in this submittal are described for the NRC's information and are not commitments.
(BVY 05-072)
TYPE (Check one)
COMMITMENT 8 SCHEDULED COMITMNT COMPLETION DATE t <. E (If Required) 0 Entergy has established administrative controls to assure performance of a once per operating cycle tabletop review X Oct. 31, 2005 of the procedures that complete the actions to repower a VYNPS 4KV bus from the VHS. Pursuant to discussions with co-host REMVEC, a system-wide annual tabletop review will take place in October 2005. During this meeting Entergy will lead a tabletop review of all actions required to support the restoration of 4KV AC to VYNPS.
This review will review the interfaces with the operator of VHS and the regional grid operator to verify that roles and responsibilities and timelines are understood and that there have been no changes that would impact the assumption in the VYNPS SBO coping strategy. Entergy will also provide the participants with additional insights regarding offsite power issues for nuclear power stations Including plant response to arid consequences of a SBO.
Training on the changes to OP 2124 and OT 3122 is currently underway. Once the training cycle is complete X O 16 2 (scheduled for September 1, 2005), the procedures will be ct. ,2005 revised and issued for use.
Various operating, surveillance and administrative procedures will be revised to incorporate a higher condensate storage tank inventory limit as either a precaution or an administrative limit by October 15, 2005.