Draft RAI, Proposed Amendment Re. Spent Fuel Storage
ML061090025
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/17/2006
From: Tam P
Plant Licensing Branch III-2
To: Loeffler R, Salamon G
Nuclear Management Co
References
TAC MD0302
Download: ML061090025 (2)


Text

From: Peter Tam To: Loeffler, Rick; Salamon, Gabor Date: 4/17/06 12:30PM

Subject:

Monticello: Draft RAI, Proposed Amendment re. Spent Fuel Storage (TAC MD0302)

Gabe, Rick:

This e-mail conveys our reviewer Yuri Orechwa's draft RAI on your application for amendment regarding contingent installation of the spent fuel rack. Please call me to set up a conference call to discuss these draft questions. The questions pertain only to Section 5.3 (Thermal-Hydraulic Considerations) and Section 5.5 (Criticality of the Monticello Nuclear Generating Plant).

(1) Are there any limitations on the use of the PaR fuel rack in your LAR (i.e. only during a FCOL, by burnup, etc.)? Please state the limiting conditions explicitly.

(2) Please compare in table form, with an attendant discussion, the current SFP licensing basis analysis to the supporting analysis of the SFP with the installation of the additional 8X8 high-density spent fuel storage rack. The information should include, but not be limited to, number of fuel assemblies and their distribution, the distribution of heat load, type of calculation, method of calculation of peak and average values, bulk temperature, clad temperature, Boral temperature, time-to-boiling, etc.

(3) Please compare in table form, with an attendant discussion, the current SFP licensing basis analysis to the supporting analysis of the SFP with the installation of the additional 8X8 high-density spent fuel storage rack. The information should include but not be limited to:

number of fuel assemblies and their distribution, the distribution of burnup and enrichment, type of neutronic calculation to determine keff, (i.e. codes, cross sections, validation, etc.) estimation of uncertainty, maximum worth of the installed and fueled 8X8 high-density storage rack, etc.

This e-mail aims solely to prepare you and others for the proposed conference call. It does not formally convey an NRC staff position, nor does it formally request for additional information. Disposition of the above questions will be discussed in the proposed conference call.

Peter S. Tam, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation e-mail: pst@nrc.gov Tel.: 301-415-1451

CC: Akstulewicz, Frank; Orechwa, Yuri Mail Envelope Properties (4443C2A3.544 : 12 : 35330)

Subject:

Monticello: Draft RAI, Proposed Amendment re. Spent Fuel Storage (TAC MD0302)

Creation Date: 4/17/06 12:30PM From: Peter Tam Created By: PST@nrc.gov Recipients Action Date & Time nmcco.com Transferred 04/17/06 12:31 PM Gabor.Salamon (Gabor Salamon)

Richard.Loeffler (Rick Loeffler) nrc.gov OWGWPO01.HQGWDO01 Delivered 04/17/06 12:30 PM FMA CC (Frank Akstulewicz) Opened 04/17/06 2:00 PM nrc.gov TWGWPO01.HQGWDO01 Delivered 04/17/06 12:30 PM YXO CC (Yuri Orechwa) Opened 04/17/06 12:31 PM Post Office Delivered Route nmcco.com OWGWPO01.HQGWDO01 04/17/06 12:30 PM nrc.gov TWGWPO01.HQGWDO01 04/17/06 12:30 PM nrc.gov Files Size Date & Time MESSAGE 3054 04/17/06 12:30PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard Reply Requested: No Return Notification: None Concealed

Subject:

No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened