MONTHYEARML19025A0822019-01-10010 January 2019 Rancho Seco Nuclear Generating Station - Report of Changes to the Rancho Seco Quality Assurance Program That Do Not Require Prior NRC Approval ML18302A1582018-11-28028 November 2018 Revised Letter for Termination of Rancho Seco Nuclear Generating Station Operating License DPR-54 and Indemnity Agreement ML18324A5902018-10-31031 October 2018 Sacramento Municipal Utility District (Smud) - Rancho Seco - Emergency Plan Manual Update IR 05000312/20180012018-09-0505 September 2018 Independent Spent Fuel Storage Installation (ISFSI) Inspection Report 05000312/2018001 and 07200011/2018001 ML18082B0762018-08-31031 August 2018 Termination of Rancho Seco Nuclear Generating Station Operating License DPR-054 ML18143B4752018-05-15015 May 2018 Biennial Report for Period Covering 05/01/2016 Through 04/30/2016 ML18081A5792018-03-0505 March 2018 Report on Decommissioning Funding Status ML18065A1852018-02-20020 February 2018 Annual Radioactive Effluent Release Report for 2017 ML17191A6322017-06-26026 June 2017 2016 Annual Financial Report for the Sacramento Municipal Utility District ML17116A1362017-05-16016 May 2017 Review of Final Status Survey Report for Rancho Seco Nuclear Generating Station Interim Onsite Storage Building ML17118A0252017-04-20020 April 2017 Final Status Survey Report Submittal - Clarifying Information ML17108A3442017-03-30030 March 2017 Records Required to Be Forwarded to the NRC Prior to Plant 10CFR50 License Termination. with Attachment 1: Annual Radioactive Effluent Release Report for the 1st Quarter of 2017 ML17108A3492017-03-30030 March 2017 Radioactive Effluent Release Report for January 1 - March 30, 2017 ML17095A9802017-03-30030 March 2017 and Independent Spent Fuel Storage Facility - Submittal of Revised Quality Manual ML17094A4072017-03-23023 March 2017 Report on Irradiated Fuel Management Funding Status ML17083A9832017-03-22022 March 2017 Orau Independent Confirmatory Survey Summary, Results, and In-Process Inspection for the Interim On-Site Storage Building and Surrounding Area at the Rancho Seco Nuclear Generating Station ML17094A7332017-03-22022 March 2017 Report on Decommissioning Funding Status ML17090A4102017-03-20020 March 2017 Annual Report of Property Insurance Levels ML17083A2602017-03-14014 March 2017 Annual Radioactive Effluent Release Report for 2016 ML17065A0342017-02-28028 February 2017 Final Status Survey Summary Report ML17026A4332017-01-17017 January 2017 Independent Spent Fuel Storage Installation Proposed License Amendment No. 4 ML16302A0702016-10-18018 October 2016 Biennial Update to Rancho Seco License Termination Plan ML16302A0712016-10-18018 October 2016 Radioactive Material Storage and Decommissioning Safety Analysis Report Amendment 3 IR 05000312/20160022016-09-16016 September 2016 NRC Inspection Report 050-00312/2016-002 ML16208A1092016-07-14014 July 2016 Sacramento Municipal Utility District (Smud), Rancho Seco Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Biennial Report for May 2014 - April 2016 IR 05000312/20160012016-06-17017 June 2016 IR 05000312/2016001 and 07200011/2016001, May 17-18, 2016, Sacramento Municipal Utility District, Rancho Seco Independent Spent Fuel Storage Installation ML16187A1922016-06-16016 June 2016 and ISFSI - Annual Financial Report for 2015 ML16106A1092016-04-0707 April 2016 Notification of Mailing Date of the Rancho Seco Report on Decommissioning Funding Status ML16097A2362016-03-31031 March 2016 Report on Irradiated Fuel Management Funding Status ML16102A0822016-03-23023 March 2016 Annual Report of Property Insurance Levels ML16102A0972016-03-14014 March 2016 Report on Decommissioning Funding Status ML16089A2932016-03-10010 March 2016 Annual Radioactive Effluent Release Report for the Period of January 1 Through December 31, 2015 ML16014A1372016-01-0707 January 2016 ISFSI - Report of Changes to the Quality Assurance Program That Do Not Require Prior NRC Approval ML15140A4212015-05-12012 May 2015 Sacramento Municipal Utility District - 2014 Annual Financial Report ML15105A0812015-03-31031 March 2015 Voluntary Submission of Pending Licensing Actions (RIS 2014-13 Response) ML15099A5742015-03-31031 March 2015 Independent Spent Fuel.Storage Installation, 10 CFR 20.2206 Annual Report of Individual Monitoring ML15099A5832015-03-30030 March 2015 and Independent Spent Fuel Storage Installation - 2014 Annual Radiological Environmental Operating Report for the Period of January 1, 2014 Through December 31, 2014 ML15093A0582015-03-23023 March 2015 Report on Decommissioning Funding Status ML15093A0592015-03-23023 March 2015 Annual Radioactive Effluent Release Report for 2014 ML15093A0562015-03-23023 March 2015 Annual Report of Property Insurance Levels ML15036A0472015-01-0707 January 2015 Report of Changes to the Rancho Seco Quality Assurance Program That Do Not Require Prior NRC Approval ML14352A3402015-01-0505 January 2015 Change in Project Manager Ltr Rancho Seco ML14310A1972014-10-30030 October 2014 Biennial Update to Rancho Seco License Termination Plan ML14310A2962014-10-23023 October 2014 Radioactive Material Storage and Decommissioning Safety Analysis Report Amendment 2 ML14308A0562014-10-22022 October 2014 Annual Notification of Foreign Ownership, Control, or Influence Status IR 05000312/20140072014-08-20020 August 2014 IR 050003122014007, on 06/23-25/2014 - 07/28-30/2014, Rancho Seco Nuclear Generating Station, NRC Inspection Report ML14219A3272014-07-24024 July 2014 Biennial Report ML14195A0272014-06-19019 June 2014 Submitting the 2013 Annual Financial Report for the Sacramento Municipal Utility District ML14142A3802014-05-0101 May 2014 Annual Notification of Foreign Ownership, Control, or Influence Status ML14154A1182014-04-30030 April 2014 Request to Register as User of Energysolutions 10-160B Package 2019-01-10
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARML0804305872008-01-0808 January 2008 Sacramento Municipal Utility District (Smud); Rancho Seco Nuclear Generating Station'S 01/08/2008 Response to 12/11/2007 Notice of Violation from the State of Utah, Dept. of Environmental Quality 2008-01-08
[Table view] |
Text
PO. Box 15830, Sacramento, CA 95852-1830; I-888-742-SMUD (7683)
MPC&D 08-006 January 8,2008 State of Utah Department of Environmental Quality 168 North 1950 West Salt Lake City, UT 84114-4850 Rancho Seco Nuclear Generating Station Generator Access Perniit Number: 0109 000 002 RESPONSE TO NOTICE OF VIOLATION Attention: Jule L. Fausto In a letter dated December 11, 2007, the Sacramento Municipal Utility District (SMUD) received a Notice of Violation (NOV) from the State of Utah, Department of Environmental Quality. The violation was identified on November 26,2007, regarding radioactive waste shipment number 0802-1 5-0046 from Rancho Seco Nuclear Generating Station to Energy Solutions Clive site in UT.
Attached is our response to the violation including corrective actions taken by SMUD and its contractor to prevent recurrence. If you, or members of your staff, have questions requiring additional information or clarification, please contact Bob Jones at (916) 732-4843.
Sincerely, Steve Redeker Manager, Plant Closure & Decommissioning Cc: NRC, Region IV i
, I r
1 i 1 2LC RANCHO SECO NUCLEAR PLANT a14440 Twin Cities Road, Herald, CA 95638-9799; (209)333-2935
Response To Notice Of Violation State Of Utah Generator Access Permit Number 0 109 000 002.
DISCUSSION Between October 25, 2007, and November 13, 2007, Sacramento Municipal Utility District (SMUD) subcontractor personnel loaded radioactive waste into gondola rail car ENVX206 142. The waste materials consisted of large bore piping wrapped with plastic as a contamination control measure, concrete debris in lift liner sacks, filters from the HVAC system and other DAW material.
The large bore piping was loaded into the gondola railcar in such a way that each of the pipes was "blocked and braced" in place against the side wall of the gondola railcar, against other piping, and lift liners. Blocking and bracing of the waste loaded in the railcar was evaluated by Duratelc and SMUD personnel, and it was determined that it would be sufficient to hold the radioactive waste in place under conditions normally incident to transportation.
After railcar loading was completed a survey was performed and used to classify the waste in the railcar as LSA I (bulk unpacltaged waste), Class A unstable. A Uniform Low-Level Radioactive Waste Manifest was completed (0802-1 5-0046) in accordance with SMUD procedures, transportation was ordered, and a five working-day shipment notification was delivered to Energy Solutions at Clive.
On November 17,2007 Union Pacific Railroad arrived at the Rancho Seco site and picked up railcar ENVX206142 and it was transported to EnergySolutions disposal site at Clive Utah where it arrived on November 26, 2007. On November 26, 2007, the Rancho Seco reactor building decommissioning project was notified by the EnergySolutions Clive disposal site that ENVX206142 had been received with a small breach in the side wall. The railcar liad been surveyed and there was no smearable contamination detected, and there was no release of radioactive material from the railcar.
After receiving the notification froin Clive and as part of the immediate corrective actions, Duratek on-site personnel issued a First Notification and halted loading of large debris into gondola rail cars. Project personnel evaluated the cause of the damage to the railcar and determined the most likely cause was that the railcar was "humped" during transit from Rancho Seco to Clive. The force of the humping action could cause the pipe that was braced against the conveyance sidewall to shift piercing the side of the railcar.
CORRECTIVE ACTIONS Prior to beginning loading of large debris in railcars the Duratek Waste Manager and the SMUD Field Engineer will develop a bloclting and bracing plan. Loading of large, loose demolition debris is an infrequent occurrence and is expected to occur only in one additional evolution (Le., polar crane dismantling, packaging, and shipping) during Rancho Seco decommissioning, which is scheduled to be completed this year. The bloclting and bracing plan will ensure compliance with the federal regulations regarding bloclting and bracing and preventing the shifting of loads.
Response To Notice Of Violation State Of Utah Generator Access Permit Number 0 109 000 002 Once the blocking and bracing plan has been developed and approved, project personnel responsible for loading radioactive waste in railcars will be trained on the blocking and bracing plan and the requirements of federal regulations, and SMUD procedures governing blocking and bracing of radioactive waste.
Elements of the blocking and bracing plan will include:
- 1. Use of a wood (plywood) "cushion" that will be installed along the walls and floor of the conveyance in order to protect the steel of the floor and sidewall and minimize the effect of the railroad humping the railcar in transit.
- 2. Use of a combination of tie-down straps, toe boards, wood, steel, and other shoring material that will prevent shifting of debris.
- 3. Blocking and bracing will be verified by the Duratek Waste Manager, and by the SMUD Field Engineer. Evaluation of the blocking and bracing will be documented on the Radioactive Shipment Quality-Control Checklist (RAD-055)