Acceptance Review of TMI-1 LAR Regarding Relocation of Equipment Load List to UFSAR - TAC ME4732
ML103000030
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 10/27/2010
From: Peter Bamford
Plant Licensing Branch 1
To: Mascitelli F
Exelon Corp
Bamford, Peter J., NRR/DORL 415-2833
References
TAC ME4732
Download: ML103000030 (2)


Text

From: Bamford, Peter Sent: Wednesday, October 27, 2010 8:12 AM To: 'Frank.Mascitelli@exeloncorp.com' Cc: 'david.helker@exeloncorp.com'

Subject:

Acceptance Review of TMI-1 LAR Regarding Rolocation of Equipment Load List to UFSAR - TAC No. ME4732 By letter dated September 22, 2010 (ADAMS Accession No. ML102650392), Exelon Generation Company, LLC submitted a license amendment request (LAR) for Three Mile Island Nuclear Station, Unit 1 (TMI-1), proposing to relocate the list of pumps, fans and valves in Technical Specification (TS) 4.5.1.1b, regarding the sequence and power transfer test, to the TMI-1 Updated Final Safety Analysis Report. Additionally, several other specifications are proposed for modification to reflect this relocation of the equipment load list.

The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed license amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again.

Peter Bamford NRR/DORL/LPL 1-2 Limerick & TMI-1 Project Manager 301-415-2833 E-mail Properties Mail Envelope Properties ()

Subject:

Acceptance Review of TMI-1 LAR Regarding Rolocation of Equipment Load List to UFSAR - TAC No. ME4732 Sent Date: 10/27/2010 7:15:42 AM Received Date: 10/27/2010 8:11:00 AM From: Bamford, Peter

Created By: Peter.Bamford@nrc.gov Recipients:

Frank.Mascitelli@exeloncorp.com ('Frank.Mascitelli@exeloncorp.com')

Tracking Status: None david.helker@exeloncorp.com ('david.helker@exeloncorp.com')

Tracking Status: None Siva.Lingam@nrc.gov (Lingam, Siva)

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 17153 10/27/2010 image001.gif 4069 Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: