MONTHYEARHNP-18-050, Request to Extend Reactor Vessel Surveillance Capsule Report Submission Date2018-09-17017 September 2018 Request to Extend Reactor Vessel Surveillance Capsule Report Submission Date HNP-18-004, License Amendment Request to Change Shearon Harris Nuclear Power Plant, Unit 1, Emergency Plan Emergency Action Level Scheme2018-08-13013 August 2018 License Amendment Request to Change Shearon Harris Nuclear Power Plant, Unit 1, Emergency Plan Emergency Action Level Scheme HNP-18-035, Relief Request I3R-18, Alternative Repair and Replacement Testing Requirements for the Containment Building Equipment Hatch Sleeve Weld, Lnservice Inspection Program for Containment, Third Ten-Year Interval2018-06-0404 June 2018 Relief Request I3R-18, Alternative Repair and Replacement Testing Requirements for the Containment Building Equipment Hatch Sleeve Weld, Lnservice Inspection Program for Containment, Third Ten-Year Interval HNP-18-049, Submittal of 1 0 CFR 50.54(q) Evaluation Form of Changes to Procedure EMP-420, Emergency Program Maintenance, Revision 192018-05-0303 May 2018 Submittal of 1 0 CFR 50.54(q) Evaluation Form of Changes to Procedure EMP-420, Emergency Program Maintenance, Revision 19 HNP-18-023, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes2018-05-0202 May 2018 Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes HNP-18-042, Annual Environmental (Non-radiological) Operating Report2018-04-30030 April 2018 Annual Environmental (Non-radiological) Operating Report HNP-18-032, Annual Radiological Environmental Operating Report2018-04-25025 April 2018 Annual Radiological Environmental Operating Report HNP-18-031, Annual Radioactive Effluent Release Report2018-04-25025 April 2018 Annual Radioactive Effluent Release Report HNP-18-047, Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval, Non-Proprietary Version of Calculation2018-04-20020 April 2018 Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval, Non-Proprietary Version of Calculation HNP-18-045, Submittal of Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval2018-04-18018 April 2018 Submittal of Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval HNP-18-044, Cycle 22 Core Operating Limits Report, Revision O2018-04-16016 April 2018 Cycle 22 Core Operating Limits Report, Revision O HNP-18-039, Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2018-04-13013 April 2018 Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-18-021, Annual Report in Accordance with Technical Specification 6.9.1.22018-02-19019 February 2018 Annual Report in Accordance with Technical Specification 6.9.1.2 HNP-18-020, Supplement to Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses2018-02-16016 February 2018 Supplement to Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses HNP-18-019, Cycle 21 Core Operating Limits Report, Revision 12018-02-14014 February 2018 Cycle 21 Core Operating Limits Report, Revision 1 HNP-18-017, CFR 50.54(q) Evaluations2018-02-0505 February 2018 CFR 50.54(q) Evaluations HNP-18-001, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors.2018-02-0101 February 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors. HNP-18-002, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2018-01-22022 January 2018 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-18-003, Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses2018-01-18018 January 2018 Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses HNP-18-007, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Supplement Regarding De Minimis Penetrations2018-01-11011 January 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Supplement Regarding De Minimis Penetrations HNP-18-006, Submittal of 14-Day Special Report for Accident Radiation Monitors2018-01-0404 January 2018 Submittal of 14-Day Special Report for Accident Radiation Monitors HNP-17-093, Supplement to License Amendment Request Proposing a New Set of Fission Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 32017-11-29029 November 2017 Supplement to License Amendment Request Proposing a New Set of Fission Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3 HNP-17-078, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2017-11-27027 November 2017 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-17-082, Response to Request for Additional Information Regarding License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Limit Detailed In..2017-10-30030 October 2017 Response to Request for Additional Information Regarding License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Limit Detailed In.. HNP-17-084, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2017-10-30030 October 2017 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-17-025, Fourth Interval Lnservice Inspection Plan, Third Interval Containment Lnservice Inspection Plan, and Fourth Interval Lnservice Inspection Pressure Test Plan2017-10-23023 October 2017 Fourth Interval Lnservice Inspection Plan, Third Interval Containment Lnservice Inspection Plan, and Fourth Interval Lnservice Inspection Pressure Test Plan HNP-17-072, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis2017-10-19019 October 2017 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis HNP-17-077, License Amendment Request Regarding Rod Control Movable Assemblies Technical Specifications2017-10-10010 October 2017 License Amendment Request Regarding Rod Control Movable Assemblies Technical Specifications HNP-17-076, Supplement to License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Duplicate Reporting Requirements.2017-10-0202 October 2017 Supplement to License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Duplicate Reporting Requirements. HNP-17-073, Supplemental Information for License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-09-14014 September 2017 Supplemental Information for License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-062, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2017-09-13013 September 2017 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal HNP-17-061, Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-07-20020 July 2017 Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-008, License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-06-28028 June 2017 License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-003, License Amendment Request for Emergency Diesel Generator Surveillance Requirements Regarding Voltage and Frequency Limits and the Voltage Limit for Emergency Diesel Generator Load Rejection2017-06-0505 June 2017 License Amendment Request for Emergency Diesel Generator Surveillance Requirements Regarding Voltage and Frequency Limits and the Voltage Limit for Emergency Diesel Generator Load Rejection HNP-17-040, Snubber Program Plan2017-06-0101 June 2017 Snubber Program Plan HNP-17-051, 10 CFR 50.54(q) Evaluation2017-05-24024 May 2017 10 CFR 50.54(q) Evaluation HNP-17-050, Transmittal of 10 CFR 50.54(q) Evaluation for Revision 21 to PEP-250, Activation and Operation of the Joint Information Center2017-05-24024 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation for Revision 21 to PEP-250, Activation and Operation of the Joint Information Center HNP-17-041, Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete2017-05-22022 May 2017 Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Du HNP-17-033, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 112017-05-22022 May 2017 License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 11 HNP-17-049, Transmittal of 10 CFR 50.54(q) Evaluation and Revision 26 to PEP-110, Emergency Classification and Protective Action Recommendations.2017-05-18018 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation and Revision 26 to PEP-110, Emergency Classification and Protective Action Recommendations. HNP-17-047, 10 CFR 50.54(q) Evaluation2017-05-18018 May 2017 10 CFR 50.54(q) Evaluation HNP-17-048, Transmittal of 10 CFR 50.54(q) Evaluation and Revision 28 to PEP-230, Control Room Operations.2017-05-18018 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation and Revision 28 to PEP-230, Control Room Operations. HNP-17-046, 10 CFR 50.54(q) Evaluation2017-05-18018 May 2017 10 CFR 50.54(q) Evaluation HNP-17-024, Annual Environmental (Nonradiological) Operating Report2017-04-28028 April 2017 Annual Environmental (Nonradiological) Operating Report HNP-17-023, Annual Radioactive Effluent Release Report2017-04-28028 April 2017 Annual Radioactive Effluent Release Report HNP-17-034, Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106..2017-04-25025 April 2017 Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106.. HNP-17-035, Request for Pilot Plant Status and Fee Waiver to Implement Tornado Missile Risk Evaluator2017-04-12012 April 2017 Request for Pilot Plant Status and Fee Waiver to Implement Tornado Missile Risk Evaluator HNP-17-045, 10 CFR 50.54(q) Evaluation of Change in Emergency Plan Implementation Procedure PEP-241, Revision 7, Technical Support Center (TSC) Emergency Ventilation System Operation2017-03-30030 March 2017 10 CFR 50.54(q) Evaluation of Change in Emergency Plan Implementation Procedure PEP-241, Revision 7, Technical Support Center (TSC) Emergency Ventilation System Operation HNP-17-014, Annual Report in Accordance with Technical Specifications, Section 6.9.1.22017-02-16016 February 2017 Annual Report in Accordance with Technical Specifications, Section 6.9.1.2 HNP-17-015, Summary of 10 CFR 50.54(q) Evaluation2017-02-15015 February 2017 Summary of 10 CFR 50.54(q) Evaluation 2018-09-17
[Table view] |
Text
Progress Energy Serial: HNP-07-103 JUL 2 6 2007 10 CFR 50.90 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/LICENSE NO. NPF-63 RESPONSE TO GENERIC LETTER 2003-01, "CONTROL ROOM HABITABILITY" COMMITMENT DATE CHANGE
Reference:
- 1. Letter from James Scarola to the United States Nuclear Regulatory Commission (Serial: HNP 03-089) "Generic Letter 2003-01, 'Control Room Habitability' Sixty-Day Response" dated August 11, 2003 2. Letter from Terry C. Morton to United States Nuclear Regulatory Commission (Serial: HNP 03-139) "180-Day Response to Generic Letter 2003-01, 'Control Room Habitability"'
dated December 09, 2003 Ladies and Gentlemen:
On June 12, 2003, the NRC issued Generic Letter 2003-01, "Control Room Habitability", which requested licensees to submit information demonstrating that control rooms comply with the current licensing and design bases, and applicable regulatory requirements.
In addition, information was requested to ensure that suitable design, maintenance and testing control measures are in place for maintaining this compliance.
Carolina Power and Light Company, doing business as Progress Energy Carolinas, Inc., provided a 180-day response to this Generic Letter on December 09, 2003.In this response, Harris Nuclear Plant (HNP) committed to the following: "HNP will submit a proposed license amendment request that will include a new Technical Specification surveillance requirement to determine inleakage in accordance with a CRE Integrity Program. A new section will be added to Technical Specification Section 6.8 'Procedures and Programs' that will specify the scope of the CRE Integrity Program. The CRE Integrity Program will rely on the use of tracer gas inleakage testing." Progress Energy Carolinas, Inc.Harris Nuclear Plant P. 0. Box 16527, New Hill, NC 27562 A&1je.
U.S. Nuclear Regulatory Commission Serial: HNP-07-103 Page 2 The due date for this commitment was "within six months following TSTF-448 approval or associated CLIIP approval, whichever is later." Since the "Notice of Availability of Technical Specification Improvement to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process" was published as approved on January 17, 2007 (Federal Register Vol. 72, No. 10), the HNP commitment date was July 17, 2007.During development of this License Amendment Request (LAR), HNP identified that its Technical Specifications do not include a Bases Control Program, which is integral to NRC's approved TSTF-448 model Safety Evaluation (SE). An LAR requesting such a change to HNP's TS to include the Bases Control Program was submitted to the NRC in accordance with the standard review process on June 15, 2007 (Serial: HNP-07-005).
However, since evaluation of a proposed Control Room Envelope (CRE) habitability LAR by the NRC under the Consolidated Line Item Improvement Process (CLIIP) is performed on an accelerated (six month) schedule, a revised date for submittal of HNP's CRE habitability TS requirement is prudent. Discussions with the NRC Project Manager for HNP, Lisa Regner, confirmed that a delay in submitting the CRE habitability LAR would allow for review of both amendments (TS Design Bases Control Program and CRE habitability) in the necessary sequence.Therefore, via this correspondence, HNP is notifying the NRC of a revised commitment date for its respective CRE habitability LAR submittal.
Under this revised commitment, HNP will submit the TSTF-448 related LAR, in accordance with the CLIIP guidelines, by January 16, 2008. This revised submittal date is still within the timeframe typically requested (one year) for TS changes published in the Federal Register using the CLIIP process.Please refer any question regarding this submittal to Mr. Dave Corlett, Supervisor
-Licensing/Regulatory Programs, at (919) 362-3137.Sincerely T. J. tale Manager, Support Services Harris Nuclear Plant W" U.S. Nuclear Regulatory Commission Serial: HNP-07-103 Page 3 TJN/kms Encl: Attachment 1 cc: Mr. P. B. O'Bryan, NRC Senior Resident Inspector Ms. B. 0. Hall, N.C. DENR Section Chief Ms. L. M. Regner, NRC Project Manager Dr. W. D. Travers, NRC Regional Administrator v" Attachment 1 to SERIAL: HNP-07-103 Page 1 of 1 Control Room Habitability Commitment Date Change LIST OF REGULATORY COMMITMENTS The actions committed to by Progress Energy Carolinas, Inc. (PEC) in this document are identified below. Any other actions discussed in this submittal represent intended or planned actions by PEC, described only for the NRC's information and are not regulatory commitments.
Committed Item Date Due HNP will submit a proposed license amendment request that January 16, 2008 will include a new Technical Specification surveillance requirement to determine inleakage in accordance with a CRE Integrity Program. A new section will be added to Technical Specification Section 6.8 "Procedures and Programs" that will specify the scope of the CRE Integrity Program. The CRE Integrity Program will rely on the use of tracer gas inleakage testing.
Text
Progress Energy Serial: HNP-07-103 JUL 2 6 2007 10 CFR 50.90 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/LICENSE NO. NPF-63 RESPONSE TO GENERIC LETTER 2003-01, "CONTROL ROOM HABITABILITY" COMMITMENT DATE CHANGE
Reference:
- 1. Letter from James Scarola to the United States Nuclear Regulatory Commission (Serial: HNP 03-089) "Generic Letter 2003-01, 'Control Room Habitability' Sixty-Day Response" dated August 11, 2003 2. Letter from Terry C. Morton to United States Nuclear Regulatory Commission (Serial: HNP 03-139) "180-Day Response to Generic Letter 2003-01, 'Control Room Habitability"'
dated December 09, 2003 Ladies and Gentlemen:
On June 12, 2003, the NRC issued Generic Letter 2003-01, "Control Room Habitability", which requested licensees to submit information demonstrating that control rooms comply with the current licensing and design bases, and applicable regulatory requirements.
In addition, information was requested to ensure that suitable design, maintenance and testing control measures are in place for maintaining this compliance.
Carolina Power and Light Company, doing business as Progress Energy Carolinas, Inc., provided a 180-day response to this Generic Letter on December 09, 2003.In this response, Harris Nuclear Plant (HNP) committed to the following: "HNP will submit a proposed license amendment request that will include a new Technical Specification surveillance requirement to determine inleakage in accordance with a CRE Integrity Program. A new section will be added to Technical Specification Section 6.8 'Procedures and Programs' that will specify the scope of the CRE Integrity Program. The CRE Integrity Program will rely on the use of tracer gas inleakage testing." Progress Energy Carolinas, Inc.Harris Nuclear Plant P. 0. Box 16527, New Hill, NC 27562 A&1je.
U.S. Nuclear Regulatory Commission Serial: HNP-07-103 Page 2 The due date for this commitment was "within six months following TSTF-448 approval or associated CLIIP approval, whichever is later." Since the "Notice of Availability of Technical Specification Improvement to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process" was published as approved on January 17, 2007 (Federal Register Vol. 72, No. 10), the HNP commitment date was July 17, 2007.During development of this License Amendment Request (LAR), HNP identified that its Technical Specifications do not include a Bases Control Program, which is integral to NRC's approved TSTF-448 model Safety Evaluation (SE). An LAR requesting such a change to HNP's TS to include the Bases Control Program was submitted to the NRC in accordance with the standard review process on June 15, 2007 (Serial: HNP-07-005).
However, since evaluation of a proposed Control Room Envelope (CRE) habitability LAR by the NRC under the Consolidated Line Item Improvement Process (CLIIP) is performed on an accelerated (six month) schedule, a revised date for submittal of HNP's CRE habitability TS requirement is prudent. Discussions with the NRC Project Manager for HNP, Lisa Regner, confirmed that a delay in submitting the CRE habitability LAR would allow for review of both amendments (TS Design Bases Control Program and CRE habitability) in the necessary sequence.Therefore, via this correspondence, HNP is notifying the NRC of a revised commitment date for its respective CRE habitability LAR submittal.
Under this revised commitment, HNP will submit the TSTF-448 related LAR, in accordance with the CLIIP guidelines, by January 16, 2008. This revised submittal date is still within the timeframe typically requested (one year) for TS changes published in the Federal Register using the CLIIP process.Please refer any question regarding this submittal to Mr. Dave Corlett, Supervisor
-Licensing/Regulatory Programs, at (919) 362-3137.Sincerely T. J. tale Manager, Support Services Harris Nuclear Plant W" U.S. Nuclear Regulatory Commission Serial: HNP-07-103 Page 3 TJN/kms Encl: Attachment 1 cc: Mr. P. B. O'Bryan, NRC Senior Resident Inspector Ms. B. 0. Hall, N.C. DENR Section Chief Ms. L. M. Regner, NRC Project Manager Dr. W. D. Travers, NRC Regional Administrator v" Attachment 1 to SERIAL: HNP-07-103 Page 1 of 1 Control Room Habitability Commitment Date Change LIST OF REGULATORY COMMITMENTS The actions committed to by Progress Energy Carolinas, Inc. (PEC) in this document are identified below. Any other actions discussed in this submittal represent intended or planned actions by PEC, described only for the NRC's information and are not regulatory commitments.
Committed Item Date Due HNP will submit a proposed license amendment request that January 16, 2008 will include a new Technical Specification surveillance requirement to determine inleakage in accordance with a CRE Integrity Program. A new section will be added to Technical Specification Section 6.8 "Procedures and Programs" that will specify the scope of the CRE Integrity Program. The CRE Integrity Program will rely on the use of tracer gas inleakage testing.