ML110960591

From kanterella
Revision as of 20:53, 10 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Response to Non-Cited Violations 05000390-10-005-03, Failure to Use Worst Case 6900 Vac Bus Voltage in Design Calculations
ML110960591
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/31/2011
From: Krich R
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IR-10-005
Download: ML110960591 (16)


See also: IR 05000390/2010005

Text

Tennessee

Valley Authority 1101 Market Street, LP 3R Chattanooga, Tennessee

37402-2801

R. M. Kirich Vice President Nuclear Licensing March 31, 2011 10 CFR 2.201 ATTN: Document Control Desk U.S. Nuclear Regulatory

Commission

Washington, D.C. 20555-0001

Watts Bar Nuclear Plant, Unit 1 Facility Operating

License No. NPF-90 NRC Docket Nos. 50-390 Subject: Response to Non-Cited

Violations05000390/2010005-03, "Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations" References:

1. Letter from NRC (Eugene F. Guthrie) to TVA (R. M. Krich),"Watts Bar Nuclear Plant -NRC Integrated

Inspection

Report 05000390/2010005," dated January 28, 2011 2. Letter from TVA (R. M. Krich) to NRC "Request for Extension

for Time to Respond to Non-Cited

Violations

05000327,05000328/2010005-03, 'Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations'

and 05000390/2010005-03, 'Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations,"'

dated February 25, 2011 In Reference

1, the Nuclear Regulatory

Commission (NRC) issued Non-Cited

Violation (NCV)05000390/2010005-03, "Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations," regarding

Watts Bar Nuclear Plant (WBN), Unit 1. The NCV addressed

issues regarding

the design basis of the degraded voltage protection

equipment.

In Reference

2, TVA requested

that the response date for potential challenge

of the Reference

1 NCV be extended to March 31, 2011.TVA has completed

a review of the concerns and issues regarding

the design of degraded voltage protection

at WBN, Unit 1, expressed

by the NRC in Reference

1.printed on recycled paper .1III-JIII

U.S. Nuclear Regulatory

Commission

Page 2 March 31, 2011 the NRC Enforcement

Policy, TVA contests Non-Cited

Violation

05000390/2010005-

03, "Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculation." The basis for TVA's denial of the subject NCV is provided in the Enclosure.

There are no commitments

associated

with this letter.If you have any questions

in this matter, please contact me at 423-751-3628.

Respectfully, Enclosure cc: NRC Director, Office of Enforcement

NRC Regional Administrator

-Region II NRC Senior Resident Inspector

-Watts Bar Nuclear Plant

ENCLOSURE TENNESSEE

VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT, UNIT I NRC INTEGRATED

INSPECTION

REPORT 05000390/2010005

REPLY TO NOTICE OF A NON-CITED

VIOLATION

TENNESSEE

VALLEY AUTHORITY WATTS BAR NUCLEAR, PLANT UNIT 1 NRC INTEGRATED

INSPECTION

REPORT NO. 05000390/2010005

REPLY TO NOTICE OF A NON-CITED

VIOLATION I. Introduction

In a letter dated January 28, 2011, the Nuclear Regulatory

Commission

issued Non-Cited Violation (NCV)05000390/2010005-03, "Failure to Use Worst Case 6900 VAC Bus Voltage In Design Calculations," regarding

Watts Bar Nuclear Plant (WBN), Unit 1. The NCV addressed issues regarding

the design basis of the degraded voltage protection

equipment.

In the letter, the NRC stated: If you contest any NCV in this report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington

DC 20555-0001;

with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, DC 20555-0001;

and the NRC Resident Inspector...

Based on the issuance date of the letter, the 30-day response date to contest the NCV was February 27, 2011. By letter dated February 25, 2011, the Tennessee

Valley Authority (TVA)requested

an extension

of the date for contesting

the NCV until March 31, 2011.TVA has conducted

a review of the NCV and of apparent NRC concerns regarding

the design of the degraded voltage protection

at WBN, Unit 1. Based on that review, TVA contests the NCV for the reasons discussed

in detail in this response.In addition to contesting

the NCV, TVA considers

that the NRC's apparent position regarding the adequacy of the design and licensing

basis for degraded voltage protection

at WBN, Unit 1 is unjustified.

The NRC's concerns in this regard, although not clearly expressed

in the inspection

report 05000390/2010005, were reflected

in the discussions

between NRC inspectors

and TVA staff during the 2010 WBN Component

Design Basis Inspection (CDBI), by NRC management

during the CDBI inspection

exit teleconference

on December 16, 2010, and during a public meeting between NRC and TVA on degraded voltage protection

issues in Rockville, Maryland on March 11, 2011.TVA is firmly committed

to fully understanding

and resolving

NRC's concerns regarding degraded voltage protection.

However, TVA's position is that the issues should be resolved in a manner that implements

both existing regulatory

requirements (such as 10 CFR Part 50, Appendix B, Criterion

III, Design Control) and existing regulatory

processes (such as the reactor oversight

process, enforcement

process, and backfit process) in a credible manner that allows for a clear understanding

of the technical

issues and the associated

regulatory

framework.

TVA's response to the NCV and the apparent underlying

technical

and regulatory

concerns are presented

below in two separate elements:* Disputes the use of 10 CFR Part 50, Appendix B, Criterion

III, "Design Control" as the basis for the NCV, and* Disputes the NRC's apparent concerns regarding

the adequacy of the WBN current licensing

basis for degraded voltage protection.

E-1

II. Disputing

the Use of 10 CFR Part 50, Appendix B, Criterion

III, "Design Control" as the Basis for Non-Cited

Violation 05000390/2010005-03

Restatement

of Non-Cited

Violation A restatement

of the subject NCV from NRC Inspection

Report 05000390/2010005

is as follows.Enforcement:

10 CFR 50, Appendix B, Criterion

Ill, Design Control, states, in part, that measures shall be established

to assure that applicable

regulatory

requirements

and the design basis for structures, systems, and components

are correctly

translated

into specifications, drawings, procedures, and instructions.

This appendix also states in part that measures shall be established

for the selection

and review for suitability

of application

of processes

that are essential

to the safety-related

functions

of the structures, systems, and components.

Watts Bar TS Section 3.3.5-1, "Loss of Power Diesel Generator

Start Instrumentation," table 3.3.5-1, item 2 specifies

the 6900 VC emergency

bus undervoltage (degraded)

relay trip setpoints

to be as follows: "Allowable

Value, >_6570 VAC, Trip Setpoint, <6606 VAC and >_6593 VA C." Contrary to the above, since at least December 2001, the licensee failed to assure that applicable

regulatory

requirements

for undervoltage (degraded)

voltage protection, including

those prescribed

in TS 3.3.5-1, item 2, were correctly

translated

into design calculation, WBN-EEB-MS-TI-06-0029, "Degraded

Voltage Analysis," Revision 31, which evaluated

motor starting voltages at the beginning

of a design basis loss of coolant accident (LOCA) concurrent

with a degraded grid condition.

Further, the process used by the licensee for the selection

of input voltage value in the design calculation

was non-conservative

with respect to the TS. Specifically, the licensee used the input value of 6672 VAC which was higher than the maximum value of 6606 VAC specified

in TS. This did not result in a loss of function of safety-related

loads.Because this finding is of very low safety significance

and was entered into the licensee's

corrective

action program as PER 296306 this violation

is being treated as a NCV, consistent

with the NRC Enforcement

Policy. This finding is identified

as NCV 05000390, 2010005-:"Failure

to Use Worst Case 6900 VAC Bus Voltage in Design Calculations." URI 05000390/2010008-02, "Worst Case 6900 VAC Bus Voltage in Design Calculations" is closed.Summary of TVA Basis for Denial of Enforcement

Against Criterion

III, "Design Control" TVA disputes the use of 10 CFR Part 50, Appendix B, Criterion

Ill, "Design Control" as the basis for the NCV. TVA's dispute is based on what TVA views as a fundamental

misapplication

of 10 CFR Part 50, Appendix B, Criterion

Ill, "Design Control," to the specific facts regarding

the design of degraded voltage protection

features at WBN and the associated

Technical Specification (TS) values. TVA is specifically

concerned

with the NRC's discussion

of the relationship

between the TS requirements

and the design calculation

referenced

in the NCV.In the NRC's discussion

for the basis of the NCV, the NRC stated: The degraded voltage relay settings at Watts Bar are in accordance

with TS Table 3.3.5-1 which states the values to be as follows: Allowable

Value >_6570 VAC, Trip Setpoint between 6606 VAC and >6593 VAC.In addition, the NRC stated that: E-2

The inspector

reviewed licensee calculation

of record WBN-EEB-MS-TI-06-0029,"Degraded

Voltage Analysis," Rev. 31, which evaluated

motor starting voltages at the beginning

of a design basis loss of coolant accident (LOCA) concurrent

with a degraded grid condition.

This calculation

used the degraded voltage setpoint of 6672 V to analyze post LOCA load motor starting.

This voltage of 6672 VAC used in the calculation

was non-conservative

with respect to the voltage specified

in TS which specified

a maximum value of 6606 VAC.Finally, the NRC concluded:

Contrary to the above, since at least December 2001, the licensee failed to assure that applicable

regulatory

requirements

for undervoltage (degraded)

voltage protection, including

those prescribed

in TS 3.3.5-1, item 2, were correctly

translated

into design calculation, WBN-EEB-MS-TI-06-0029, "Degraded

Voltage Analysis," Revision 31, which evaluated

motor starting voltages at the beginning

of a design basis loss of coolant accident (LOCA) concurrent

with a degraded grid condition.

Further, the process used by the licensee for the selection

of input voltage value in the design calculation

was non-conservative

with respect to the TS. Specifically, the licensee used the input value of 6672 VAC which was higher than the maximum value of 6606 VAC specified

in TS. This did not result in a loss of function of safety-related

loads.With respect to the referenced

requirements

of 10 CFR Part 50, Appendix B, Criterion

Ill,"Design Control," the regulations

state in part: Measures shall be established

to assure that applicable

regulatory

requirements

and the design basis, as defined in § 50.2 and as specified

in the license application, for those structures, systems, and components

to which this appendix applies are correctly translated

into specifications, drawings, procedures, and instructions.

The regulations

in 10 CFR Part 50, Appendix B, Criterion

III create an expectation

that implementing

documents

used at the plant (i.e., specifications, drawings, procedures

and instructions)

should accurately

reflect the design basis for the associated

Structure, System or Component (SSC) and the regulatory

requirements

for the SSC. The NCV confuses the fact that the design basis of the SSC is developed

in part based on regulatory

design requirements

and the fact that the design basis then gives rise to certain operational

limits which may themselves

be established

as regulatory

requirements

via a condition

of the operating

license.For example, the design basis of an SSC may be developed

in part based on applicable

regulatory

requirements

such as those contained

in 10 CFR 50, Appendix A, General Design Criteria (GDC) or other applicable

design oriented sections of 10 CFR Part 50. The GDC in such instance as this example are binding regulatory

requirements

with regard to the design of the facility.In addition to regulatory

requirements

related to the design of the SSC, 10 CFR 50.36 requires the development

of TS which "will be derived from the analyses and evaluation

included in the safety analysis report, and amendments

thereto..." Within the TS, 10 CFR 50.36 requires the inclusion

of limiting conditions

for operation

which are "the lowest functional

capability

or performance

levels of equipment

required for safe operation

of the facility." The analyses from which the TS are derived include analyses which form, or support, the design basis (since 10 CFR 50.34 requires that the final safety analysis report include information

that presents the design bases). The TS are binding regulatory

requirements

insofar as these are imposed as an Appendix of the facility operating

license and they are in addition to the regulatory

requirements

on which the design was based.E-3

The NRC appears to have mischaracterized

the relationship

between the design basis for the degraded voltage protection

system at WBN (which incorporates

design-related

regulatory

requirements)

and the TS Allowable

Values which are derived from the design basis. Simply stated, the NCV could be read to imply that TVA should have used values which are derived from the design basis (i.e., the TS Allowable

Values) as input requirements

to the design basis calculation

-which is itself the basis from which the TS are derived. TVA views this essentially

circular logic as inconsistent

with the purpose of 10 CFR Part 50, Appendix B, Criterion

Ill,"Design Control." Alternatively, the NRC's NCV discussion

may be read to imply that TVA should have used the TS Allowable

Values as input to a portion of the calculation

whose purpose was to confirm that, for circumstances

not linked to specific expected post-accident

conditions

and for stressed grid voltage conditions

not specifically

linked to any particular

failure mode, individual

loads powered from the auxiliary

power system would have sufficient

voltage to start without tripping protective

devices and without causing the degraded voltage protection

system to transfer from the preferred

offsite power system to the onsite AC power system. As discussed

below, it is difficult to understand

the logic of evaluating

the ability to start motors under conditions

in which the expected effect will be to cause degraded voltage relays to dropout and, with some likelihood, cause the Auxiliary

Power System to transfer to the onsite power source.Relationship

of Calculation

WBN-EEB-MS-TI06-0029, Revision 31 to TS 3.3.5 Allowable Values The discussion

in NRC Inspection

Report 05000390/201005

associated

with the NCV refers to the WBN calculation

WBN-EEB-MS-TI06-0029, Revision 31, "Degraded

Voltage Analysis." WBN-EEB-MS-TI06-0029

is a design calculation

and, as demonstrated

below, is related to the TS values referenced

in the NCV in that it provides an input (analytical

limit) to calculations

that specifically

derive the TS values. From the standpoint

of 10 CFR Part 50, Appendix B, Criterion Ill, "Design Control," WBN-EEB-MS-TI06-0029, and related calculations

discussed

below, are the means by which the regulatory

requirements

regarding

the design of the degraded voltage protections

system are translated

into specifications

-in this case, the TS themselves.

TVA first issued WBN-EEB-MS-TI06-0029

in 1992 and the purpose of WBN-EEB-MS-TI06-0029

is stated in Section 1 of Revision 31 of the calculation:

1.1 The purpose of this calculation

is to demonstrate

that the Watts Bar Auxiliary Power System complies with NRC Branch Technical

Position PSB-1 and to establish the basis for the degraded and loss of voltage relay setpoints

and their associated

time delays.1.2. Ensure that the voltage level is adequate to allow required safety electrical

equipment and devices to successfully

complete their safety function.1.3. Ensure that the duration of the degraded voltage at a given voltage level does not result in thermal degradation

or damage of any equipment.

WBN-EEB-MS-TI06-0029

is the design calculation

for the degraded voltage protection

system at WBN. As the design basis calculation, it captures the design related regulatory

basis for the degraded voltage protection

scheme. For degraded voltage protection

design, there are no explicit requirements

in 10 CFR Part 50, nor is there illuminating

guidance in an existing regulatory

guide. Thus, the reference

to NRC Branch Technical

Position (BTP) PSB-1 constitutes

the effective

regulatory

design requirements

for this system. The relationship

between WBN-EEB-MS-TI06-0029, Revision 31 and the TS Table 3.3.5-1 Allowable

Value and E-4

Trip Setpoints

is found in Section 5.1 of the calculation "Second Level Undervoltage (Degraded Voltage) Relay Dropout Setpoint." A lower boundary should be established

for the dropout setting of the degraded voltage relay.The lower boundary should be greater than the minimum safety bus voltage established

below. The nominal setpoint of the dropout setting should be equal to the lower boundary plus all tolerances

from potential

transformer (PT) ratio and burden errors, setpoint drift errors, and any other errors in accordance

with TVA Technical

Instruction

TI-28 (reference

2.13).The minimum safety bus voltage is selected by evaluating

operation

of the auxiliary

power system under steady-state (running)

conditions, with the 6.9kV Shutdown Boards voltages as low as possible while still keeping all connected

safety-related

loads within their rated operating

voltage range (within ANSI C84.1 utilization

voltages, range "B", reference

2.14).5.1.1. The loads evaluated

are safety-related

loads required for Unit I design basis event, safety injection

phase A or B. which would be used in normal operation

and/or initiated

upon an accident signal. Load types considered

are motor loads including

vendor package loads, 120VAC motor control circuits, and MCC 120VAC distribution

panel loads. The acceptance

criteria and means of evaluation

is as follows: 5.1.1.1. The lowest possible voltage at the 6.9kV Shutdown Boards without tripping (actuating)

the Degraded Voltage Relay is 6555 volts. (Sec. 3.9). The voltage at the various 480V class 1E boards is evaluated

at 6555V based on this relay setting at the 6.9kV Shutdown Board and the maximum steady state loading (Normal Operation

loading)conditions

to ensure that the minimum steady-state

running voltage requirements

to distribution

board and connected

equipment

are maintained.

Starting of motors is evaluated at voltage based on the upper reset setpoint operational

limit of the degraded voltage relays. Starting at a lower voltage could result in dropping out the degraded voltage relays and not being able to reset them prior to disconnection

and transfer to the emergency diesel generators.

This approach is consistent

with the guidelines

given in IEEE 741-1997, reference

2. 12.The degraded voltage protection

relay system operates to provide two distinct functions.

One function of the degraded voltage protection

relays is to ensure that the Auxiliary

Power system does reliably transfer from the offsite power supply to the onsite power supply under conditions

which are indicative

of a sustained

degraded voltage condition

on the offsite power supply. The design requirement

to have the Degraded Voltage Relay dropout setting linked to the Minimum Operating

Voltage ensures that the Auxiliary

Power System does not transfer from the offsite power supply to the onsite power supply except under voltage conditions

which are indicative

of a sustained

degraded voltage condition, that is, to ensure it does not prematurely

transfer from an offsite power supply that is sufficiently

reliable to supply safety related loads under normal and accident conditions.

Because the Degraded Voltage Relays are equipment

required for the safe operation

of the plant, values associated

with the Degraded Voltage Relay dropout setting are included in the TS. The TS Table 3.3.5-1 values referred to in the NCV are the 6.9 kV Emergency

Bus Undervoltage (Degraded

Voltage) Bus Undervoltage

Allowable

Value L>6570V) and Trip Setpoints

(> 6593 and <6606V). These values are associated

with the Degraded Voltage Relay dropout. These values do not include the reset setpoint for the Degraded Voltage Relays. The current TS Trip Setpoints

were calculated

in TVA calculation

WBPE2119202001.

The TS voltage values (Allowable

Value and Trip Setpoint)

are unchanged

from the values issued in the TS when the WBN, Unit 1 Operating

License was issued on February 7, 1996.E-5

As illustrated

by the above discussion, from a 10 CFR Part 50, Appendix B, Criterion

Ill, consideration, WBN-EEB-MS-TI06-0029, Revision 31, and related calculation

WBPE2119202001

are the means by which the regulatory

requirements

regarding

the design of the degraded voltage protections

system are translated

into specifications.

Relationship

of TS Table 3.3.5-1 Allowable

Values and Calculation

WBN-EEB-MS-TI06-

0029, Revision 31 Analysis of Motor Starting In the NCV, the NRC stated that TVA: failed to assure that applicable

regulatory

requirements

for undervoltage (degraded)

voltage protection, including

those prescribed

in TS 3.3.5-1, item 2, were correctly translated

into design calculation, WBN-EEB-MS-TI-06-0029, "Degraded

Voltage Analysis," Revision 31, which evaluated

motor starting voltages at the beginning

of a design basis loss of coolant accident (LOCA) concurrent

with a degraded grid condition.

Further, the process used by the licensee for the selection

of input voltage value in the design calculation

was nonconservative

with respect to the TS. Specifically, the licensee used the input value of 6672 VAC which was higher than the maximum value of 6606 VAC specified

in TS. This did not result in a loss of function of safety-related

loads.TVA's position is that, while the TS are regulatory

requirements, they are not design related requirements

and, in the case of the analysis of motor starting capability

in Section 6.2 of WBN-EEB-MS-TI06-0029, use of the TS values as inputs to the design analyses would be inconsistent

with the stated purpose of that analysis.The analysis in Section 6.2 of WBNEEBMSTI060029, Revision 31 provides insight to TVA as to the ability of the Auxiliary

Power System to provide sufficient

starting capacity for safety related motors for circumstances

in which the offsite power supply may be under sustained

degraded voltage conditions (whether post design basis accident or for other, unspecified

circumstances).

The approach to the analysis in Section 6.2 is identified

in Section 5.2 which states: The safety bus voltages associated

with the upper boundary of the reset setting are evaluated

to ensure adequate operation

of the auxiliary

power system under steady state (starting)

conditions

and recovery (running)

voltage conditions.

This portion of the calculation

was added in WBN-EEB-MS-TI06-0029, Revision 30, which was issued in January 2001. The "post LOCA" motor starting analysis referred to in the NCV was a confirmatory

evaluation

performed

over and above the design basis which existed when the NRC had previously

found the degraded voltage protection

scheme in conformance

with PSB-1 (see discussion

of NUREG-0847

and supplements

in Section II). Revision 31 of WBN-EEB-MS-

T106-0029

explicitly

indicates

the reason for not performing

the motor starting confirmatory

calculation

at voltage values similar to those of the degraded voltage setpoint (dropout):

Starting of motors is evaluated

at voltage based on the upper reset setpoint operational

limit of the degraded voltage relays. Starting at a lower voltage could result in dropping out the degraded voltage relays and not being able to reset them prior to disconnection

and transfer to the emergency

diesel generators.

To elaborate, the circumstances

under which the voltages may have degraded so far below the minimum grid operational

voltage are varied. If the bus voltage is degraded in a situation

where E-6

a safety injection

signal and block start of accident loads have caused the voltage to drop below the degraded voltage dropout setpoint (but not below the loss of voltage setpoint)

but then, due to unspecified

failure mechanisms, recover to a level well below 100% nominal, the Degraded Voltage Relay may or may not have reset. Evaluating

motor starting under such a non-mechanistic

scenario (i.e., by evaluating

at a voltage below the relay reset setpoint)

provides very little useful confirmatory

insight into the capability

of the auxiliary

power system. For that reason, TVA elected to use the value 6672 V AC (which bounds the Degraded Voltage Relay reset of 6681 V AC) rather than a lower value, which as stated in the calculation, would likely simply demonstrate

that the Degraded Voltage Relays would dropout.Furthermore, there is no conflict between TVA's minimum starting voltage analysis and Appendix B, Criterion

III because there are no specific requirements

in the NRC regulations

regarding

the method for evaluating

the competing

degraded voltage protection

system requirement

to provide protection

to safety related equipment

under degraded voltage conditions

and to support an onsite and offsite power system that meets the performance

requirements

of GDC-1 7, "Electric

Power Systems." Thus, TVA's design basis for the degraded voltage protection

scheme, including

the methodology

and assumptions

for a minimum starting voltage analysis, is that which is presented

in WBN-EEB-MS-TI06-0029, Revision 31.As a result, TVA's position is that the NRC's assertion

that TVA failed to properly incorporate

TS requirements

into the design calculation (i.e, specifications, instructions, drawings or procedures)

is unjustified.

Ill. Disputing

the NRC's apparent concerns regarding

the adequacy of the WBN current licensing

basis for degraded voltage protection

During the course of the WBN Component

Design Basis Inspection, including

the pre-exit and exit meetings and at a public meeting with the NRC on March 11, 2011, the NRC referred to concerns regarding

various aspects of the current licensing

basis for degraded voltage protection

at WBN. In addition to the NRC concerns regarding

the methodology

for performing

minimum starting voltage analyses discussed

above, the NRC expressed

concerns about the analytical

consideration

given to the installed

automatic

high-speed

Load Tap Changers associated

with the Common Station Service Transformers.

TVA is presenting

an evaluation

of the degraded voltage protection

current licensing

basis to address what appear to be NRC's underlying

concerns.

Reinforcing

TVA's perspective

that the NRC's concerns are fundamentally

grounded in the current licensing

basis was a discussion

provided by the NRC at the 2011 Regulatory

Information

Conference (RIC) on March 9, 2011.At the RIC technical

session on degraded voltage issues, the NRC confirmed

a recent.trend

in enforcement

actions regarding

degraded voltage protection

systems (consistent

with the recently issued draft Regulatory

Issue Summary (RIS) 201 1-XX, "Adequacy

of Station Electrical

Distribution

Systems," dated January 12, 2011). In discussing

the background

for the enforcement

trend, the NRC acknowledged

that, because degraded voltage protection

requirements

are not grounded in typical regulatory

hierarchy, the licensing

basis from plant to plant is quite variable.

The NRC did acknowledge

that understanding

the degraded voltage protection

requirements

and commitments

for any one plant requires a thorough review of the plant specific current licensing

basis. The NRC indicated

that a thorough review of any one plant's current licensing

basis documentation

can be time consuming.

TVA agrees that a thorough review of the current licensing

basis for a specific issue can be resource intensive

in many cases. However, TVA's position is that such a review is warranted in this case in order to establish

the clearest shared understanding

between the NRC and TVA of the complex technical

and regulatory

issues related to the NCV. TVA's analysis of the degraded voltage protection

system licensing

history at WBN is presented

below.E-7

WBN, Unit I Degraded Voltage Protection

Current Licensing

Basis As discussed

in the recently issued draft Regulatory

Issue Summary (RIS) 201 l-XX, "Adequacy of Station Electrical

Distribution

System," dated January 12, 2011, the NRC's regulatory

actions associated

with degraded voltage protection

essentially

began in the wake of the degraded voltage event at Millstone

Station in July 1976. The history of all of the NRC's regulatory

actions between the Millstone

event and the development

of the current WBN degraded voltage protection

licensing

basis in the early 1990's is not presented

here. The draft RIS provides an overview of the early years of generic regulatory

oversight

for this issue, including

reference

to the issuance of Branch Technical

Positions (BTP) of the Standard Review Plan, PSB-1, Revision 0, which was issued in July 1981.Development

of TVA Degraded Voltage Protection

Design Calculations

In the early 1990's, TVA developed

a methodology

for selecting

Degraded Voltage Relay (DVR)setpoints

based on the recommended

guidelines

that were issued as DMEDS 9211-01/HEE, EDS Clearinghouse

Recommendations

and Guidance Concerning

Settings of Second Level Undervoltage

Protection, dated November 20, 1992 (hereafter

referred to as EDS Clearinghouse).

The EDS Clearinghouse

guidance was developed

by the industry in response to NRC issues during Electrical

Distribution

System Functional

Inspections

in the late 1980s and early 1990s. The EDS Clearinghouse

guidance summarized

existing NRC requirements

for degraded voltage protections

as follows: Branch Technical

Position PSB-1 is a principal

source of NRC Staff technical

guidance in this area. The document is included as a "reference" in the NRC Temporary

Instruction

for EDSFIs TI 2515/107, pg. 4. The only NRC regulation

referenced

in PSB-1 is 10 CFR 50, Appendix A, General Design Criteria (GDC) 17, "Electric

Power Systems." However, GDC 17 does not specifically

address degraded grid voltage issues.With regard to motor starting voltage under accident conditions, the EDS Clearinghouse

stated: "Licensees

should be able to establish

adequate terminal voltages of accident loads under auxiliary

system transient

conditions (such as motor starting transients)

without tripping of protective

devices such as overcurrent

relays, thermal overloads, circuit breakers and fuses. We recommend

that licensees

perform analyses to ensure that during worst case motor transients

with bus voltage equivalent

to the minimum switchyard

voltage during anticipated

worst case system operation; (i) the bus voltage will not drop below the dropout setting of the relay during the transient

or (ii) if the bus voltage drops below the dropout setting of the relay during the transient, it will recover above the reset setting of the relay prior to the relay timing out." With regard to proper setting of degraded voltage relay setpoints, specifically, relay dropout setpoints, the EDS Clearinghouse

guidance stated: "When considering

the dropout setting of the relay, we recommend

lower and upper boundaries

be established.

The lower boundary is the value that is equivalent

to the minimum voltage at the safety related buses to ensure adequate downstream

terminal voltage for steady state operation

of accident loads. In our view, transient

conditions

of accident loads need not be considered

to establish

the lower boundary of the relay setting.If the bus is operating

at a voltage level that is at the lower boundary of the dropout setting, then any transients

applied to the bus, such as a motor start, will: a. cause the relay to dropout, b. begin the time delay to separate the safety bus from the grid, E-8

c. where the bus voltage is already below the reset setting of the relay, it will not recover to a sufficient

level to reset the relay following

the motor transient.

Therefore, the bus will separate from the grid, and d. energize the EDGs, initiate load shedding and resequencing

accident loads onto the bus.When establishing

the lower boundary of the dropout setting, we recommend

that the"enveloping

component

of the accident loads be identified.

Once the enveloping

component is identified, the minimum bus voltage to supply adequate terminal voltage to the enveloping

component

for the worst case "steady state" operating

scenario should be calculated.

When the lower boundary for steady state operation

of accident loads has been determined, we recommend

sufficient

margin be added to this value to establish

the lower end of the relays allowable

tolerance

band for technical

specification

purposes." With regard to the factors to be considered

when identifying

the minimum voltage for starting motors, the EDS Clearinghouse

provided the following

recommendations

on this subject: "In our view, transient

conditions

of accident loads need not be considered

to establish the lower boundary of the relay setting. If the bus is operating

at a voltage level that is at the lower boundary of the dropout setting, then any transients

applied to the bus, such as a motor start, will ... cause the relay to dropout...""Licensees

should be able to establish

adequate terminal voltages of accident loads under auxiliary

system transient

conditions (such as motor starting transients)

without tripping of protective

devices ... We recommend

that licensees

perform analyses to ensure that during worst case motor transients

with bus voltage equivalent

to the minimum switchyard

voltage during anticipated

worst case system operation: (i) the bus voltage will not drop below the dropout setting of the relay during the transient

or (ii) if the bus voltage drops below the dropout setting of the relay during the transient, it will recover above the reset setting of the relay prior to the relay timing our." The EDS Clearinghouse

recommended

the lower boundary of the DVR Dropout setting to be calculated

based on: "...the value that is equivalent

to the minimum voltage at the safety related buses to ensure adequate downstream

terminal voltage for steady state operation

of accident loads." TVA applied the recommendations

of the EDS Clearinghouse

by developing

plant specific design calculations.

WBN-EEB-MS-TI06-0029

as the Degraded Voltage Protection

Design Basis For WBN, TVA developed

calculation

WBN-EEB-MS-TI06-0029, Revision 0 which was issued in March 1992. Unlike SQN, TVA's calculation

for degraded voltage analysis for WBN did not reference

the EDS Clearinghouse

guidance as a source document.

Rather, WBN-EEB-MS-

T106-0029, Revision 0 cited NRC Branch Technical

Position (BTP) PSB-1 as a source of design input. Between the issuance of Revision 0 of WBN-EEB-MS-TI06-0029

in March 1992 and the issuance of NRC's NUREG-0847, "Safety Evaluation

Report related to the Operation

of Watts Bar Nuclear Plants, Units 1 and 2," Supplement

20 in February 1996, WBN-EEB-MS-T106-0029

remained the design basis calculation

for the degraded voltage protection

scheme although it was revised from time to time to account for plant design changes during construction.

Of particular

note relative to NCV 05000390/2010005-03, WBN-EEB-MS-TI06-0029, Revision 0 does not contain an explicit evaluation

of single motor starting capability

as currently

exists in Revision 31. The section of WBN-EEB-MS-TI06-0029 (Section 5.2) which states E-9

"The safety bus voltages associated

with the upper boundary of the reset setting are evaluated

to ensure adequate operation

of the auxiliary

power system under steady state (starting)

conditions

and recovery (running)

voltage conditions." was added in Revision 30 of the calculation

issued in January 2001. The motor starting analysis referred to in the NCV was a confirmatory

evaluation

performed

over and above the design basis which existed when the NRC found the degraded voltage protection

scheme in conformance

with PSB-1. However, as listed below, the NRC found the degraded voltage protection

approach at WBN in conformance

with Branch Technical

Position PSB-1.NRC Licensing

Conclusions

Regarding

TVA Degraded Voltage Methodology

As part of the its review of TVA's application

for an operating

license for WBN, the NRC issued NUREG-0847, "Safety Evaluation

Report related to the Operation

of Watts Bar Nuclear Plants, Units 1 and 2," including

numerous supplements.

In NUREG-0847

and supplements, the NRC found TVA's degraded voltage protection

scheme in conformance

with PSB-1: WBN 1982 SER: "...in IEEE Standard 308-1974, which states that preferred

offsite and the standby onsite emergency

power supplies shall not have a common mode failure between them. The positions

that the staff have developed

are being used in the evaluation

of electrical

power designs for operating

plants, and CP and OL applications.

The applicant

was made aware of these positions, which have been incorporated

into SRP Appendix 8A as BTP PSB-1. The applicant

documented

that the Watts Bar design will be modified as shown on FSAR Figure 040.62-1 to meet BTP PSB-1. By letter dated October 9, 1981, the applicant

provided additional

descriptive

information

to support the conclusion

that the Watts Bar design, once modified, will be in conformance

with positions

B-I and B-2 of BTP PSB-1. The staff concludes

that the proposed design meets BTP positions

and is acceptable.

In addition, design implementation

will be verified as part of the site visit/drawing

review. In regard to positions

3 and 4, the applicant

has documented

that the auxiliary

power system meets these positions

and that the analyses will be verified in the preoperational

testing program. This meets the staff positions

and is acceptable, pending verification

of the analyses.

The staff will verify the test results." WBN 1982 SER, SER Supplement

7, dated September

1991: "In the SER, the staff stated that it would verify the adequacy of the applicant's

analysis regarding

compliance

with Branch Technical

Position (BTP) PSB-1 once the preoperational

test was completed.

The staff noted that the preoperational

test has shown that the Watts Bar design conforms with BTP PSB-1 (see Inspection

Report 50-390/84-90, dated February 11, 1985). The staff is still evaluating

the status of this issue and will update the status in a future SSER." WBN 1982 SER, SER Supplement

13, dated April 1994: "In the SER, the staff stated that it would verify the adequacy of the applicant's

analysis regarding

compliance

with BTP PSB-1 once the preoperational

test was completed.

The staff had confirmed

that a preoperational

test had shown that the Watts Bar design conforms with BTP PSB-1 (see Inspection

Report 50-390/84-90, dated February 11, 1985). Hence, Confirmatory

Issue 28 was resolved.

However, due to design changes, the results obtained from the previous test are no longer valid and the applicant

is performing

preoperational

tests again. The staff will review this issue when it inspects the applicant's

preoperational

test program." E-10

WBN 1982 SER, SER Supplement

14, dated December 1994: "The material that follows revises the discussion

in SSER 13.(1) Allowable

Technical

Specification

Limits for the Inverse Time Delay Relay. In SSER 13, the staff stated that Technical

Specifications

should require, for example, that the capability

of the relays not to trip when subjected

to a voltage of 75 percent for 30 seconds be demonstrated.

The staff implied that this had been included in the draft Technical

Specifications.

This statement

was wrong. Instead, the staff required that the setpoints

and allowable

values for the load-shed

and diesel start relays be included in the plant's Technical

Specifications

to resolve the concerns." WBN 1982 SER, SER Supplement

20, dated February 1996: In SSER 13, the staff stated that Confirmatory

Issue 28 was resolved on the basis of a preoperational

test documented

in Inspection

Report 50-390/84-90, dated February 11, 1985. However, the staff stated that the results obtained from that test were no longer valid since TVA was reperforming

the preoperational

tests. The preoperational

test was conducted

by TVA and reviewed by the staff in Inspection

Reports 50-390/95-22 (September

8, 1995) and 50-390/95-77 (December

6, 1995). This update does not change the staff's conclusion

regarding

Confirmatory

Issue 28.Additional

Licensing

Basis Documents

Regarding

WBN Degraded Voltage Protection

WBN License Amendment

36 -2002 Since issuance of the Facility Operating

License in 1996, TVA has obtained only one amendment

to the TS related to the degraded voltage protection

scheme for WBN. The license amendment

is relevant to concerns expressed

by the NRC during the WBN CDBI inspection

and at the March 11, 2011 public meeting on degraded voltage protection

issues. The particular

concern, as best understood

by TVA, relates to the "crediting" of automatic

load tap changers in analyses related to degraded voltage protections

designs. This Enclosure

does not include a detailed technical

discussion

regarding

the appropriate

consideration

for any feature of the non-safety related offsite power system including

automatic, high speed load tap changers.However, it should be noted that to the extent that voltage recovery following

a voltage transient is influenced

by many features of the offsite power system, the performance

of automatic

load tap changers in establishing

Degraded Voltage Relay time delay settings cannot be separated from the performance

of those tap changers in evaluating

dynamic voltage performance

on the distribution

system.By letter dated May 14, 2001, TVA requested

an amendment

to the WBN TS to revise the Trip Setpoint and Allowable

Value for Table 3.3.5-1, Function 2(b), 6.9 kV Emergency

Bus Undervoitage (Degraded

Voltage) -Time Delay, as follows:* The Trip Setpoints

were revised from: > 5.84 sec and < 6.16 sec to> 9.73 sec and <10.27 sec.* The Allowable

Value was revised from > 5.7 sec and < 6.3 sec to > 9.42 sec and <10.49 sec.As reason for the change, TVA stated: E-11

WBN design modification (DCN D-50565-A)

would change the setpoint of the degraded voltage relay timers from a nominal 6 seconds to 10 seconds to relax the offsite power criteria.

The primary purpose of this change is to provide the plant additional

operating margin by allowing additional

time for the automatic

load tap changers (LTCs) on the Common Station Service Transformers

C and D (0-XFMR-200-C/CSST

and 0-XFMR-200-

D/CSST) to compensate

for postulated

degraded voltage conditions

on the WBN 161 kV Off-Site Power Grid.In the application, TVA presented

additional

information

regarding

the analyses of on-site distribution

system performance

that had been conducted

to support the proposed amendment, including

consideration

of the role of the automatic

load tap changers.On January 23, 2002, the NRC issued Amendment

36 to the WBN TS and approved the proposed changes. In the safety evaluation (SE) accompanying

the amendment, the NRC stated: The design modification

would change the setpoint of the degraded voltage relay timers from a nominal 6 seconds to 10 seconds to relax the offsite power criteria.

The primary purpose of this change is to provide the plant additional

operating

margin by allowing additional

time for the automatic

LTCs on the CSSTs. C and D to compensate

for postulated

degraded voltage conditions

on the 161 kV off-site power grid.Recent analysis of the offsite grid indicates

that due to future grid loading projections (within about 2 years), voltage fluctuations

on the grid could unnecessarily

challenge

the EDGs and associated

equipment

if the current time delay settings are maintained.

The longer time delay setpoint would relax the present offsite power criteria by allowing a more severe worst case degraded voltage condition

on the 161 kV grid to be accommodated

by the CSST C and D LTCs. This extended time delay would eliminate

an unnecessary

electrical

transient

associated

with the automatic

transfer from the preferred

offsite power supply to the EDGs when a degraded voltage condition

of less than 10 seconds is experienced.

Consequently, challenges

to equipment

associated

with the actuation

of breakers, shedding of loads, starting of the EDGs, etc., would also be reduced or eliminated.

The analysis was performed

using the Electrical

Transient

Analyzer Program. The software includes the capability

to analyze the electrical

auxiliary

power system for loading, short-circuit

currents, running voltages, and starting voltages.

The calculations

demonstrated

the ability of the offsite power system to start and operate all required loads for a worst case DBE without transferring

to the EDGs. Increasing

the delay time from 6 to 10 seconds will not change the voltage recovery profile. The lower boundary dropout and the upper reset setpoint of the degraded voltage relays remains unchanged.

Analyses have shown that operating

equipment, such as motors, would not be damaged and would accelerate

back to rated speed, thus ensuring their continued

availability

to perform their intended safety function.

Specifically, the analysis demonstrated

that the required safety-related equipment

in operation

at the time a degraded voltage condition

occurred would continue to operate throughout

the 10-second

delay. If the degraded voltage condition cleared during this time period, the voltage would return to nominal levels and be available for equipment

required to perform safety functions.

Calculations

demonstrated

that the automatic

LTCs remain capable of regulating

the 6.9 kV shutdown board voltage within the present voltage relay setpoints.

The LTCs will restore 6.9 kV shutdown board voltage for a safety injection

signal with a simultaneous

worst case grid drop before the degraded E-12

voltage relays actuate to transfer power supply to the EDGs. Engineered

safeguard motors will have sufficient

voltage available

at the terminals

to ensure proper starting and operation, when supplied by offsite power. Maximum loading on transformers, distribution

system cables, and 6900 V and 480 V boards is bounded by current analyses and remains below component

ratings. If the degraded condition

still existed at the end of the 10-second

time period, transfer to the EDGs would occur and the voltage would recover to an acceptable

level. In either case, acceptable

voltage levels would be available

for equipment

to respond in a timely manner if called upon to perform a safety function.IV. Conclusion

As discussed

in Section II of this enclosure, TVA's position is that the NRC's use of 10 CFR Part 50, Appendix B, Criterion

III, Design Control in issuing NCV 50-390/2010005-03

is not consistent

with essential

purpose of that important

regulatory

requirement

and is not consistent

with the facts associated

with TVA's control of the design of the degraded voltage protection

scheme at WBN, Unit 1. Accordingly, TVA denies the subject NCV.As discussed

in Section III of this enclosure, TVA understands

that the NRC is currently

giving additional

focus to degraded voltage protection

issues at nuclear power plants. While the NRC has attempted

to explain its current concerns through numerous vehicles including

through individual

inspection

activities, a limited number of plant specific backfits, and issuance of draft RIS 2011 -XX, the technical

and regulatory

concerns of the NRC remain unclear.To respond to the NRC's expectations

in the NCV that TVA evaluate post LOCA motor starting using the Degraded Voltage Relay dropout value rather than the 6672 V AC currently

in the design, TVA would have to modify the fundamental

design documents

of the facility which constitutes

a change to the facility design. To the extent that such a modification

would be made in response to the NRC's position in the NCV which conflicts

with the NRC's previous position in NUREG-0847

and related supplements

regarding

conformance

of the design to Branch Technical

Position PSB-1, TVA's position is that such a modification

would constitute

a backfit. Accordingly, should the NRC seek to pursue the issues regarding

the adequacy of the WBN degraded voltage protection

system design, TVA requests that the NRC treat the matter in accordance

with the provisions

of 10 CFR 50.109, "Backfitting." TVA does not take any position in this denial of the subject NCV regarding

whether such a backfit would be eligible for the exceptions

to the backfit analysis and documentation

provisions

of 10 CFR 50.109. However, TVA notes that in the draft RIS, the NRC uses language regarding degraded voltage analysis requirements

and limitations

that do not exist in any previous regulatory

requirement

or guidance documents

on this subject and which now directly conflict with NRC reviewed provisions

of the WBN current licensing

basis.E-13