Official Exhibit - NYS000046-00-BD01 - Pre-filed Testimony of David A. Schlissel (Schlissel Pft)
ML12334A518
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 12/13/2011
From: Schlissel D
Schlissel Technical Consulting
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 21536, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01
Download: ML12334A518 (50)


Text

Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 1 UNITED STATES 1 NUCLEAR REGULATORY COMMISSION 2 BEFORE THE ATOMIC SAFETY AND LICENSING BOARD 3-----------------------------------x 4 In re: Docket Nos. 50-247-LR; 50-286-LR 5License Renewal Application Submitted by ASLBP No. 07-858-03-LR-BD01 6Entergy Nuclear Indian Point 2, LLC, DPR-26, DPR-64 7 Entergy Nuclear Indian Point 3, LLC, and 8 Entergy Nuclear Operations, Inc.

December 13, 2011 9-----------------------------------x 10 PREFILED WRITTEN TESTIMONY OF 11 DAVID A. SCHLISSEL 12 REGARDING CONTENTION NYS-37 13 On behalf of the State of New York ("NYS" or "the State"), 14 the Office of the Attorney General hereby submits the following 15 testimony by David A. Schlissel regarding Contention NYS-37.

16Q. Please state your full name.

17A. My name is David A. Schlissel.

18Q. By whom are you employed and what is your position?

19A. I am the President of Schlissel Technical Consulting, 20 Inc. My business address is 45 Horace Road, Belmont, MA 02478.

21Q. Please summarize your educational and professional 22 qualifications.

23 United States Nuclear Regulatory Commission Official Hearing Exhibit In the Matter of

Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3)

ASLBP #:07-858-03-LR-BD01 Docket #:05000247 l 05000286 Exhibit #:

Identified:

Admitted: Withdrawn:

Rejected: Stricken: Other: NYS000046-00-BD01 10/15/2012 10/15/2012 NYS000046 Submitted: December 14, 2011 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 2A. I have served since 1973 as a consultant, expert 1 witness, and attorney on complex management, engineering, and 2 economic issues, primarily in the fields of energy and the 3 environment. I have been retained by regulatory commissions, 4 consumer advocates, publicly-owned utilities, non-utility 5 generators, governmental agencies, and private organizations in 6 more than 35 states to prepare expert analyses on issues related 7 to electric, natural gas, and telephone utilities. I have 8 presented testimony in more than 100 cases before regulatory 9 boards and commissions in 35 states, two federal regulatory 10 agencies, and in state and federal court proceedings.

11 I hold BS and MS degrees in Astronautical Engineering from 12 the Massachusetts Institute of Technology (MIT) and Stanford 13 University, respectively. I also received a Juris Doctor degree 14 from Stanford University School of Law. I also have studied 15 Nuclear Engineering and Project Management at MIT. I am a 16 member of the New York State Bar and the American Nuclear 17 Society. My recent work has involved the evaluation of utility 18 resource planning analyses, the economics of proposed and 19 existing power plants, electric system reliability, and power 20 plant operations and outages. I also have examined the 21 economics of, and the alternatives to, the extension of the 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 3 service lives of operating nuclear power plants. A copy of my 1 current CV is attached as Exh. NYS000050.

2Q. I show you what has been marked as Exhibit NYS000052.

3 Do you recognize that document?

4A. Yes. It is a copy of my expert report entitled Report 5 on the Availability of Replacement Capacity and Energy for 6 Indian Point Units 2 & 3 , dated November 28, 2007 ("2007 Synapse 7 Report")(ML073400205), which was submitted in support of New 8 York State's contention challenging Entergy's Environmental 9 Report (NYS-9, ML073400187). NRC Staff was served a copy of my 10 2007 Synapse Report as attached to NYS-9. The report accurately 11 reflects my analysis and opinions.

12Q. I show you what has been marked as Exh. NYS000053. Do 13 you recognize that document?

14A. Yes. It is a copy of my declaration, dated February 15 27, 2009 ("2009 Schlissel Decl.")(ML090690303), in support of 16 New York State's contention, NYS-33 (later consolidated as NYS-17 9-33) (ML090771328). My declaration commented on and challenged 18 NRC Staff's impact analysis of energy alternatives in the 19 context of the no-action alternative, and provided additional 20 information on New York's energy markets, energy efficiency, 21 energy conservation, renewable energy, facility repowering, and 22 transmission enhancements, relevant to Chapter 8 of the December 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 4 22, 2008 Draft Supplemental Environmental Impact Statement 1 ("DSEIS") prepared by NRC in this proceeding. NRC Staff was 2 served a copy of my 2009 Decl. as attached to NYS-33. The 3 declaration accurately reflects my analysis and opinions.

4Q. I show you what has been marked as Exh. NYS000054. Do 5 you recognize that document?

6A. Yes. It is a copy of my declaration, dated January 7 31, 2011 ("2011 Schlissel Decl.")(ML110680290),which updated my 8 previous report and declaration with additional information on 9 New York's energy markets, energy efficiency, energy 10 conservation, renewable energy, facility repowering, and 11 transmission enhancements, as relevant to the no-action 12 alternative considered by Staff in Chapter 8 of FSEIS prepared 13 by NRC in this proceeding. I prepared this later assessment 14 with the assistance of staff at Synapse Energy Economics, Inc., 15 who worked under my direction and supervision. NRC Staff was 16 served a copy of my 2011 Decl. as attached to NYS-37. The 17 declaration accurately reflects my analysis and opinions.

18Q. What is the purpose of your testimony?

19A. I have been retained by the New York State Office of 20 the Attorney General to provide expert services to the State of 21 New York concerning the proposed relicensing of the two 22 operating reactors located at the Indian Point Nuclear Power 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 5 Station in the Village of Buchanan in Westchester County (Indian 1 Point Unit 2 and Indian Point Unit 3) and NRC's consideration of 2 energy alternatives in the context of the "no-action" 3 alternative (i.e. license denial).

4 The December 3, 2010 Final Supplemental Environmental 5 Impact Statement ("FSEIS") looks at the consequences of the no-6 action alternative to relicensing by relying, in part, on the 7 findings and conclusions in the discussion of alternatives in 8 the FSEIS at FSEIS § 8.3.

See FSEIS § 8.2, p. 8-22. I have 9 also reviewed and analyzed that section of the FSEIS and 10 identified significant deficiencies in its consideration of 11 conservation, renewable energy, purchased electrical power, 12 transmission constraints and the need for power as these relate 13 to the no-action alternative.

14 Q. Have you reviewed materials in preparation for your 15 testimony?

16 A. Yes.

17 Q. What is the source of those materials?

18 A. Many are documents prepared by government agencies, 19 published articles, or documents prepared by Entergy or the 20 utility industry.

21 Q. I show you Exh. NYS000055 through Exh. NYS000096, 22 NYS000111, and NYS000132 through NYS000134. Do you recognize 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 6 these documents?

1 A. Yes. These are true and accurate copies of the 2 documents that I referred to used and/or relied upon in 3 preparing my reports, declarations, and this testimony. In some 4 cases, where the document was extremely long and only a small 5 portion is relevant to my testimony, an excerpt of the document 6 is provided. If it is only an excerpt, that is noted on the 7 cover of the Exhibit.

8 Q. How do these documents relate to the work that you do 9 as an expert in forming opinions such as those contained in this 10 testimony?

11 A. These documents represent the type of information that 12 persons within my field of expertise reasonably rely upon in 13 forming opinions of the type offered in this testimony.

14Q. Please summarize your testimony.

15 A. The FSEIS ignored significant developments that have 16 occurred in New York State's energy markets since the 17 Environmental Report was released in 2007 that make it more 18 likely that New York State can replace Indian Point's generation 19 by 2015 when the units are scheduled to retire, as outlined in 20 my 2007 Synapse Report and subsequent declarations. Instead of 21 confronting this evidence, the FSEIS primarily relied on older 22 studies such as the National Research Council of the National 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 7 Academy of the Sciences Committee on Alternatives to the Indian 1 Point Energy Center for Meeting New York Electric Power Needs 2 (June 2006) ("2006 National Research Council"),Exh. NYS000055, 3 and Indian Point Retirement Options, Replacement Generation, 4 Decommissioning/Spent Fuel Issues and Local Economic/Rate 5 Impacts , prepared by Levitan and Associates, Inc. (June 2005) 6 ("2005 Levitan Report"),Exh. NYS000056,both of which pre-dated 7 the 2008 financial crisis, the subsequent prolonged economic 8 recession, fundamental changes in the natural gas sector, 9 significant decreases in wholesale energy prices, and decreased 10 energy demand and load forecasts for New York State. These 11 reduced energy sales and peak loads will delay and defer the 12 need for the energy and capacity from Indian Point Units 2 and 3 13 if their operating licenses were not renewed and will likewise 14 impact the timing and viability of the no-action energy 15 alternative. Cumulatively, these developments create a more 16 favorable environment for retiring Indian Point Units 2 and 3 at 17 the end of their operating licenses in 2013 and 2015 18 respectively, and for replacing their generation capacity with 19 energy efficiency, repowered generation, purchased electrical 20 power, renewable energy, or some combination thereof, at less 21 environmental impact and cost than considered by the FSEIS.

22 Because NRC Staff did not provide an accurate and meaningful 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 8 impact analysis for these generation alternatives, and did not 1 accurately account for lowered load forecasts and energy prices, 2 and changes in New York's energy markets since the recession, 3 the FSEIS does not give decisionmakers a real sense of the 4 economic and environmental costs and benefits of the no-action 5 alternative.

6Q. Please summarize the conclusions of your November 28, 7 2007 Synapse Report on the Availability of Replacement Capacity 8 and Energy for Indian Point Units 2 & 3, hereafter ("2007 9 Synapse Report").

10 A. My 2007 Synapse Report concluded that the capacity and 11 energy provided by Indian Point Units 2 and 3 can be replaced if 12 the Units are not relicensed. Exh. NYS000052 at pp.10-11. In 13 particular, energy efficiency, renewable resources, the 14 repowering of older generating facilities, transmission 15 upgrades, and new natural gas-fired generating facilities 16 represent viable no-action generation alternatives in the event 17 the units are not relicensed. Substantial reductions in peak 18 demand and energy requirements will be achieved by 2013 under 19 the State's "15x15" Clean Energy Plan.

Id. at pp. 3-6.

20 Significant amounts of new renewable resources will be available 21 as a result of the state's renewable energy portfolio standard 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 9 and other initiatives.

Id. at pp. 7-12. In addition, thousands 1 of megawatts ("MW") of new generating capacity can be provided 2 by the repowering (i.e. rebuilding) of older generating 3 facilities both along the Hudson River and in the downstate area 4 of the state in New York City and on Long Island.

Id. at pp. 5 12-14. At the same time, transmission system upgrades also can 6 increase the amounts of power that can be provided to the 7 downstate region of the state.

Id. at pp. 14-15. Finally, my 8 report concluded there is the potential for the addition of 9 several thousand megawatts of new generating capacity in the 10 Hudson River Valley and in downstate New York.

Id. at pp. 15-1118.12Q. Are the conclusions of your 2007 Synapse Report still 13 valid today?

14 A. Yes. Developments in the nearly four years since that 15 Report was submitted have confirmed and further supported these 16 conclusions. Since 2000, New York has added over 7,800 MW of 17 new generation, nearly 1,300 MW of new transmission, and nearly 18 2,400MW of demand response. Eighty percent of the new 19 generation has been added where demand is the greatest in the 20 New York City, Long Island, and Hudson Valley regions. Exh.

21 NYS000057: NYISO 2010 Summer Outlook at pp. 10-11. Substantial 22 transmission capacity has been added, as discussed below, to 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 10 bring more power to the downstate region from out of state. The 1 total resource capability in the New York Control Area ("NYCA")

2 for 2010 was 43,000 MW (including demand response) which was 3 greater than the 118% of the 2010 peak load.

Id.Cumulatively, 4 these developments create a more favorable environment for 5 retiring Indian Point Units 2 and 3 at the end of their 6 operating licenses in 2013 and 2015 respectively, and for 7 replacing their generation capacity with energy efficiency, 8 purchased electrical power, renewable energy, or some 9 combination thereof, at less environmental impact and cost than 10 assumed by the FSEIS.

11 LOWERED ENERGY AND PEAK DEMAND FORECASTS 12 Q. In your opinion, does the FSEIS accurately portray New 13 York's energy markets, sources of generation, transmission grid 14 conditions, and alternative sources of generation reasonably 15 available to support a no-action alternative to the relicensing 16 of Indian Point?

17 A. No. As noted earlier, the FSEIS primarily relies on 18 studies such as the National Research Council's 2006 report on 19 the alternatives to Indian Point and Levitan's 2005 report on 20 the retirement of Indian Point and the natural gas sector. Both 21 of these studies pre-dated the 2007 financial crisis, the 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 11 subsequent prolonged economic recession, fundamental changes in 1 the natural gas sector, significant decreases in wholesale 2 energy prices, and decreased energy demand and load forecasts.

3 This Board may take judicial notice of the fact that the 4 United States, including New York State, is experiencing a 5 prolonged recession. This recession has led to lower than 6 expected electricity sales and peak loads and reduced 7 projections of future electricity sales and peak loads for an 8 extended period of time and will impact directly the time frame 9 within which the alternatives (e.g., conservation, efficiency, 10 renewables, transmission enhancements, addition of new capacity 11 and the repowering of existing units) would need to be 12 implemented under the no-action alternative. Moreover, New 13 York's projected energy requirements and peak demand have been 14 reduced significantly since my November 2007 Synapse Report was 15 submitted as a result of the ongoing economic recession.

16 As set forth in my 2011 declaration in support of NYS-37, 17 dated January 31, 2011, Exh. NYS000054: 2011 Schlissel Decl

.at 18 p.2, the significant developments that have occurred in New York 19 State's energy markets since the publication of those reports, 20 make it more likely that New York State can replace Indian 21 Point's generation by 2015 when the units are scheduled to 22 retire. NRC's Staff's impact analysis furthermore ignores the 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 12 fact that New York State experienced a 4.1% drop in power demand 1 due to the recession and weak economic recovery. Exh.

2NYS000058:NYISO 2010 RNA Report, p.C-3.

3 This trend is forecast to continue over the period of 4 license renewal. The NYISO recently noted that annual peak 5 demand growth is expected to decline from an average annual rate 6 of 0.68% in the past decade, to 0.47% over the years 2010 to 7 2014 and to decline further to 0.27% over the years 2014 through 8 2018. The New York State Energy Plan further projects that 9 increases in conservation programs, coupled with moderated 10 economic growth, will cause lower expected energy use per capita 11 through 2018. Nonetheless, NRC Staff continue to assume the 12 same need for power assumptions that were contained in Entergy's 13 environmental report, and which formed the basis for Staff's 14 impact analysis contained in the Draft Environmental Impact 15 Statement.

Compare e.g. DSEIS § 8.3, pp. 8-32, 8-56, 8-65 with 16 FSEIS § 8.3, pp. 8-27, 8-39, 8-59.

17Q. Are there any other recent developments in New York 18 State's energy markets and infrastructure that are relevant to 19 the timing, choice, and viability of generation alternatives in 20 the no-action alternative, which are not reflected in the FSEIS?

21 A. Yes. The NYISO's 2009 Annual Report, Energizing the 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 13 Empire State, Exh. NYS000059 at p.12, summarizes the recent and 1 fundamental changes to New York's energy markets as follows:

2 The number of participants in New York's wholesale 3 electricity markets has tripled - from 120 in 2000 to 4 approximately 400 in 2009. The value of transactions 5 in the NYISO markets has grown to more than $75 6 billion. Demand response programs, providing 7 incentives for energy conservation during peak 8 periods, were created and have flourished. They now 9 total over 2,300 megawatts, an amount equal to four 10 medium sized power plants.

11 Market prices reached historic lows in 2009 - 50 12 percent lower than in 2008 -- driven by lower 13 electricity use and drops in the prices of natural gas 14 (one of New York's chief generating fuels).

15 Discounting fluctuations in the cost of fuel used to 16 generate electricity, wholesale electricity costs 17 dropped by 18 percent, representing a $2.2 billion 18 savings on a current annual basis. In the market 19 environment, power producers have invested heavily in 20 new generation and upgrades to existing facilities.

21 Consumers have benefited through prices that are lower 22 than they might have been otherwise.

23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 14 Environmental quality has been enhanced by the 1 addition of more emission-free, renewable power 2 resources and enhanced power plant efficiencies that 3 have contributed to reduced emission rates. For 4 example, the system-wide heat rate of fossil-fueled 5 power plants improved by 21 percent. Power plant 6 emission rates, measured in tons per year for sulfur 7 dioxide, nitrogen oxides, and carbon dioxide, have 8 dropped by double digits since 2000. NYISO markets 9 continued to evolve in 2009 as innovations made New 10 York the first to integrate wind in economic dispatch 11 and adopt pioneering design to enable new energy 12 storage technologies to provide regulation-only 13 service.14 Exh. NYS000059:2009 NYISO Energizing Empire State at p.12 15 Although New York's energy markets have changed 16 considerably since the publication of the licensee's 17 Environmental Report, and Draft SEIS, NRC Staff's core 18 assumptions regarding New York State's technical and economic 19 ability to retire the Indian Point units has remained virtually 20 unchanged.

21 Q. How do NRC Staff's assumptions regarding the project 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 15 area's demand for power, impact Staff's analysis of the 1 generation alternatives that would be available if the Indian 2 Point units were not relicensed?

3 A. Staff's assumptions regarding the project area's demand 4 for power skews the analysis in favor of relicensing by 5 artificially narrowing generation alternatives considered by 6 Staff. For example, NRC Staff reasons that "given that the 7 demand for electricity is increasing and, in the near term, 8 planned new sources within the NYCA are just keeping pace with 9 retirements, the NRC staff does not consider delays in the 10 retirements of existing plants to be a feasible alternative to 11 compensate for the loss of power from IP2 and IP3." FSEIS 12§8.3.4.11.

13 In fact, as set forth in my prior declarations, Exh.

14 NYS000053: 2009 Schlissel Decl. at ¶¶ 5,6,7 and Exh. NYS000054:

15 2011 Schlissel Decl

. at pp. 2-6, the projected future demands 16 for electricity in New York State, and in the zones specifically 17 supplied by Indian Point (New York Control Area ("NYCA")

18 capacity zones H,I,J and K), have sharply decreased as a result 19 of the economic downturn, the State's energy efficiency 20 programs, and strong growth in demand response programs. For 21 example, significant new demand response programs, providing 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 16 incentives for energy conservation during peak periods, were 1 created in New York in recent years and have flourished. They 2 now total over 2,300 megawatts, an amount equal to four medium 3 sized power plants. Exh. NYS000059: NYISO 2009 Annual Report, 4 p. 12. Despite this growth, the FSEIS's impact analysis of 5 conservation does not consider New York's demand response 6 programs.7 In addition, the short and long-term outlook for supplies 8 and prices of natural gas in electricity generation continue to 9 be favorable, supporting new natural gas capacity in New York 10 State as well as the repowering of existing generating capacity 11 with more efficient natural gas-fired technology. Exh.

12 NYS000054: 2011 Schlissel Decl. pp 15-17. For this reason, new 13 generating units fueled by natural gas as well as the repowering 14 of existing units would be a viable alternative to a portion of 15 the capacity and energy generation provided by the two Indian 16 Point Units. In fact, new natural gas-fired capacity is under-17 construction or is being proposed to come on-line in New York 18 State in the near to mid-term and repowering projects also are 19 being undertaken that are not reflected in the FSEIS. Thus, 20 Staff's conclusion that the no-action alternative has the 21 smallest effect, but "would necessitate additional actions to 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 17 replace generation capacity (whether with newly constructed 1 power plants or purchased power) and/or to institute 2 conservation" FSEIS § 9.2., p. 9-7, is not supported by a 3 critical analysis of how much additional capacity and/or 4 conservation would be necessary in a no-action alternative, 5 given current market conditions.

6 Furthermore, Staff's selection of reasonable examples of 7 combinations [of replacement capacity sources] does not "address 8 comments received, on-going State level programs and resource 9 availability." FSEIS § 8.3. p. 8-28. Contrary to this 10 assertion, the FSEIS ignored my reports and declarations which 11 suggest that the Indian Point units can be retired at the end of 12 their operating licenses at less cost and with less 13 environmental impact, than assumed in the ER and DSEIS.

14 ENERGY EFFICIENCY 15Q. What did the 2007 Synapse Report conclude regarding 16 energy efficiency as a potential replacement for the power 17 supplied by Indian Point, and what was the basis for that 18 conclusion?

19 A. My 2007 Synapse Report found that substantial 20 reductions in peak demand and energy requirements will be 21 achieved both in New York State as a whole and in Downstate New 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 18 York by 2013 under the state's "15 by 15" Clean Energy Plan and 1 that these reductions would more than offset the expected annual 2 generation and peak generation output from Indian Point. Exh.

3 NYS000052 at pp.3-6.

4 For example, my 2007 Synapse Report concluded that the "15 5 by 15" plan would reduce statewide energy consumption by 6 approximately 27,000 gigawatt hours ("GWh") by 2015.

Id. at 7 p.3. This would be approximately 11,600 GWh more than the 8 expected annual generation from both Indian Point Units after 9 2013.10 The 2007 Synapse Report also calculated that by 2013 the 11 Statewide cumulative summer peak capacity savings from the "15 12 by 15" plan would be 5,950 to 6,311 MW, or approximately triple 13 the cumulative capacity of both Indian Point Units.

Id. at p.5.14 The Downstate New York regional summer peak capacity savings 15 would be approximately 2,586 MW in 2013 and 3,321 MW by 2015.

16 Id. at p. 6. Consequently, the 15 percent energy reduction (and 17 associated reduction in peak demands) under the "15 by 15" Clean 18 Energy Plan would more than offset both the energy and the 19 capacity from both Indian Point units and would eliminate any 20 need to extend the licenses of the two units in 2013 and 2016.

21 Moreover, the 15 percent reduction in statewide energy 22 consumption anticipated under the "15 by 15" plan would not 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 19 represent all of the economical potential energy efficiency that 1 has been identified in New York State. For example, a 2 presentation by Philip Mosenthal of Optimal Energy, Inc has 3 projected that there is 61,506 GWh of economical potential 4 energy efficiency in New York State. Exh. NYS000060: 2007 5 Optimal Slide No. 9.

6Q. Based on the latest energy efficiency studies for New 7 York State, and in particular, the energy efficiency gains 8 expected in NYCA capacity zones H, I, J and K, and the summer 9 energy peak demand anticipated in those same zones, do you still 10 conclude that a 15% energy reduction in 2015 statewide would 11 more than offset the need to extend the license of the Two 12 Indian Point units in 2013 and 2015?

13A. Yes. Subsequent to the submittal of my November 2007 14 Synapse Report, Governor Spitzer's goal of a 15 percent decrease 15 in energy demand from forecasted levels by the year 2015 (more 16 than 27,000 GWh) was formalized by the New York PSC's Order 17 Establishing Energy Efficiency Portfolio Standard and Approving 18 Programs, adopted on June 23, 2008. Exh. NYS000061: June 2008 19 NYS PSC Order. The EEPS Order gives funding to specific energy 20 efficiency programs, and energy savings coming directly from 21 those programs are estimated to be approximately 7,639 GWh in 22 2015, Exh. NYS000062: 2009 NYS Energy Efficiency Assessment, p.

23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 20 29, which is slightly less than half of what is needed to 1 replace the Indian Point generating Units.

2 Moreover, according to a draft energy efficiency potential 3 study done in 2008 by Optimal Energy, which updated an earlier 4 2003 energy efficiency potential study, New York State's 5 achievable energy efficiency potential through 2015 is 26,000 6 GWh. Exh. NYS000063: 2008 Optimal Report, p.6. Of this 26,000 7 GWh of achievable potential, Optimal Energy concludes that 38%

8 (9,824 GWh) of the savings can be realized in New York City, 14%

9 (3,603 GWh) in Long Island, and the remaining 48% (12,573 GWh) 10 in the rest of New York State.

Id.11 This 26,000 GWh represents a 14% decrease from the 2015 12 forecast of electricity demand, which is slightly short of the 13"15 by 15" goal. This estimated efficiency potential only takes 14 into account policies that are currently in effect, however.

15 Optimal Energy also estimates that policies related to improved 16 building codes and appliance standards which have passed but not 17 yet taken effect, or for which implementation is highly likely 18 in the next ten years, can provide additional electricity 19 savings of 11,000 GWh, or an extra 5.7% from forecasted demand.

20 Id. at p. 5. If the same percentages apply to the regional 21 savings values stated above, New York City's (Zone J) total 22 potential would increase to just over 14,000 GWh and Long 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 21 Island's (Zone K) total potential would increase to more than 1 5,000 GWh. Along with the additional potential in Zones H and I, 2 if achieved, energy efficiency reductions in New York City and 3 Long Island would more than offset the energy generated each 4 year at Indian Point Units 2 and 3. Exh. NYS000054: 2011 5 Schlissel Decl. at p.8.

6 Nevertheless, as quantified by Optimal Energy, there is 7 sufficient energy efficiency potential in the state to meet the 8 state's goal of "15 by 15." New York has a long history of 9 investments in energy savings, first through the implementation 10 of the Systems Benefit Charge program ("SBC"), and now through 11 the EEPS. New York's efforts at energy efficiency to date 12 should indicate that the state can be expected to achieve full 13 implementation of the 2015 goal. Annual energy efficiency 14 savings to date, achieved largely from the SBC program (that was 15 initiated in 1998), already have reached more than 4,000 GWh per 16 year.Id. Savings from EEPS funded programs are expected to be 17 an additional 7,639 GWh in 2015.

Id. It is reasonable to 18 expect that some of these savings have and will occur in areas 19 of New York that are served by the Indian Point Units. Long 20 Island Power Authority ("LIPA") and New York Power 21 Authority("NYPA") can be expected to contribute another 3,000 22 GWh in energy savings by the year 2015 - most, if not all of 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 22 which will be achieved in those areas of the state that 1 currently rely on Indian Point.

Id. Together, all of these 2 energy efficiency savings can offset a significant portion, if 3 not all of, the electric generation that would be generated by 4 Indian Point Units 2 and 3 if the units were denied license 5 renewal.6 In addition, NYISO Demand Response programs, which enlist 7 electricity customers to conserve power in response to system 8 conditions, are effectively reducing the need for additional 9 capacity. One of the NYISO Demand Response programs, Special 10 Case Resources ("SCR"), has registered 2,084 MW as of 2009. Exh.

11 NYS000064: 2009-2018 NYISO Reliability Summary, pp. 5 - 6.

12Q. Did the FSEIS provide a critical analysis of your 13 expert report regarding the economic and technical energy 14 efficiency potential identified for zones H, I, J and K as a 15 source of replacement generation for the Indian Point units?

16A. No, it did not. There is no mention of any of the 17 expert reports or declarations I prepared on generation 18 alternatives to relicensing Indian Point in support of New York 19 State's contentions and comments in this proceeding. The FSEIS 20 provides no critical analysis of my study of the economic and 21 technical energy efficiency potential available in the event the 22 Indian Point Units are not relicensed.

23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 23 Q. Have you identified any errors in NRC Staff's impact 1 analysis of energy conservation provided in the December 2010 2 Final Environmental Impact Statement ("FSEIS") for Indian Point?

3 A. Yes. The NRC's analysis of energy efficiency as an 4 alternative to relicensing Indian Point is: (a) not site 5 specific; (b) methodologically unclear; (c) incomplete; and (d) 6 fails to provide a factual basis for its conclusions for the 7 following reasons:

8 (a) NRC staff generically adopt the findings of its Shearon 9 Harris assessment(NUREG-1437, Supplement 33 dated August 2008), 10 Exh. NYS000065, which considered utility based conservation as 11 an alternative to license renewal for a 900 MW pressurized water 12 nuclear reactor, located 20 miles outside of Raleigh, North 13 Carolina in a regulated electricity market. The Shearon Harris 14 facility shares little, if any, similarity to the substantially 15 larger, deregulated, Indian Point facilities. The analysis 16 provided in Shearon Harris is based primarily on data from a 17 single 2006 study of North Carolina's energy markets, contains 18 no analysis of New York's energy markets, and provides no 19 analysis of utility based conservation programs in New York; 20 (b) NRC staff also adopt the findings of its Three Mile 21 Island ("TMI") Unit 1 assessment(NUREG-1437, Supplement 37 dated 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 24 June 2009),Exh. NYS000066, which considered Pennsylvania's 1 Alternative Energy Portfolio Standard ("AEPS") as an alternative 2 to license renewal for a 800 MW pressured water reactor. This 3 analysis relies on a single study, conducted in 2004 of 4 Pennsylvania's energy efficiency potential (Pletka). The TMI 5 analysis makes no reference to New York State, Indian Point, or 6 the energy efficiency potential relevant or forecasted to be 7 available in the zones currently receiving power from Indian 8Point.

9 (c) The NRC Indian Point FSEIS is incomplete because it 10 provides no factual support that the analysis contained in 11 NUREG-1437 of North Carolina's regulated program is relevant or 12 substantially similar, to any such program in New York State's 13 deregulated energy market. Likewise, the NRC Indian Point FSEIS 14 analysis of energy conservation/efficiency is incomplete because 15 it provides no factual support that the energy efficiency 16 programs put in place by the State of Pennsylvania in 2004 are 17 relevant or applicable to the energy efficiency programs already 18 in place, or likely to be in place, and available to replace the 19power generated by Indian Point.

20 (d) NRC Staff's conclusion that its proposed energy 21 conservation/ energy efficiency "alternative" will result in 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 25"SMALL to MODERATE socioeconomic impacts, which will not be 1 offset by conservation", FSEIS § 8.3.3., p. 8-43, lacks factual 2 support and/or further analysis. For example, no attempt is 3 made to assess the potential for job creation and/or economic 4 development presented by NRC's energy efficiency alternative, 5 which may vary substantially depending on the specific nature of 6 the efficiency / conservation programs considered.

7 Because the NRC Indian Point FSEIS does not define what 8 energy efficiency and/or energy conservation programs it 9 anticipates will be available to replace the power generated by 10 Indian Point, it is impossible to determine site specific 11 impacts for, the reasonableness of, or the viability of NRC's 12 energy efficiency/conservation no-action alternative. Here 13 again, NRC's conclusion that license denial would require 14"additional actions . . . to institute conservation programs,"

15 FSEIS § 9.2. p. 9-7, is unsupported by a critical analysis of 16 the amount of additional investment in conservation and/or 17 energy efficiency that would be necessary, given New York 18 State's already substantial progress in this area, should the 19 Indian Point units be retired at the end of their current 20 operating licenses.

21 RENEWABLE GENERATION 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 26 Q. What did your 2007 Synapse Report conclude with 1 respect to renewable energy sources as a potential source of 2 replacement power for the Indian Point units?

3 A. My 2007 Synapse Report found that significant amounts 4 of new renewable resources will be available as a result of New 5 York State's renewable energy portfolio standard and other 6 initiatives and that these renewable resources can replace a 7 significant amount of the energy and capacity from Indian Point.

8 Exh. NYS000052 at pp. 7-12.

9 Q. Do you think this conclusion is still valid today?

10 A. Yes. My 2009 and 2011 declarations provided 11 additional information that shows that New York State can 12 replace a significant amount of the capacity and energy supplied 13 by Indian Point with renewable generation if the units are not 14 relicensed. Exh. NYS000053 2009 Schlissel Decl. at ¶¶ 4, 8, and 15 Exh. NYS000054 2011 Schlissel Decl. pp. 9-12.

16 For example, in his 2009 State of the State address, former 17 Governor Paterson proposed to increase the state's goal for 18 energy efficiency and renewable resources by announcing New 19 York's "45 by 15" clean energy goal. Exh. NYS000067: 2009 20 Paterson Address. This goal challenged the State to meet 45 21 percent of its electricity needs by 2015 through increased 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 27 energy efficiency and renewable energy and was subsequently 1 formally adopted by the New York State PSC in 2010. The State's 2 current energy goal is to reduce electricity end-use by 15 3 percent, primarily through the expansion of energy efficiency 4 activities, while simultaneously meeting 30 percent of the 5 State's electricity supply needs through renewable resources.

6 New York State is already well on its way towards achieving 7 these goals, as shown in Table 1 of my 2011 declaration, Exh.

8 NYS000054: 2011 Schlissel Decl

. p.10, which shows the amounts of 9 electricity generated from in-state renewable resources in each 10 year between 2001 and 2009 increasing from 16% to over 23% in 11 that time period. These totals only include in-state resources 12 and do not include imported renewable energy, out-of-state 13 renewable energy attributes (Renewable Energy Certificates 14 ("RECs") acquired through green purchasing in the voluntary 15 market), or customer-sited renewable generation, all of which 16 contribute toward meeting the State's RPS requirements.

17 Furthermore, the 2009 New York State Energy Plan Renewable 18 Energy Assessment presents evidence that the technical/practical 19 potential for renewable resources is forecast at more than 20 141,000 GWh by the year 2018, compared to the approximately 21 15,000 GWh generated by Indian Point. Exh. NYS000068: 2009 NYS 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 28 REA, p.7. As set forth in greater detail in my 2011 1 declaration, there is 7,935 MW (rated summer capacity) of 2 renewable capacity awaiting approval for interconnection with 3 the grid between 2010 and 2017. Exh. NYS000054 at p. 12. The 4 majority of the proposed resources are for wind generation with 5 over 2,000 MW of wind requesting to be online in 2011, and 6 another 1,500 MW of wind from the Lake Eerie and LIPA/Con Edison 7 offshore wind projects requesting to come online in 2015.

Id.8 Additional wind projects totaling more than 500 MW have also 9 requested to be interconnected in 2016 and 2017.

Id.10 Historically, a large portion of the requests that enter the 11 Interconnection Queue are not actually constructed. However, 12 even if only 20% of the proposed projects come online, there 13 would still be a 1,587 MW increase in wind generating units by 14 2017, in addition to the substantial amount of wind generation 15 already in place in New York State.

16Q. Did the FSEIS provide a critical analysis of your 17 expert report regarding the economic and technical potential of 18 renewable generation as a source of no-action replacement 19 generation for the Indian Point units?

20 A. No, it did not. There is no mention of any of the 21 expert reports or declarations I prepared on renewable 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 29 generation in support of New York State's contentions and 1 comments in this proceeding. The FSEIS provides no critical 2 analysis of my study of the economic and technical potential of 3 New York State's renewable sector to provide replacement 4 capacity in the event the Indian Point Units are not relicensed.

5 Moreover, Staff's analysis of New York's renewable sector 6 is neither consistent nor thorough. For example, Staff relies 7 on the Department of Energy / Energy Information 8 Administration's (DOE/EIA) "Annual Energy Outlook 2010 with 9 Projections to 2035" Department of Energy (DOE/EIA 2010) report 10 to "help select reasonable alternatives to license renewal,"

11 FSEIS § 8.3. pp. 8-28, l. 37. NRC Staff adopts DOE/EIA's 12 conclusion that coal generation is forecast to decline, but 13 ignores the DOE/EIA's conclusion that renewable generation is 14 forecast to sharply increase over the time period relevant to 15 license renewal.

16Q. Do you agree with the following statements from the 17 Final Environmental Impact Statement (FSEIS):

18 Wind power by itself is not suitable for large base-19 load capacity. As discussed in Section 8.3.1 of the 20 GEIS [NRC 1996], wind has a high degree of 21 intermittency and average annual capacity factors for 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 30 wind plants are relatively low (less than 30%). Wind 1 power in conjunction with energy storage mechanisms, 2 might serve as a means of providing base-load power.

3 However, current energy storage technologies are too 4 expensive for wind power to serve as a large base-load 5 generator.

FSEIS §8.3.4.1., p. 8-44.

6 A. No. Many of the tired old concerns and arguments 7 about the possible impacts of large wind generation on the 8 transmission grid have been shown to be exaggerated or unfounded 9 by a growing body of research studies and empirical 10 understanding gained from the installation and operation of 11 large amounts of wind generation in the United States. Instead, 12 it is increasingly accepted that when combined with other energy 13 resources, wind can produce energy in patterns comparable to a 14 baseload generation facility. At the same time, the effects of 15 short term wind variability can be mitigated by a building 16 larger number of wind turbines and by siting the wind turbines 17 in different geographic locations. As a result, there is no 18 evidence that any replacement capacity for Indian Point would 19 need to be a fully dispatchable facility and Staff did not offer 20 any response to my evidence to the contrary.

21 Indeed, Staff's rejection of wind as a replacement for 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 31 capacity and energy from Indian Point also is contradicted by 1 the fact that the electricity grid in New York State already has 2 a large number of fully dispatchable facilities. In addition, 3 in its 2009 Annual Report, NYISO states that it has implemented 4 a state-of-the-art wind forecasting system, and "became the 5 first grid operator to integrate wind-generated electricity into 6 economic dispatch." Exh. NYS000059 2009: NYISO Energizing 7 Annual Report, p. 6. It is planning for more wind energy by 8 considering new operating procedures, market rules, storage 9 technologies, and transmission reinforcements that would 10 increase "the amount of wind that could be reliably integrated 11 into the bulk power system and delivered to the load." Exh.

12 NYS000069: 2008 Integration of Wind, p. 5-1. In fact, the most 13 recent NYISO wind study concluded that "the addition of up to 14 8,000 MW of wind generation to the New York power system will 15 have no adverse reliability impact (and) would supply in excess 16 of 10% of the system's energy requirement." Exh. NYS000070:

17 2010 NYISO Report Growing Wind Study, p. iv.

18 Furthermore, the FSEIS fails to acknowledge that energy 19 storage projects also could play a significant role in the 20 development of other renewable resources, as they would provide 21 a way to help manage the intermittency of other types of 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 32 resources. One example of this type of resource that has 1 already begun construction is the Beacon Power flywheel energy 2 storage plant in Stephentown, New York. A flywheel energy 3 storage plant works by accelerating a rotor (flywheel) to a very 4 high speed and maintaining the energy in the system as 5 rotational energy. This project has a capacity of 20 MW and is 6 expected to be the first full-scale flywheel system in the US 7 that provides grid regulation services after it is completed in 8 2012. Exh. NYS000059: NYISO 2009 Energizing Annual Report, 9 p.6.10 Contrary to substantial evidence in the record, the FSEIS 11 erroneously concludes, without any critical analysis and with 12 only bare assertions regarding NRC Staff's beliefs, that there 13 are too many obstacles to implementing sufficient wind power or 14 other renewable energy sources such that these sources could not 15 provide anything more than 600 MW to replace either or both IP 16 units. See FSEIS § 8.3.5. 8-59 to 8-61. This Staff belief is 17 obviously arbitrary since the FSEIS, itself, contradicts it by 18 forecasting a total amount of 1,765MW combined renewable 19 generation to be online and available by 2015. FSEIS § 8.3.5.

20 8-61.21 In my opinion, NRC Staff's decision to limit the amount of 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 33 wind generation considered to a maximum of 600 MW is 1 unsupported, relies on obsolete arguments against wind power, 2 and disregards the conclusions of my 2007 Synapse Report and my 3 2011 Declaration that wind power can reduce the need for the 4 capacity from the Indian Point units and can provide low cost 5 energy to New Yorkers. Furthermore, I note that the FSEIS 6 emphasizes the negative environmental impacts of wind, while 7 discounting its positive environmental benefits.

8 Q. Please identify the deficiencies, if any, in the 9 FSEIS's analysis of solar energy's potential as a source of 10 replacement power for Indian Point Units 2 and 3 in combination 11 with other generation sources if the units were retired in 2015?

12 A. The FSEIS cites the 2006 National Research Council 13 study estimate that solar photovoltaics ("PV") can generate 325 14 MW in the New York City Area ("NYCA") by 2015 if PV costs 15 decline and there is a long-term commitment to expand New York's 16 PV program. FSEIS § 8.3.4.1. However, NRC Staff dismissed 17 solar PV from consideration as an alternative to license 18 renewal, with no analysis of my November 2007 report on the 19 availability of replacement capacity, which suggested continued 20 growth in New York's solar sector.

21 Q. Please identify the deficiencies, if any, in the 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 34 FSEIS's analysis of combined heat and power ("CHP")'s potential 1 as a source of replacement power for Indian Point Units 2 and 3 2 in combination with other generation sources if the units were 3 retired in 2015?

4 A. NRC Staff's sole rationale for dismissing CHP from 5 consideration as a source of replacement capacity, is to assert 6"that the current IP2 and IP3 are only used to produce 7 electrical power, and do not supply heat to any offsite users.

8 Combined heat and power, then, fulfills a need not currently met 9 by IP2 and IP3, and is not a direct alternative to IP2 and IP3 10 license renewal." FSEIS § 8.3, p. 8-49, lines 11-13. This 11 statement is wrong in two respects. First, the electrical 12 portion of CHP is of course a potential replacement for IP 13 power. Secondly, CHP heat may substitute for heat that is 14 produced electrically or may free up natural gas as an 15 alternative to electricity for other purposes.

16 RENEWABLE ENERGY & ENERGY EFFICIENCY AS A COMBINED ALTERNATIVE 17 Q. What did the 2007 Synapse Report conclude with respect 18 to the technical and economic potential of energy efficiency and 19 renewable energy as a combined source of no-action replacement 20 power for Indian Point Units 2 and 3?

21 A. My 2007 Synapse Report concluded that energy 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 35 efficiency and renewable resources together have sufficient 1 technical and economic potential to replace the approximately 2 2000 MW of capacity from Indian Point Units 2 and 3. Exh.

3 NYS000052 at p. 10.

4 Q. In your opinion, was it reasonable for NRC Staff to 5 dismiss renewable generation and energy efficiency as a combined 6 no-action alternative to replace the power from Indian Point 7Units 2 and 3 if the units were retired in 2015?

8 A. No, in my opinion, it was not reasonable. NRC Staff's 9 decision to exclude renewable generation and energy efficiency 10 as a combined source of replacement power for Indian Point Units 11 2 and 3 is unsupported by current studies on New York's 12 renewable generation sector, energy efficiency, conservation and 13 demand side management programs, and does not provide a critical 14 analysis of my 2007 Synapse Report and subsequent declarations 15 which concluded that there is sufficient technical potential for 16 renewable energy and energy efficiency in combination to 17 displace the need for Indian Point Units 2 and 3 by 2015. Exh.

18 NYS000052: 2007 Synapse Report at p. 10.

19 PURCHASED ELECTRICAL POWER & TRANSMISSION ENHANCEMENTS 20Q. What did your 2007 Synapse Report conclude with 21 respect to transmission system enhancements and upgrades as a 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 36 potential source of replacement power for Indian Point Units 2 1 and 3 if the units were retired in 2015?

2 A. My 2007 Synapse Report found that transmission system 3 enhancements could be part of the portfolio of options for 4 replacing the capacity and energy from Indian Point Units 2 and 5 3. Such enhancements and upgrades could increase the capability 6 to import power into the Hudson River Valley and Downstate New 7 York from New England, Upstate New York, or the PJM system to 8 the south. Exh. NYS000052: 2007 Synapse Report at pp. 14-15.

9 Q. What developments, if any, have occurred in the status 10 of the downstate electricity grid since 2007 that are relevant 11 to the retirement of Indian Point that were not included in the 12 FSEIS's consideration of no-action alternative?

13 A. Since I submitted my November 2007 Synapse Report, 14 developers in New York have been actively licensing and building 15 upgrades and enhancements to the transmission system. One 16 project that was referenced in the November 2007 Synapse Report 17 as being "proposed" has actually come online. The three Linden 18 Variable Frequency Transformers began operating at the Linden, 19 New Jersey cogeneration facility on December 8, 2009 and have 20 the capability to feed up to 315 MW of electricity into New York 21 City from the New Jersey power system. These transformers are 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 37 helping to stabilize NYC's power grid, increase reliability, and 1 reduce the need for new capacity inside the city. Exh.

2 NYS000071: 2009 Smart Press Release.

3 A number of other transmission projects also have been 4 approved or proposed since November 2007 that are not reflected 5 in the FSEIS's analysis of the no-action alternative. For 6 example, the Hudson Transmission Partners line ("HTP"), 7 mentioned as "proposed" in the November 2007 Synapse Report, was 8 approved by the NY PSC on September 8, 2010. Exh. NYS000072:

9 2010 NYSPSC Order Press Release. This 345 kV line will connect 10 PJM to midtown Manhattan, running between the Bergen Substation 11 in Ridgefield, New Jersey and terminating at Consolidated Edison 12 substations. It is expected to initially provide 320 MW of firm 13 capacity from PJM to New York City, with the potential to 14 provide 660 MW of firm capacity if necessary investments are 15 made to upgrade PJM facilities. In the Order approving this 16 line, the NY PSC stated that the HTP facility "will assist in 17 maintaining system reliability in the event that one or both of 18 the Indian Point plants close." Exh. NYS000111: Sept. 15, 2010 19 NYS PSC Order at p.44. The FSEIS did not consider the HTP line 20 in its impact analysis of the no-action alternative at all.

21 Other new transmission proposals to import power into the 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 38 New York City zone that have been proposed or approved since my 1 November 2007 Synapse Report was completed include the Cross 2 Hudson Cable and the Champlain-Hudson Power Express ("CHPE")

3 line. The Cross Hudson Cable is a 345 kV alternating current 4 line, and will run for 8 miles between the Bergen Switchyard in 5 Ridgefield, New Jersey, owned by PSEG, and the West 49th Street 6 substation in Manhattan, owned by Consolidated Edison. The most 7 recent project updates for the Cross Hudson Cable include a 8 transmission import capability of 700 MW and a projected online 9 date of summer 2013. Exh. NYS000073: 2010 Cavallo Press 10Release. The CHPE line would connect the US-Canadian 11 border with a converter station that will be built in Yonkers, 12 New York and would supply 1,000 MW of new wind and hydro 13 electricity now being targeted for development in Canada into 14 the New York City zone. Modeling performed by London Economics 15 International, and submitted to the NY PSC, assumes in the 16 Baseline scenario that the CHPE line would operate at a 90%

17 capacity factor and deliver 7,640 GWh of renewable generation 18 into New York annually. The CHPE line is expected to be 19operational by 2015. Exh. NYS000074:2010 LEI Study, p.14. The 20 electricity brought into New York from the CHPE line alone would 21 represent almost half of the generation that can be expected 22 from the Indian Point Units in the future.

23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 39 Combined, these new transmission projects would have the 1 capability to import more than two thousand MW of capacity into 2 the New York City zone. When combined with electric generation 3 imported into downstate New York over other transmission 4 projects, a significant amount, if not all, of the capacity and 5 energy from Indian Point Units 2 and 3 could be replaced if the 6 units were denied license renewal.

7Q. Did the FSEIS provide a critical analysis of your 8 expert report regarding the potential of imported electrical 9 power and transmission line enhancements to replace the 10 generation capacity of the Indian Point units in the event the 11 units are not relicensed?

12 A. No, it did not. There is no mention of any of the 13 expert reports or declarations I prepared on generation and 14 energy issues in support of New York State's contentions and 15 comments in this proceeding. The FSEIS provides no critical 16 analysis of my assessment of New York State's transmission grid 17 and its current and future ability to support additional 18 purchased electrical power as replacement capacity in the event 19 the Indian Point Units are relicensed.

20 Q. Do you believe that the FSEIS provides an accurate 21 environmental impact analysis of purchased electrical power as a 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 40 source of replacement capacity if the Indian Point units are not 1 relicensed?

2 A. No. In fact the FSEIS does not provide an 3 environmental impact analysis for purchased electrical power.

4 The FSEIS only provides a general discussion of the potential 5 environmental impacts of two large-scale "illustrative projects" 6 (New York Regional Interconnect ("NYRI") and CHPE. A rational 7 analysis of the potential for purchased electrical power 8 alternative to license renewal should account for the recently 9 approved HTP line and Linden transmission projects that I 10 identified in my 2007 Synapse Report, Exh. NYS000052: 2007 11 Synapse Report at p. 14, as both of these projects increase 12 transmission capacity into the zones currently supplied by 13 Indian Point.

14 In addition, the NRC's analysis of purchased electrical 15 power in the FSEIS relied on inaccurate information because it 16 states that "as of November 10, 2010 the New York Regional 17 Interconnection is still seeking the approval of the New York 18 State Public Service Commission (NYPSC)" to build a major 19 transmission project. FSEIS § 8.3.2., p. 8-40. In fact, on 20 April 21, 2009 the New York State Public Service Commission 21 recognized and approved NYRI's application to formally withdraw 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 41 its petition for a certificate under Article VII of the Public 1 Service Law. The PSC granted NYRI's withdrawal request, with 2 prejudice, and dismissed the application. Exh. NYS000075: April 3 2009 NYS PSC Correspondence. Furthermore, NRC Staff declined to 4 evaluate the impacts of NYRI and CHPEI "in the absence of any 5 specific route information." FSEIS § 8.3.2. p. 8-41. In fact, 6 the proposed route for NYRI was publicly available at the NYSPSC 7 prior to NYRI's withdrawal from consideration, and specific 8 route maps for CHPEI were available on the Department of 9 Energy's website for the project prior to the issuance of the 10 FSEIS and public scoping for the project's EIS was in process 11 throughout 2010. Exh. NYS000076: DOE CHPEI.

12 NEW OR REPOWERED GENERATING FACILITIES 13 Q. Do new natural gas-fired generating facilities 14 represent a potential source of replacement power for Indian 15 Point Units 2 and 3 if the units were retired?

16 A. Yes. New natural gas-fired capacity is under-17 construction or is being proposed to come online in New York 18 State in near to mid-term. For example, the NYISO 2010 RNA 19 includes two new generating plants in Zone J (New York City) in 20 2011 that were not included in previous Reliability Needs 21 Assessments - the 513 MW Bayonne Energy Plant and the 550 MW 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 42 Astoria Energy II plant. Exh. NYS000059: NYISO 2010 RNA, pp. i, 1 17. The Astoria Energy II plant, a new 550 MW unit in Queens, 2 began operations in early July 2011. Of the approved or 3 proposed projects that I listed in my November 2007 Synapse 4 Report, the Bowline Unit 3 and Arthur Kill projects have been 5 withdrawn. The Empire Generating Project is listed as an 6 existing generator in the NYISO's 2011 Load and Capacity Report 7 with an in service date of September 2010. The Spagnoli Road 8 Energy Center is listed in the Interconnection Queue with an 9 online date of 2013.

Id. at p. 4. Because the FSEIS did not 10 provide a critical analysis of the amount of new capacity that 11 is already scheduled to be on line prior to the retirement of 12 the first Indian Point unit in 2013, it may well overestimate 13 the economic and environmental costs of additional replacement 14 capacity in the event the Indian Point units are not relicensed.

15 Q. Does the repowering of older existing generating 16 facilities also represent a potential source of replacement 17 capacity and energy if the Indian Point Units were retired?

18 A. Yes. My 2007 Synapse Report concluded that repowering 19 existing older generating facilities located on the Hudson River 20 between Albany and New York City or on Long Island with new 21 combined cycle technology could add additional generating 22 capacity to replace Indian Point at the same time that it would 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 43 provide significant economic and environmental benefits. Exh.

1 NYS000052: 2007 Synapse Report at pp. 12-14.

2 Q. Did the FSEIS provide a critical analysis of your 3 conclusion that repowering existing older generating facilities 4 located on the Hudson River between Albany and New York City or 5 on Long Island with new combined cycle technology could add 6 additional generating capacity to replace Indian Point at the 7 same time that it would provide significant economic and 8 environmental benefits?

9 A. No, it did not.

10 Q. Based on developments in New York's energy markets 11 since 2007, do you still believe that repowering existing power 12 plants with combined cycle technology could add additional 13 generation capacity to replace Indian Point at the same time 14 that it would provided significant economic and environmental 15 benefits?16 A. Yes. Repowering of existing older, less efficient 17 generating units with new combined cycle technology could add 18 hundreds to thousands of MW of efficient new capacity.

19 For example, the Astoria Repowering Project also is being 20 undertaken in Zone J by Astoria Gas Turbine Power LLC, a 21 subsidiary of NRG Energy Inc. Exh. NYS000077: 2008 Astoria 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 44 Scoping. The Astoria facility is currently 600 MW, made up of 1 31 simple-cycle peaking units, and the repowering would covert 2 the peaking facility to more efficient combined-cycle (CC) 3 generating units in two Phases. Phase 1 would replace seven of 4 the peaking turbines with two 260 MW CC units, which are 5 projected to be operational in 2013. Phase 2 would replace the 6 remaining 24 peaking turbines with an additional two CC turbines 7 of 260 MW each. The repowered units will have a combined 8 capacity of 1,040 MW, for a net addition of 440 MW. Id.

9 Upgrading to combined cycle technology would also mean that the 10 repowered units will have the capability to generate 11 significantly more energy (in GWh) than the existing combustion 12 turbines. The NYISO 2010 Reliability Needs Assessment shows a 13 projected online date for these projects of June 2012. Exh.

14 NYS000058: NYISO 2010 RNA at p.4.

15 Q. Is it reasonable to project that there would be ample 16 supplies of reasonably priced natural gas to burn as fuel in 17 these new or repowered generating facilities?

18 A. Yes. The short and long-term outlooks for natural gas 19 use in electricity generation continue to be favorable, 20 supporting new natural gas capacity in New York State as well as 21 the repowering of existing generating capacity with natural gas 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 45 turbines. As a result of an existing and expected future supply 1 glut, current and projected prices of natural gas have been 2 significantly reduced. Exh. NYS000078: 2009 Little Gypsy Unit 3 3 Report, pp. 6-8. This has led to what many other utilities, 4 such as the Entergy Corporation, and an increasing number of gas 5 and electric industry sources, consider a structural change in 6 the natural gas market. Id

.7 Until very recently, natural gas prices were expected to 8 increase substantially in future years. The decline in natural 9 gas prices since the summer of 2008 reflects, in part, a 10 reduction in demand resulting from the downturn in the U.S.

11 economy. The Interconnection Queue in New York State includes 12 some 4,500 MW of potential natural gas-fired generation. It is 13 unlikely that all of these units will be built. However, if 14 only 25 percent of the proposed capacity in the Queue actually 15 is built, that would be mean the addition of 1,125 MW of new 16 gas-fired capacity in New York State within the next five years.

17 For these reasons, new generating units fueled by natural gas as 18 well as the repowering of existing units would be a viable 19 alternative to a portion of the capacity and energy generation 20 provided by the two Indian Point Units in the event they are 21 denied license renewal.

22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 46 Q. Please identify errors, if any, in NRC Staff's impact 1 analysis of repowered power plants.

2 A. In Section 8.3.1. (Natural Gas Combined Cycle) of the 3 FSEIS, NRC Staff assumed, with no supporting analysis of 4 specific impacts, that the environmental impacts of a natural 5 gas combined cycle plant "would be essentially the same for a 6 repowered facility as for a facility constructed at Indian 7 Point." FSEIS § 8.3.1, p. 8-29. In fact, as outlined in my 8 2007 Synapse Report, repowered plants have unique and compelling 9 environmental impacts and cost advantages, which were not 10 considered by NRC Staff. For example, the location of the plant 11 is relevant to project cost, transmission congestion, 12 reliability, and socio-economic impacts. Exh. NYS000052: 2007 13 Synapse Report at p.12-13. Thus, the FSEIS may well overstate 14 the environmental and economic costs of replacing Indian Point's 15 capacity with repowered facilities in the event the units are 16 denied license renewal.

17 Q. In your opinion, does the NRC's impact analysis for 18 Indian Point accurately represent current market conditions as 19 relevant to replacement capacity in the no-action alternative?

20 A. No. NRC's impact analysis for Indian Point fails to 21 accurately represent the current availability of alternative 22 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 47 sources of generation available to state energy planners in the 1 event the Indian Point units are not relicensed because it:

2 (1) ignores the impact of the recession on short and long 3 term energy and demand forecasts, and the impacts of reduced 4 energy and load demands on the timing and choice of energy 5 alternatives; 6 (2) bases its analysis of natural gas-fired combined-cycle 7 (NGCC) generation on a single study (Levitan 2005) that predates 8 significant structural changes in the natural gas sector, as 9 outlined above, that directly impact the viability of plant 10 repowering, plant retirement and new gas-fired generation in New 11 York State; 12 (3) continues to rely primarily on economic data and 13 studies that pre-date the recession and the implementation of 14 aggressive state-wide policies and programs to significantly 15 increase energy efficiency, conservation, and renewables 16 throughout the state, in general, and in the zones currently 17 receiving power from Indian Point, in particular; 18 (4) fails to recognize significant new developments since 19 2007 in New York State's transmission grid system that directly 20 impact and increase New York State's capacity to import 21 electrical power and utilize off-site renewable generation as 22 alternatives to the power supplied by Indian Point; 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 48 (5) does not account for the impact of the federal 1 stimulus program, American Recovery and Reinvestment Act of 2 2009("ARRA") and state incentives since 2007 that significantly 3 support the expansion of energy efficiency programs and 4 renewable electricity generation in New York State and which 5 increase the viability and effectiveness of those generation 6 alternatives.

7 (6) unreasonably fails to examine the present reasonable 8 viability of energy conservation and renewable generation as a 9 combined alternative to Indian Point given the current forecasts 10 for New York State's renewable sector and energy efficiency /

11 conservation programs.

12 The NRC's impact analysis for Indian Point relies 13 substantially on obsolete information and did not attempt to 14 address the substance of my expert report and declarations, 15 setting forth current market developments that substantially 16 increase New York State's ability to retire the Indian Point 17 units in 2015, and to replace their power with generation 18 sources that have less environmental impact, such as energy 19 efficiency and demand side management, purchased electrical 20 power, renewable generation, or some combination thereof.

21 Because NRC Staff did not provide an accurate and 22 meaningful impact analysis for these alternatives, and did not 23 Pre-filed Written Testimony of David A. Schlissel Contention NYS-37 49 accurately account for lowered load forecasts and energy prices, 1 and changes in New York's energy markets since the recession, 2 the FSEIS gives decisionmakers no real sense of the economic and 3 environmental costs and benefits of relicensing the units or 4 retiring the units.

5Q. Does this conclude your testimony?

6A. Yes.

7 I have reviewed all the exhibit referenced herein. True 8 and accurate copies are attached.

9